Irrigation Project

Summer 2012 Maintenance at Emirates Golf Club




![]()
Irrigation Project





The maintenance team at Emirates Golf Club took on some extensive projects this summer. The main project was the installation of the new irrigation system on the Majlis Golf Course. This included upgrades to the Faldo Mainlines and a full replacement on the Majlis system.

Large excavation of mainline trenching

Two discharge lines one for each course out of the new pump station

Double mainline piping for Majlis and Faldo supply


























Spray out area to be extended

Lower mound and bring in growing medium

Sprig planting




back surround and lay sand on green edge








Left of 3rd grown in
Short mown extesion fairway to approach
Short mown around bunkers at 3rd green
Run off down left of 3rd green




Drill and Fill
Close up of Drill holes Using plywood to turn on extensions
Mowing area clean following drill




Debris being removed
1st green recovery after first week
Close up of graden following 2 passes After two weeks begun to core




One further pass with Graden
Heavy topdress of green Surfaces after 8 weeks
Recovery at 4 weeks




Scarification on 18th fairway
Debris from 6th fairway
Debris from 9th fairway
Removal of debris with blowers




Second direction with Graden 2nd fairway after second pass Additional Graden work on the 3rd 1st fairway following works then scalped

Topdressing on 6th fairway

Topdressing on 3rd fairway

Heavy topdress of all fairways

With the irrigation install you will experience having more consistent surfaces throughout the year. From the club’s perspective, our ability to manage this valuable resource is now phenomenal and we are better equipped to manage our daily output on all surfaces.

The greens extensions bring the greens back to their original design, create additional pin positions and improve the playability of the golf course by giving the golfer additional opportunities in how to approach the hole. Encroachment on the edges was becoming an issue and we now have a clean and pure stand of Tiff Eagle throughout the greens.

Our aerification programmess were sever and have greatly enhanced the playing surfaces. We have very true greens surfaces that have remained firm and the fairways have been significantly improved by the removal of unwanted material allowing us a better opportunity to produce a firmer, faster golf course for all to enjoy.

A special thank you to the Emirates Golf Club members and guests for their patience this summer in allowing us to carry out these works. We hope you enjoy the golf course!
The maintenance team is led by Course Superintendent, Craig Haldane and his two assistants, Luke Partridge and Remi Milana with a great team of course maintenance crew, without whom this project would never have been completed on time and within the operational budget.
Thank you