The town of Eden Bay owns and maintains a fleet of vehicles. You are a systems analyst reporting to Dawn, the town’s IT manager. Eden Bay, a medium-sized municipality, has experienced rapid growth, leading to increased demand for town services. Currently, the town owns 90 vehicles, including police cars, sanitation trucks, fire trucks, and other municipal vehicles. The maintenance budget has risen sharply over recent years, prompting discussions on whether to continue internal maintenance or outsource to private firms.

Following a preliminary investigation into a new information system aimed at reducing costs and improving maintenance efficiency, Dawn has decided to proceed. She has requested assistance in preparing a budget proposal for the next Town Council meeting. The proposal development process involves several tasks with specific durations and dependencies:

Double-check cost and benefit data (3 days).

Send an email to the Town Council requesting the proposal be placed on the agenda (1 day).

Develop the proposal, including all necessary documents and charts (5 days).

Print copies of handout material for the meeting (2 days).

Develop a PowerPoint presentation (5 days).

Conduct a rehearsal for the Council meeting (2 days).

Assist Dawn in delivering the presentation during the meeting (1 day).

The tasks start simultaneously with initial coordination. Tasks such as emailing the council and developing the proposal are performed in parallel after the initial data validation. Printing handouts and developing the presentation also occur concurrently once the proposal is ready. Rehearsal can only be performed after both the presentation and the handouts are complete. The final aid, helping Dawn deliver the presentation, depends on the rehearsal being completed.

Task List with Durations

Double-check cost and benefit data – 3 days

Send email to Town Council for agenda placement – 1 day

Develop project proposal (documents and charts) – 5 days

Print handout material – 2 days

Develop PowerPoint presentation – 5 days

Conduct rehearsal for Council meeting – 2 days

Assist Dawn with delivering the presentation – 1 day

Analysis of Dependencies and Critical Path

Analysis indicates that the email to the council and the proposal development happen in parallel following data verification. Printing handouts and preparing the presentation are dependent on the completion of the proposal. Rehearsal depends on both the presentation and handouts being ready. The final presentation delivery depends on the rehearsal’s completion. These dependencies are typical in project scheduling and determine the project timeline and critical path.

Project Network (PERT Chart)

The PERT (Program Evaluation and Review Technique) chart can be visualized as follows:

Start → Data verification (3 days)

Parallel tasks after initial step:

Send email (1 day)

Develop proposal (5 days)

After proposal completion (after 5 days):

Print handouts (2 days)

Develop presentation (5 days)

After both handouts and presentation are complete (7 or 10 days depending on sequence):

Rehearsal (2 days)

Final delivery assistance (1 day), only after rehearsals

The critical path is identified as the sequence of tasks with the longest duration, dictating the minimum project completion time. In this case, the sequence involving developing the proposal (5 days), developing the presentation (5 days), and rehearsing (2 days) forms the primary critical path, totaling 12 days, assuming no overlaps reduce the overall duration.

Understanding dependencies and the critical path allows project managers to allocate resources effectively, monitor progress, and ensure timely completion of the budget proposal to facilitate informed decision-making by the Town Council.

Conclusion

This project exemplifies typical project management processes, including task listing, dependency analysis, and critical path identification. Effective scheduling ensures that preparation for the Town Council meeting proceeds smoothly with minimum delays, ultimately supporting strategic decision-making regarding the maintenance of Eden Bay’s fleet vehicles and potential transition to outsourcing. As the project progresses, regular monitoring and adjustments are essential, especially considering the dependencies identified, to meet the ambitious timeline and project goals.

References

Kerzner, H. (2017). *Project Management: A Systems Approach to Planning, Scheduling, and Controlling.* John Wiley & Sons.

Schwalbe, K. (2020). *Managing Project Risks.* Springer.

Leach, L. P. (2014). *Critical Chain Project Management.* Artech House.

Paul D. et al. (2020). *Effective Project Scheduling and Control.* CRC Press.