OCTOBER 2026 2026 FPRA PROGRAMS & ACTIVITIES SUMMARY
Table of Contents Streetscape Beautification
Youth Banner Art Showcase
01
Infrastructure Improvements
02-06
Mural Program
07 - 08
Grant Programs
09-10
Jetty Park West Depot Drive IAvenue D Reconstruction ndian River Drive Corridor Delaware Ave & 33rd Street Jaycee Park Improvement/Mural
St. Andrew’s Episcopal Academy Sunrise City Elevators
Commerical Facade Commercial Sign
Wayfinding
11
On Demand Transportation
12
Community Policing
Gateway Signs
Master Plans Lincoln Park
Freebee
Downtown Jetty Park North 25th Street
13
14 - 17
STREETLIGHT POLE BANNER PROGRAM
Youth Banner Art Showcase
The FPRA Youth Banner Art Showcase installation is nearing completion, with the majority of the banners now installed throughout the Peacock Arts District. The banners feature artwork submitted by local students and showcase the creativity and talent of Fort Pierce youth while enhancing the visual identity of the district. Staff experienced a brief delay while awaiting replacement banner arms for several damaged poles. Once the remaining banners are installed, staff plans to issue a press release highlighting the Youth Banner Art Showcase, including information about the program and the locations where the students’ artwork can be viewed throughout the district.
PAGE 1 | OCTOBER 2026
PARKING LOT IMPROVEMENTS Jetty Park West
The Boundary and Topographic Survey has been completed and reviewed by City staff. The design team is currently finalizing the project layout and advancing the design toward a complete plan set. A preliminary layout has also been provided for review, and the project continues to progress on schedule.
Depot Drive The FPRA Board and City Commission have approved the funding agreement and authorized engineering services for the Depot Drive Parking Lot Improvement Project. The survey has been completed, and the project is currently advancing through the 60% design phase. Improvements will enhance parking, lighting, drainage, landscaping, and the overall visitor experience in downtown Fort Pierce. Following staff review of the 60% design plans, final bid plans will be due within 30 days.
PAGE 2 | OCTOBER 2026
INFRASTRUCTURE IMPROVEMENTS Avenue D Reconstruction
Concrete work continues along western Avenue D, while milling and resurfacing is underway from S. 13th Street to U.S. 1. Work is expected to continue for 2–3 weeks, followed by the stamped asphalt crosswalks. The project remains on schedule for completion before Thanksgiving.
PAGE 3 | OCTOBER 2026
INFRASTRUCTURE IMPROVEMENTS Indian River Drive: Seaway Drive to Avenue A
Current construction activities include storm drainage improvements, electrical utility relocations, curb and gutter installation, sidewalk construction, brick paver crosswalk installation, and construction of pervious paver parking areas. Final project completion is anticipated in Spring 2027.
Pervious Paver Parking Area
Sidewalk Formboard at Veteran’s Park
Storm Drainage Installation
PAGE 4 | OCTOBER 2026
Pervious Paver Parking Base
Brick Paver Crosswalk
INFRASTRUCTURE IMPROVEMENTS Delaware Ave. & 33rd St. Intersection Improvements Utility relocations have been completed, and drainage improvements are substantially complete, with only a few remaining items to be addressed. Layout work for the curb and sidewalk is currently underway. Once the curb and sidewalk improvements are completed, the remaining asphalt work will begin, followed by installation of the pedestrian signals.
PAGE 5 | OCTOBER 2026
JAYCEE PARK IMPROVEMENT The Jaycee Park Improvement Project continues to move forward following approval of the necessary agreements by the City Commission and FPRA Board. The project includes the replacement of eight (8) pavilion roofs and installation of a sail shade structure over the playground. The mural on the FPUA water tank has also been completed. Staff is now working with the vendors to begin the permitting process, finalize project plans, and coordinate construction schedules for the upcoming improvements.
PAGE 6 | OCTOBER 2026
MURAL PROGRAM The FPRA recently issued a Call for Artists for the St. Andrew’s Episcopal Academy Mural Project. Staff received approximately 40 artist submissions in response to the call. Staff plans to present the submissions to the CRA Advisory Committee for evaluation and review. Following the evaluation process, the recommended artist will be presented to the FPRA Board at its November meeting for approval.
PAGE 7 | OCTOBER 2026
SUNRISE CENTER ELEVATORS The FPRA issued a Call for Artists for the Sunrise Center Parking Garage Elevator Project. The project includes the development of graphic artwork for the interior elevator cabs, as well as murals for the exterior elevator areas on each floor of the parking garage. The Call for Artists generated significant interest, with staff receiving nearly 100 submissions. An evaluation team is scheduled to meet on October 15, 2026, to review and evaluate the artist submissions. Following the evaluation process, the recommended artist(s) will be presented to the FPRA Board for approval.
CITY HALL
PAGE 8 | OCTOBER 2026
GRANT PROGRAMS Commercial Facade
The FPRA’s Commercial Façade Grant Program continues to support property and business owners in making exterior improvements that enhance the appearance of commercial properties throughout the District. Several previously awarded projects are moving forward, demonstrating the program’s continued impact on the District’s commercial corridors. The project pictured below, located at 1109 Delaware Avenue, is currently underway and will contribute to the ongoing revitalization and improvement of the surrounding area.
1109 Delaware Ave
BEFORE
PAGE 9 | OCTOBER 2026
IN PROGRESS
GRANT PROGRAMS Commercial Sign
The FPRA is continuing to accept applications for the Commercial Façade Sign Program! This program provides reimbursable grants of up to $5,000 per property to help existing businesses upgrade outdated signage with modern, visually appealing designs. These improvements not only beautify the community but also increase business visibility, helping to attract new customers and strengthen brand identity. Eligible applicants must be businesses located within the FPRA District. The program is currently open and actively accepting applications, reflecting strong interest and engagement from local property owners. Visit our website at choosefortpierce.com
APPLY NOW
NOW ACCEPTING APPLICATIONS
PAGE 10 | OCTOBER 2026
GATEWAY SIGNS Comprehensive Sign Program
The Gateway Sign Project continues to move forward. All required permits and approvals have been received for the gateway sign locations. The contractor, Don Bell Signs, is currently coordinating the project schedule and plans to begin installation of the gateway signs during November 2026.
State Rd 5, South Midway Road FDOT APRROVED State Rd 5, South of the North Causeway Bridge FDOT APRROVED Okeechobee Road at the I-95 interchange FDOT APRROVED Orange Avenue west of Jenkins Road FDOT APRROVED
PAGE 11 | OCTOBER 2026
LINCOLN PARK
Master Plan
A Work-in-Progress presentation for the Lincoln Park Master Plan was presented at the September 15 FPRA Board meeting. The Work-in-Progress incorporated public input gathered through community engagement exercises and workshops and included a zoning and mapping analysis of the community. The Lincoln Park Master Plan is slated to be presented at the November 10 FPRA Board meeting.
PAGE 12 | OCTOBER 2026
FREEBEE The Freebee program continues to be a strong mobility resource for the community, providing convenient, no-cost transportation throughout the year. A total of 4,408 rides were completed during the month of September, serving 5,624 passengers. The majority of riders requested trips through the Freebee mobile app, with 3,678 rides booked via the app. Usage remained highest among ages 35-50, accounting for 35.1% of all riders, followed closely by ages 21-34 at 34.9%. These trends reflect the program’s appeal to workingage adults and reinforce Freebee’s role in supporting daily travel, access to destinations, and overall connectivity within the community. FREEBEE RIDERSHIP
PASSENGERS & RIDES EACH MONTH Passengers
Rides
7,000 6,000 5,000 4,000 3,000 2,000 1,000 0
March 2026
April 2026
PAGE 13 | OCTOBER 2026
May 2026
June 2026
July 2026
August 2026 September 2026
COMMUNITY POLICING DOWNTOWN, JETTY & NORTH 25TH
Primary Focus: Maintaining a visible and proactive security presence throughout key redevelopment areas by providing patrols, addressing suspicious activity and community concerns, supporting traffic and public safety, and helping maintain a safe environment for residents, businesses, and visitors.
HOURS OF PATROL DOWNTOWN
JETTY PARK
F ri d a y s 6 :3 0 P M – 2 :3 0 A M S a t u rd a y s 8 :0 0 A M – 2 :0 0 P M 3 :0 0 P M – 9 :0 0 P M 9 :0 0 P M – 3 :0 0 A M Sundays 8 :0 0 A M – 1 2 :0 0 P M
F ri d a y s 7 :0 0 P M – 1 :0 0 A M S a t u rd a y s 7 :0 0 P M – 2 :0 0 A M Sundays 8 :0 0 P M – 1 2 :0 0 A M
PAGE 14 | OCTOBER 2026
NORTH 25 T H STREET Wednesdays 1 1 :0 0 P M – 2 :0 0 A M
F ri d a y s 9 :0 0 P M – 2 :0 0 A M S a t u rd a y s 1 0 :0 0 P M – 2 :0 0 A M Sundays 6 :0 0 P M – 1 1 :0 0 P M
COMMUNITY POLICING DOWNTOWN, JETTY & NORTH 25TH
CALLS FOR SERVICE Downtown
Jetty
North 25th St.
80
60
40
20
0
Aug 2026
*Note the updates provided in this section are one month behind to allow ample time for data collection and reporting.
PAGE 15 | OCTOBER 2026
SCHOOL RESOURCE OFFICERS
SRO Markeis Washington - Dan McCarty Middle School
Officer Washington participated in the tunnel of hope welcome back to Dan McCarty Middle School Campus on August 14, 2026. Dan McCarty Middle School participated in a fire drill as required by Department of Education with that assistance of Officer Washington. During the month of August Officer Washington attended two school events Jersey Day and Sunshine Day. As Officer Washington keeps demonstrating her skills and ability to build connections with her students, she continues to safeguard Dan McCarty Middle School. Officer Washington also continues to support her school by assisting school staff with lunchroom monitoring to prevent altercations and makes sure her students arrive home safe by partnering with her school admin and assisting during dismissal with bus riders, student walkers and parent pick up. 2026-2027 School year is starting to shape up to be a safe and fun year at Dan McCarty Middle School with the assistance of Fort Pierce Officer Washington.
PAGE 16 | OCTOBER 2026
SCHOOL RESOURCE OFFICERS SRO Markeis Washington and SRO Jorge Goz
As the Fort Pierce Police Department continues to strengthen its School Resource Officer (SRO) Unit, officers participated in Back-to-School Training on August 6, 2026, alongside the St. Lucie County Sheriff’s Office and Port St. Lucie Police Department. Training included updates to Florida school laws, mental health resources, school security procedures, and coordination among SROs and School Resource Deputies throughout St. Lucie County. During August, SROs also completed Active Aggressor Response Training at Samuel Gaines Academy K–8 and participated in their respective school open house events. These collaborative efforts strengthen partnerships among local law enforcement agencies and support the safety of students, staff, families, and visitors throughout St. Lucie County.
SRO Jorge Goz - Chester A. Moore Academy of Success K-8 Chester A. Moore has successfully transitioned from an elementary school to a Kindergarten through 8th Grade (K–8) campus, with Officer Goz and the Fort Pierce Police Department now supporting both elementary and middle school students. Officer Goz continues to maintain an active presence on campus, participating in the Tunnel of Hope welcome-back event, required fire drills, and the school’s Glow Party recognizing students for meeting school expectations. Officer Goz also serves on the school’s Attendance Committee, assisting with attendance concerns, connecting families with resources, and conducting welfare checks when appropriate. During August, he completed four investigations, including two school threat assessments, helping maintain a safe campus without disruption to school operations. PAGE 17 | OCTOBER 2026
CONTACT US fpra@cityoffortpierce.com 100 North US Hwy. 1 Fort Pierce, FL 34950 www.choosefortpierce.com