Skip to main content

Utah 26 December 22, 2019

Page 1

UTAH STATE EDITION

A Supplement to:

®

December 22 2019 Vol. III • No. 26

“The Nation’s Best Read Construction Newspaper… Founded in 1957.” Your Utah Connection – Debbie Hansen – 1-702-239-0348 – dhansen@cegltd.com

SLC $4 Billion Airport Construction Enters Final Stage Salt Lake City International Airport photo

Salt Lake City International Airport photo

At a cost of approximately $4 billion, construction crews in Utah are working on the first new hub airport to be built in the nation in the 21st Century. Seen here is the elevated roadway bent cap concrete pour.

By Cindy Riley CEG CORRESPONDENT

At a cost of approximately $4 billion, construction crews in Utah are working on the first new hub airport to be built in the nation in the 21st Century. The Salt Lake City International Airport (SLC) Redevelopment Project calls for replacing three aging terminals with one large, central terminal and two linear concourses connected by a passenger tunnel. It is the largest public service project ever built in Utah. “The current facilities were built in the early 1960s for 10 million passengers,” said Salt Lake City Department of Airports

Service

Executive Director Bill Wyatt. “In 2018, SLC recorded more than 26 million passengers. There is congestion curbside, in the gate hold areas and on the airfield. SLC has grown into a hub airport, and is Delta’s fourth largest hub in terms of annual seats,

and their third fastest growing hub.” In addition, the existing facility does not meet seismic standards, while the new airport will meet or exceed them. It’s also being built to today’s security needs, with efforts underway to achieve LEED Gold certifica-

“SLC is currently compiling a master plan that will address the growth of the airport for the next 20 years.”

Bill Wyatt

Salt Lake City Department of Airports

tion. Wyatt noted that the facility is being built to accommodate future demands. “This design will allow the airport to build additional concourses to the north when needed. SLC is currently compiling a master plan that will address the growth of the airport for the next 20 years.” Wyatt also said travelers are not being significantly affected by the work taking place. “The construction of the first phase of The New SLC has had little impact on passengers. Except for minor road changes into and out of the airport, passengers have not been negatively impacted. Passengers will experisee SLC page 4

Specializing in New, Used & Rebuilt Replacement Parts

• Undercarriage Parts • Field Service • Equipment Sales • Attachments • Full Service Shop • Hydraulic Cylinder Repair • New and Used Parts • Track Repair • Teeth & Edges We Buy Salvage Equipment Alternative to the dealer for all makes & models

Utah Track & Welding Service & Sales

801-972-8939

6382 West 2100 South, Salt Lake City, Utah 84128 • www.utahtrackandwelding.com • sam@utahtrackandwelding.com

Sales


Page 2 • December 22, 2019 • www.constructionequipmentguide.com • Utah State Supplement • Construction Equipment Guide

UTTAH AH

Salt Lake City 801-972-3660

Myton 435-216-7777

St. George 435-986-1000

NEV VADA ADA

Las Vegas 702-399-1004

Elko 775-753-7557

Reno 775-356-1334

WYOMING

Casper 307-223-4660

Gillette 307-682-1445

Rock Springs 307-686-1300

Winnemucca 775-753-7557


Construction Equipment Guide • Utah State Supplement • www.constructionequipmentguide.com • December 22, 2019 • Page 3

NO HA HASSLES SS ES. NO H HIDDE IDDEN COSTS O S. NO O KIDDIN KID NG.

UTAH SALT LT LAKE L CITY Y 4343 Century Dr. Salt Lake City, UTT 84123 Phone: 801-262-5761 Fax: 801-262-5780

SPRINGVILLE 1350 South 2000 West Springville, UT 84663 Phone: 801-794-1463 Fax: 801-794-1414

LOGAN 453 North 1000 West Logan, UT 84321 Phone: 435-752-1533 Fax: 435-752-5722

All rights reserved. CASE is a trademark registered in the United States and many other countries, owned by or licensed to CNH Industrial N.V., its subsidiaries bsidiaries or affiliates.

CED DAR CITY 4822 North N Main Street Ceddar City, UT 84720 Phoone: 435-586-4406 Faxx: 435-586-2362 Email: del.maxedon@centuryeq.com


Page 4 • December 22, 2019 • www.constructionequipmentguide.com • Utah State Supplement • Construction Equipment Guide

Tight Labor Market Could Prove Challenging for SLC Job SLC from page 1

ence more changes in the second phase, when the airport uses a combination of new gates with existing gates, as we tear down existing facilities and build the concourses to the east.” Early in the planning process, the airport decided that art would not be an afterthought, but integrated into the airport model. “This foresight allowed the architects to work with an artist to incorporate large-scale art installations as part of the design. These installations will make a lasting impression on passengers traveling through The New SLC Airport.” The facility will be built in two phases. The first includes construction of the central terminal, parking garage and parts of the new concourses, and is expected to be complete by September 2020. No local tax dollars are being spent on the project, which is funded by user fees, primarily by airlines serving SLC, as well as savings, car rental fees, passenger facility charges and airport revenue bonds. According to the official website, construction of the parking garage, elevated roadway, terminal and west ends of the south and north concourses has been visible since steel erection began in May 2017. Prior to the above-ground work, underground stone columns were installed to provide seismic stability, while steel piles were put in place to support the weight of the building. Crews installed 7,600 stone columns to stabilize the ground and drove more than 3,200 steel piles. Salt Lake City Airport Redevelopment Program Director Mike Williams said the program currently averages approximately 1,825 trade workers. As for the biggest concerns when rebuilding an entire airport, “There can be limited impacts to the current airport operations. To achieve this, there is considerable planning whenever construction will occur close to the airside or landside operations.” Safety also is a key concern. “There are trained safety

staff on the construction, airport and program management teams,” said Williams. “Anyone spending time onsite must attend safety training.” Like with any major construction project, there are obstacles that must be addressed. “The job market is extremely tight with a lot of opportunities, so keeping trade workers on the project for the duration is challenging,” said Williams. “Keeping the entire team focused and excited about the finish line requires the celebration of milestones along the way.” Williams noted that detailed construction schedules and phasing plans help keep the project on target. The major focus right now is interior finish construction and the installation of the technology system. Construction on the prosee SLC page 6

Salt Lake City International Airport photos

The project team for the north concourse is a joint venture between Austin Commercial and Okland Construction. HOK serves as the architectural firm.

Salt Lake City International Airport photo

Crews install cooling towers on the North Concourse.

“Keeping the entire team focused and excited about the finish line requires the celebration of milestones along the way.” Mike Williams Salt Lake City Airport Redevelopment

Salt Lake City International Airport photo

Contractors perform the Gateway bridge hoist.


Construction Equipment Guide • Utah State Supplement • www.constructionequipmentguide.com • December 22, 2019 • Page 5


Page 6 • December 22, 2019 • www.constructionequipmentguide.com • Utah State Supplement • Construction Equipment Guide

Salt Lake City International Airport photo

Salt Lake City International Airport photo

Crews perform the final elevated roadway pour.

Holder Construction, Big-D Lead SLC Redevelopment SLC from page 4

gram actually began in July 2014, and will continue in phases through 2023/2024. The parking garage, terminal building and west portions of the north and south concourses will be completed in 2020. In October 2019, crews installed charging stations on the south concourse-west for electric vehicles and began installing the glass curtain wall on the west portion of the terminal where Customs and Border Protection is located. They also completed roofing and glass curtain walls on the north concourse-west and set initial passenger boarding bridges on the north concourse-west. Crews continued work on two 76-ft. tall

helices on the south side of the parking garage, started installing terrazzo, ceiling tiles and column covers in the north concourse-west and finished apron paving around the south concourse-west in preparation for a hard stand operation. Work also started on the curbside baggage handler system installation and asphalt paving on inbound elevated roadway. The airport’s 1.7 million-sq.-ft. parking garage will feature 3,600 parking stalls, which is twice the number of stalls in the current structure. It also includes four escalators, 9,000 tons of rebar, 90,000 cu. yds. of concrete and is the size of three football fields. Regarding sustainability efforts, the new airport will connect to

Salt Lake City International Airport photo

Crews top out the last beam in May 2019.

Salt Lake City International Airport photo

The Salt Lake City International Airport (SLC) Redevelopment Project calls for replacing three aging terminals with one large, central terminal and two linear concourses connected by a passenger tunnel. It is the largest public service project ever built in Utah.

public transit, make use of waterefficient plumbing fixtures, purchase 2.1 MW of off-site Green Power through Rocky Mountain Power, procure a minimum of 20 percent of materials locally containing recycled content and divert more than 95 percent of construction waste from the landfill. In addition, the linear layout of The New SLC will be more efficient than the current pier configuration, reducing taxi times and aircraft idling while waiting for a gate. Also, more windows will result in more natural light, which is environmentally friendly. A wide variety of equipment is being used on the project. Heavy machinery required to complete

the work includes 90-ton roughterrain cranes, a Grove RT890E, paving equipment, lulls and lifts, backhoes and heavy haulers. Williams said, overall, the most time-consuming part of the construction involves evaluating and incorporating user change requests. “Each request must be evaluated to determine if it is ‘a must have’ or ‘a nice to have’, and then must be analyzed against the budget and schedule before bringing it to the executive team for approval. The project team for The New SLC is HDJV, a joint venture of Holder Construction and Utah’s Big-D Construction, which is responsible for work on the car

rental facilities, central utility plant, parking garage, elevated roadway, south concourse, terminal, central tunnel, airfield paving and economy parking. The project team for the north concourse is a joint venture between Austin Commercial and Okland Construction. HOK serves as the architectural firm. SLC is operated and managed by the Salt Lake City Department of Airports. Salt Lake City’s Mayor, the City Council and a nine-member advisory board of citizen volunteers oversee its affairs. SLC is the 23rd busiest airport in North America, and the 85th busiest in the world. More than 370 flights depart daily to 99 nonstop destinations.  CEG


Construction Equipment Guide • Utah State Supplement • www.constructionequipmentguide.com • December 22, 2019 • Page 7

KeyBank Secures $23.5M for Affordable Housing in Utah FULL PAGE

The project is adjacent to Arcadia Apartments I, previously developed by Wasatch Residential Group.

10.125”x10.625”

Open $635

13 Time $590

1/2 PAGE 10.125”x5.25” or 5”x10.625”

KeyBank Community Development Lending and Investment (CDLI) has secured $23.5 million of construction and permanent financing for the Wasatch Residential Group (WRG), a real estate development, construction, finance and asset management company based in Salt Lake City to construct Arcadia Apartments II in Sandy, Utah. The 177-unit affordable family housing apartment development, which will be limited to 60 percent area median income, will consist of 52 one-bedroom, 82 two-bedroom, and 43 three-bedroom units. The project is adjacent to Arcadia Apartments I, previously developed by WRG, and will share

access to amenities including a pool, hot tub and fitness room. The project was awarded a four-percent low-income housing tax credit (LIHTC), and Enterprise Community Partners, the equity investor, is providing $15.6 million in LIHTC equity. The project also was awarded private activity bonds, which were purchased by KeyBank as a private placement. Sarah Geis of Key’s CDLI team arranged the financing. KeyBank has worked with WRG since the early 1990s on numerous multifamily, office and residential condominium properties. 

Open $525

13 Time $445

UTAH PUBLISHING 2020 Issue#

Closing

Publishing

3

January 23

February 2

5

February 20

March 1

7

March 19

March 29

9

April 16

April 26

11

May 14

May 24

13

June 11

June 21

15

July 9

July 19

August 6

August 16

17

1/4 PAGE Open $355

19

5”x5.25”

21

13 Time $330

September 3 September 13 October 1

October 11

23

October 29

November 8

25

November 23

December 6


Page 8 • December 22, 2019 • www.constructionequipmentguide.com • Utah State Supplement • Construction Equipment Guide


Turn static files into dynamic content formats.

Create a flipbook
Utah 26 December 22, 2019 by Construction Equipment Guide - Issuu