
3 minute read
As I-95 Reopens, Officials Make Plans for Permanent Fix
REOPENING from page 1 destroyed back open so commerce and travelers could resume their lives.”
This aggressive schedule meant bridge reconstruction would be impossible. Instead, project planners decided to have the debris and bridge removed and an asphalt road built where the destruction had occurred.


Cleanup in Three Days

PennDOT called on C.Abbonizio Contractors to handle the first step. The contractor, headquartered in nearby New Jersey, handled clean up in just three days. The north deck of the bridge had collapsed on the roadway, so Abbonizio cut the deck into pieces and hauled it away. Workers for the firm then cut up the otherdamagedsectionsandhauledit off site for crushing and later recycling. The heat from the original accident and the explosion was so intense that much of the material, including the rebar was pulverized.
“Abbonizio got in and got out quickly, so we could rapidly move on to the next step,” said Gleason.
To get a rebuilt roadway open in record time, workers constructed three lanes, each 11-ft. wide with a shoulder. The highway will have a standard construction for the median. The traffic is being pushed to the inside, while the outside lanes are being built. The final stage will move traffic to the newly built asphalt lanes to allow sufficient room for constructing the other lanes.
“This is a temporary fix, and we are already making plans for a more permanent solution,” said Gleason. “We have ordered the beams and have done the design for a new bridge, but with supply chain issues, we are not sure when we will be able to start on a new four-lane road.”
The old road was just 10 years old and PennDOT plans to mimic construction of similar roads in the state.
The work for rebuilding a new road will require ordering the new beams, cleaning up the parapet walls and doing hydro demolition to remove inadequate material. Once this is complete, work crews will rebuild the back wall and pedestals. The team will then do more demolition to the remaining approach slabs before installing new dams, new bearing pads and new beams.
The next steps will include Installing the new deck with rebar. The workers will pour new concrete slab and approaches. They will then form the rebar and pour the new parapet walls and median barrier. This is all on the outside portion of the bridge. Finally, workers will restripe the lanes and open them to traffic on the new outside lanes. This work will be repeated on the inside lanes and full traffic on the new roadway will resume.
The current work required 200 tons of steel and more than 1,500 tons of reinforced concrete. The road used 15,000 cu. yds. of lightweight recycled glass aggregate. This lightweight aggregate was mainly used to reduce the dead load, since there are two storm sewers underneath the Cottman Ave. roadway.
Gleason and the project team considered manyoptionsbeforedecidingtobuildaroad with flexible pavements as it looked like the fastest solution.
“It will be tricky making the proper tie-ins from asphalt to the concrete roadway, but our contractor is prepared for it. That team see REOPENING page 90

LOWE® Trenchers

Wrecking Balls For
Berlon’s Skeleton Rock Grapple has dual independent claws for complete clamping down on awkward loads. This bucket is ideal for rock picking, clearing fence lines, construction, scrap metal and other clean-up applications.
The LOWE® trenching attachments have proven to be one of the most useful tools in the attachment market. Primarily used on skid steer loaders, trenching attachments also excel on compact track loaders and a wide range of mini-loaders.



With a large selection of boom lengths and digging chains available, the LOWE® trenching attachment can make your machinery investment more useful.
The BP-Series planetary reduction auger drives bring elements of performance and dependability to the attachment marketplace.
-Features include: increased gear strength, stronger shaft support and through hardened alloy drive shaft.
Berlon’s Heavy Duty Extended Lip bucket provides greater cutting edge visibility while standard heavy duty package makes it ideal for machines 75HP and greater.
Features include: ¼” body, Reinforcement tube across back of bucket for added strength, Bucket bottom includes a heavy-duty dimple plate *A Berlon Exclusive*, 3/4”x6” weld-on cutting edge w/holes.

Berlon’s Compact Articulating Loader bucket is ideal for loading feed mixers and other heavy duty material handling equipment. Features include: ¼” body, Reinforcement tube across back of bucket for added strength, Bucket bottom includes 5 wear bars for durability, 3/4”x6” weld-on cutting edge with holes.


Contractors Sales Company www.contractorssales.com
121 Karner Road Albany, NY 12212 518-456-1445 • 888-468-5479
1283 Dolsontown Road Middletown, NY 10940 845-956-0222
Chappell Tractor www.chappelltractor.com
454 Route 13 South Milford, NH 03055 603-673-2640
251 Route 125 Brentwood, NH 03833 800-616-5666
391 Loudon Road Concord, NH 03301 800-358-6007 www.georgeandswede.com
George & Swede Sales & Service Inc.
7155 Big Tree Road Pavilion, NY 14525 585-584-3425 • 800-724-8722
Link-Belt Mid-Atlantic Construction Equipment www.Link-BeltMidAtlantic.com Ashland, VA 866-955-6071

Chesapeake, VA 800-342-3248 Frederick, MD 833-546-5235 www.woodscrw.com
Wood’s CRW Corp.
7096 Carlisle Pike Carlisle, PA 17015 717-795-0700 www.heavymachinesinc.com
Heavy Machines, Inc.
159 North Avenue Skowhegan, ME 04976 888-875-3954 2401 Broadway, Building #3 South Portland, ME 04106 877-202-1275
ESSCO Truck & Equipment info@ESSCOequipment.com
20 Kinsey Place Staten Island, NY 10303 844-44-ESSCO
1300 New Jersey 33 Farmingdale, NJ 07727
Chadwick-BaRoss www.chadwick-baross.com
10 Fox Hollow Road Oxford, CT 06478 203-200-8637
67 McGuire Road South Windsor, CT 06074 860-761-0381 www.marshall-machinery.com 348 Bethel School Road Honesdale, PA 18431 570-729-7117
Marshall Machinery, Inc.
15 Katrina Road Chelmsford, MA 01824 978-479-1524
31 James P Murphy Ind. Hwy West Warwick, RI 02893 844-238-7673









