3 minute read

Crews Move On to Next Phase of GDOT’s I-16/I-75 Project

GDOT from page 1

• Continue demolition and removal of the existing I-16 westbound and I-75 northbound and southbound bridges;

• Construction of MSE (retaining) walls along I-75 northbound and southbound and at other locations throughout the project continues;

• Construction of concrete sound and visual walls along I-75 northbound and southbound continues;

• Continue demolition of the existing pavement on the left lanes of I-75 northbound from Hardeman Avenue to north of the Riverside Bridge; and

• Continue concrete paving for new I-75 northbound and southbound roadways, and new I-75 southbound ramp to new I-16 eastbound.

Crews began the newest phases of construction on Feb. 10.

Phases 4, 5: From I-16 WB/I-75 to Walnut Creek

Work for these phases consists of:

• Continue construction of bridge substructures for I-16 Spring Street entrance and exit ramps;

• Continue construction of new Second Street bridge substructure;

• Continue construction of one new I-16 westbound bridge substructure and two superstructures;

• Continue construction of two new I-16 eastbound bridge substructures;

• Pouring bridge deck spans and edge beams on new I-16 eastbound bridge superstructure;

• Continue construction of two new I-16 westbound entrance ramps;

• Continue demolition of bridge ramp to I16 eastbound;

• Continue construction of new MSE (retaining) walls along I-75 northbound and southbound and other walls throughout the project; and

• Installing pipe and other drainage structures throughout the project area.

Constracting crews and members from GDOT currently are evaluating project area for remaining work items of Phase 1.

Overall, the I-16/I-75 Interchange Improvement project will enhance safety and mobility of the interchange by widening and reconstructing I-75 from Hardeman Avenue to Pierce Avenue and I-16 from I-75 to Walnut Creek within the city of Macon and Macon-Bibb County. This project represents a $500 million investment in the city, the Middle Georgia region and the state’s transportation system and will support Georgia’s growing freight and logistics industry.

More specficially, the project aims to construct additional interstate lanes, wider shoulder lanes and additional on- and offramps. A new collector/distributor (CD) road system will be constructed parallel to both I16 and I-75, which will allow additional noninterstate traffic capacity. Modifications will be made to bridges and surface streets within the project area to accommodate the additional interstate and CD lanes. These surface street improvements will add or expand dedicated turn lanes, which will reduce congestion and improve mobility for commuter traffic.

Phases Complete

Phase 1: I-16 Eastbound — Improved approximately 1.5 mi. of I-16 EB between I75 and Coliseum Drive. Phase 1 construction contract was awarded to C.W. Matthews, low bid at $70 million.

This portion was completed in summer 2022. Roadwork included operational improvements to I-16 WB at the Spring Street interchange. These improvements eliminated the existing weave and improve safety on I-16 EB between I-75 and Spring Street. Crews also closed the Spring Street loop ramp and constructed the I-16 EB collector distributor (CD) road between I-75 and Spring Street.

Pleasant Hill Community

Phase 1B — Involved the mitigation improvements to the Pleasant Hill Neighborhood on each side of the I-75 corridor. The Phase 1B construction contract was awarded to E.R. Snell for $13 million.

This portion of the project was completed in spring 2018. Roadwork included the relocation and rehabilitation of home to seven vacant lots and building 17 new residential structures throughout the community; created a linear park that includes green space and multi-use trail, lighting and information kiosks along the east side of I-75; created the Jefferson Long Park on the west side of I-75; the boyhood home of Little Richard, the Penniman House, was relocated adjacent to the Jefferson Long Park and serves as a community resource center, where specially created mobile interpretative panels are now displayed; constructed noise and visual walls along I-75 within Pleasant Hill; replaced the David Lucas Pedestrian bridge, transformed an existing open drainage ditch into a grasscovered culvert and streetscaping (resurfacing and sidewalk rehabilitation) throughout the community; and the closure of Frontage Road between First and Second Streets to be

Connected to Customers, from Rock to Road®

We help build the roads that connect goods to markets, people to communities and families to one other. Astec pavers, screeds, mills, stabilizers and MTVs yield innovative and reliable Rock to Road solutions that create value and connection. We are inspired to connect with our customers through innovative design for safe and reliable roads. astecindustries.com

This article is from: