By Irwin Rapoport CEG CORRESPONDENT

Employing an accelerated bridge construction method (ABC), Q&D Construction was able to complete the California Department of Transportation’s $14.1 million U.S. Highway 50 Echo Summit Sidehill Viaduct Replacement Project three months ahead of schedule. The original bridge (two lanes, 129-ft. long and two spans), constructed in 1939 for $25,000 in El Dorado County, served motorists for more than 80 years as the primary route between Sacramento, Calif., and South Lake Tahoe. The new structure, two lanes and 96-ft. long single span, meets current safety and seismic standards. “By utilizing ABC elements with a full closure of the highway, the project was accelerated by about three months and completed in two seasons rather than extending into 2021,” said Caltrans North Region Construction Chief Andrew Alvarado. see BRIDGE page 4

Crews from Q&D Construction recently completed the Echo Summit bridge replacement three months ahead of schedule due to an accelerated bridge construction (ABC) method.

SACRAMENTO ONLINE EQUIPMENT AUCTION

WOODBURN ONLINE EQUIPMENT AUCTION

Friday, July 30th, 2021 @ 8:30am Saturday, July 10th, 2021 @ 8:30am 4751 Power Inn Rd., Sacramento, CA 95826 17129 Pacific Highway, Woodburn, OR 97071

www.barnoneauction.com | (866) www.BARNONEAUCTION.com 866 372 - 372- -1700 1700


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.