Flatiron Construction Ahead of Schedule for I-710 Project By Irwin Rapoport CEG CORRESPONDENT

Construction began in May 2018 on the California Department of Transportation’s (Caltrans) $150.7 million Interstate 710 Pavement Rehabilitation and Bridge Widening Project, which was awarded to Flatiron Construction Corporation in February 2018. Crews have been making solid progress on the project that covers a 3.5-mi. stretch of the north-south I-710 through the cities of Commerce, Vernon, Bell, and the unincorporated area of East Los Angeles from Slauson Ave. to State Route 60. The project, financed by state and federal dollars, is scheduled to be completed in 2021. Rehabilitation The project consists of rehabilitating a portion of the highway (five lanes in each

During weekend closures, Flatiron vehicles are able to enter and exit the work zone.

Operations are ongoing to remove sections of the old road to be replaced.

direction) with joint plain concrete pavement, (JPCP), and continuously reinforced concrete pavement (CRCP). All northbound lanes between Bandini Boulvard and the I5/I-710 Interchange are being replaced with JPCP. The Hobart Yard Bridge, which spans BNSF16 rail tracks and several Metro lanes, is being widened.

The highway has five non-standard lanes (11 ft.) in each direction and is being widened to five standard lanes (12 ft.) with 8-ft. wide shoulders (inside and outside). In addition, the median shoulders are being repaved with JPCP and the median barrier will be upgraded to meet current standards. The work also includes installing new overhead sign structures, an overhead changeable message sign, and upgrades to drainage.

Caltrans wants the project completed rapidly and crews are working non-stop, seven days a week, with road closures occurring between 7 p.m. and 6 a.m. for 24 weekends (16 thus far); 55-hour closures are invoked. The Hobart Yard Bridge at 1,200 ft. is the longest, while the Bandini, Washington, and Pacific Way bridges are shorter. The on/off ramps for the bridges also are being see FLATIRON page 10

SACRAMENTO MONTHLY PUBLIC AUCTION

PORTLAND MONTHLY PUBLIC AUCTION

Saturday, February 8th, 2020 @ 9:00am 4751 Power Inn Rd., Sacramento, CA 95826

Friday, February 28th, 2020 @ 8:30am 1501 N. Schmeer Rd., Portland, OR 97217

www.barnoneauction.com | (866) www.BARNONEAUCTION.com 866 372 - 372- -1700 1700


Page 2 • January 19, 2020 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide


Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • January 19, 2020 • Page 3

ZZER ZE ERROOO% % FIFFINAN INA INAN IN NAANNNCCIN CING CI CINNGG 0 DO DDOWN WN. WN. WN N. 0 HHA HASSLE. ASSSLE AS SLE.E GET 0% FOR F 60 MONTTHS ON SELECT SELECCT NEW CA ATT M MACHIN NES

*

®

Owning and operating new Cat® compact equipment has never been simpler. No matter which one best suits your business, you can rely on the expertise of your local Cat dealerr to make machine ownership hassle-free.

www.hawthornecat.com San Diego 858-239-1120

www.petersoncat.com Bay Area & Northern California, Oregon, and Southwest Washington 844-349-4353

www.quinncompany.com Central & Southern California nia 888-842-2155

*Financing offers valid from February 1, 2020 through June 30, 2020. 0% interest for 60 months financing with zero down payment available only on the following new Cat machines manufactured anufactured by Caterpillar Inc.: Skid Steer Loaders, Mini Excavators, Compactt Track T Loaders, Multi Terrain Terrain Loaders, Compact Wheel Loaders, Backhoe Loaders, Small Dozers, Small Wheel Loaders and TTelehandlers. elehandlers. This promotion includes a low monthly payment financed with ith Cat Financial Services Corporation on a 60-month Instal Installment Sale Contract or Conditional Sales Contract. Financing, zero down and published rate terms are subject to credit approval through Cat Financial for customers who qualify. Not all buyers may qualify. Higher rates apply for buyers with lower credit rating or qualifications. Offer available only at participating Cat dealers. Flexible payment terms available to those who qualify. Offer is available to customers in the USA only. Offer subject to machine availability. Offer may change without prior or notice and additional terms and conditions may apply ply. Contact your Cat dealer for details. © 2020 Caterpillar. All Rights Reserved. CA ATT, CA ATERPILLAR, TERPILLAR, LET’S DO THE WORK, their respective logos, “Caterpillar YYellow”, ellow”, the “Power Edge” and Cat “Modern Hex” trade dress as well as corporate and product identity used herein, are trademarks of Caterpillar and may not be used without permission. www.cat.com / www.caterpillarr.com .com


Page 4 • January 19, 2020 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide

Can You Dig It: Slew of Construction Projects Begin

Anvil Builders crews sort through the wreckage of the Camp Fire in Paradise. All cars were removed and hauled away for recycling. A loader cleans up the beach in Coronado with the Hotel Del Coronado visible in the background.

Independent Construction uses a fleet of 657 scrapers to move mountains to make way for thousands of new homes. Ferma Corp. demolishes an old shopping mall in Cupertino using a fleet of its custom demolition machines, including this high reach excavator.

LB3 Enterprise’s Hitachi 1200 excavator moves excess dirt on a housing development project in Southern California.

A Caltrans loader cruises Highway 1 in Big Sur after cleaning up material washed onto the highway following winter storms. see DIG page 6


Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • January 19, 2020 • Page 5


Page 6 • January 19, 2020 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide

Paving the Way: Town of Moraga Honored With Award The Town of Moraga, Calif., was honored By leveraging $600,000 of the $1.7 million by FP2 Inc. late last year with the 2019 James annual sales tax revenue, the town yielded B. Sorenson Award for Excellence in $7.7 million to complete an intensive threePavement Preservation, which recognizes year pavement repair program focused on superior pavement preservation practice, usuresidential streets, with the first year (2013) ally to a city, township, county or state agency. concentrating on preventive maintenance, The award was presented to Moraga public second year (2014) on overlays, and third works director/town engineer Edric Kwan, at year (2015) on reconstruction treatments. the October annual meeting of the Rocky Educating the public from the start that Mountain West Pavement Preservation Measure K is a critical funding source to help Partnership in Park City, Utah. address, but not fix, the town’s entire pave“By 2012, Moraga’s Pavement Condition ment network set realistic expectations by Index [PCI] had deteriorated to 49 and was expressing that the $7.7 million would only ranked in the bottom 15 of all 109 Bay Area tackle 30 percent of the $25 million in backcities and counties,” Kwan said. “The town’s log needs. pavement network was at a critical juncture, Public outreach for the intensive pavement with a backlog of $25 million in pavement program over three years included pre-conneeds. Without significant maintenance, the struction activities such as letters mailed to town’s network would deteriorate at a more At the October Rocky Mountain West Pavement Preservation Partnership meeting affected residents, door-to-door education by rapid rate and put much of the network at risk in Park City, Utah, National Center for Pavement Preservation director Judith volunteers and two town hall public outreach Corley-Lay presents FP2’s James B. Sorenson Award for Excellence in Pavement meetings. of falling into poor condition.” The Town of Moraga is a semi-rural com- Preservation to Edric Kwan, public works director/town engineer of the Town of It included construction literature such as a munity of 17,416 located east of Oakland. Moraga, Calif. public outreach brochure, frequently asked Moraga was incorporated in 1974 and in the questions and door hangers; a project website years that followed, its street network of 56 centerline miles public outreach program through a Revenue Enhancement with up-to-date project status reports and a three-week look Community Outreach to Neighborhoods (RECON) commit- ahead; a Facebook site; and notifications two weeks in was neglected due to lack of dedicated funding. tee to communicate the critical need of the town’s roads. advance of work and three days in advance of no-parking After a vigorous public outreach, town voters approved signs. Conveying the Need for Improvement Recognizing the funding shortfall and community needs, Measure K on Nov. 6, 2012 — instituting a 1 percent sales see MORAGA page 11 the town embarked on an intensive and thorough grassroots tax — with a 70 percent approval rate.

Contractors Moving Mountains in Effort to Get Projects Started DIG from page 4

Turner Mining Group moves blasted limestone with a Volvo 750 excavator and a fleet of 4-ton articulated trucks.

Graniterock paving crews work overnight to resurface Highway 1 near Pacifica.

Anvil Builders laying pipe using a 374F in San Francisco. This project involves the redevelopment of old industrial piers to create new office space.

One of Graniterock’s D11T’s pushes blasted granite toward the mouth of its mobile crusher at the AR Wilson Quarry in Aromas.


Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • January 19, 2020 • Page 7

*Excludes S70 Bobcat skid steers, MT55 & MT-85 mini track loaders.

NOTT ALL EXCAV E VATOR RS ARE CREATED C D EQUAL. EQUAL Proven performance. More M comfort. Better design. The redesigned, revolutionary lineup of Bobcaat® compact excavators has it all. Dig and slew with more power, stability and confiddence.

BSW

Berchtold Equipment

Bobcat of the Bay

www.BobcatSouthWest.com

www.berchtold.com

www.totalequipmentandrental.com

3000 Pegasus Drive Bakersfield, CA 93308 661-323-7817

Bobcat of Fremont

Miramar Bobcat, Inc.

South Coast Bobcat, Inc.

Valley Bobcat, Inc.

9370 Miramar Road San Diego, CA 92126 858-566-4600

1783 N. Batavia Street Orange, CA 92865 714-998-5445

9324 San Fernando Road Los Angeles, CA 91352 818-768-8300

Inland Bobcat, Inc.

Bobcat of Los Angeles, Inc.

5494 Via Ricardo Riverside, CA 92509 951-788-3030

13728 Alondra Blvd. Carritos, CA 90703 562-926-2342

1410 W. Betteravia Road Santa Maria, CA 93455 805-922-7905

43801 Osgood Rd. Fremont, CA 94539 510-897-4123

Bobcat of Santa Rosa 3675 Santa Rosa Ave. Santa Rosa, CA 95407 707-595-3261

Bobcat of Contra Costa Bobcat , the Bobcat logo and the colors of the Bobcat machine are registered trademarks of Boobcat Company in the United States and various other countries. ®

2035 E. Leland Road Pittsburg, CA 95466 925-318-4465


Page 8 • January 19, 2020 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide

Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • January 19, 2020 • Page 9

LIFETIME E FRAME & STRUCTUR RE WARRANTY TY

LIFETIME BOOM, FRAME A & ARM GUARANTEE E

T Ne The Nw

EC200 0 ELL

Baker kersfield Bakersfield, CA A 661 387 6090 661.387.6090 Corona Corona, CA 951.277.7620

D Designed forr Yo our Need ds

Fresno Fresno, CA 559.834.4420 Sacramento Sacramento,, CA A 916.504.2300

24 HOUR R PARTS GUARANTEE* EE**

ACTIVECARE RE DIRECT 24/7/365 MONITORING NG

2ND AND D 3RD YEAR R ADDITIONAL AL WARRANTY TY

BUY-FI SMART CREDIT

San Diego Lakeside, CA 619.441.3690 San Leandro San Leandro, CA 510.357.9131 Turlock Turlock, l k CA 209.410.6710

Rates as lo ow w as

0% for 36

FUEL EFFICIENCY CY GUARANTE EE

*

months

Th he new EC200EL is purpose-buiilt to take on your tough jobs, day in and day out. Right now, ta ake advantage of special bundle financing f and receive extended warranty w coverage for up to th hree years. Discover the power an nd performance you need combined with fuel efficiency y and a lo ow cost of ownership today at yo our local Volv Volvo Construction Equipment uipment & Services Ser location.

vcesvolvo..com

*Fiinance Guidelines/Conditions: The offering finance company for this progrram am is Volvo Volvo Financial Services (VF VFS), and the trrans ransaction is subject to to VF VFS credit approval. val. Dealer must rec ceivve e VF VFS approval val and contrract act must be funded on or before e 12-3 12-31-20 12 31 2019 for units to to qualifyy. y. Final rat ratte and tterms erms are subject bject to t credit review and underwriting by VF VFS, and all cussttomers omers may not qualifyy. VF VFS reserves the right tto o amend or canc c el this progrram am at any time without notice. Valid Valid for U.S. S. dealers and trrans ansactions. Progrram am may not be c combined with th any other offer unless explicitly permittted ed by b VF VFS. Any dea aler specific progrrams ams will supersede this offerr.. This progrram am c cannot be combined with the Conquest Excavvat ator progrram. am. ** Some restrictions applyy. For For a list of terms t and conditions, visit sit www w.volv volvoce.com/parts24.


Page 10 • January 19, 2020 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide

Construction Crews Work to Replace 37 Lane Miles

Weekend operations are crucial to the removal of sections of the old highway 710.

FLATIRON from page 1

widened. “The Bandini, Washington, and Pacific Way bridges are most utilized by trucking,” said Peter Lee, Disrict 7 resident engineer. Approximately 37 lane miles will be replaced, which includes all lanes of I-710 from Slauson to SR 60. “The project will reduce congestion,” said Eric Menjivar, public information officer of Caltrans District 7. “With the shoulders, motorists in an emergency will have a safe place to pull over and backups will not occur. It also provides a safe place for the California Highway Patrol and Caltrans maintenance workers to do their jobs. It will improve the movement of goods into and out of the Port of Los Angeles and the rail yards, creating a smooth transition for trailers where there is no interruption for them and motorists.” Planning for the initiative began in 1999. The infrastructure was built in the 1960s and upgrades are needed to extend the lifespan. Prior to construction, the highway carried 214,000 cars and trucks daily. When completed, the new infrastructure will be able to handle 230,000 vehicles and meet

traffic demands for the next two decades. New Infrastructure In-house Caltrans engineers designed the new infrastructure. “The biggest challenge is widening the Hobart Yard Bridge over the rail yard,” said Lee. “We’re also rehabilitating the old concrete pavement, which is being

Flatiron crews are preparing a new section of a concrete surface for a new lane on I-710.

done on weekends from Friday night to Monday morning, reducing traffic to two lanes. We’re using a fast setting concrete, with a polyester concrete overlay, that sets in 12 hours. With conventional concrete, we could not put traffic on for at least 10 days. Normally the concrete pavement is 9-to-10 in. thick, but we’re putting in over 13 in. — a thicker, beefier pave-

ment because a lot of trucks use the highway.” The existing drainage system is being extended to the areas being widened with reinforced concrete pipe and drainage inlet, along with a Gross Solids Removal Device system (GSRD) to filter out the debris from the runoff before it goes into the channel adjacent to the Washington Bridge. A mini-

This is a section of the old road being removed. The rebuilding process has crews going directly under the subbase.

mum amount of landscaping using drought tolerant foliage will be done when feasible. Local traffic is impacted due to lane closures. “Since the start of construction, extended closure signs have been posted at the start and end of the construction zone,” said Menjivar. “Signs alerting drivers that there may be temporary closures are also at every ramp in the construction zone. Electronic changeable message signs with detour and closure information will be posted at various locations around the construction zone during construction hours.” Caltrans is extensively using social media to keep motorists updated on lane closures and detours. Flatiron has completed nearly 90 percent of the bridge work, with the remainder taking place on the Hobart Yard Bridge. But a fair amount of the road work sill remains. “We’re about 70 percent complete,” said Lee. “For the 2020 construction season, our goal is to finish all the weekend pavement work by May and finish the Hobart Yard Bridge work just before summer so the full weight of that see FLATIRON page 14


Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • January 19, 2020 • Page 11

2010 Case 586, 2607 Hrs, 5K, Cummins Eng, SS, Stilt, 2WD, Serviced and Ready To Work ............................................................$31,500

2013 Freightliner M2 106, Cummins, 152K Mi ISC, Def, Carb Comp, Dpf, A/T, Morgan 20’ Body....................................................$39,500

2013 Bobcat T650, Stk# SS-18-2815, 1384 Hrs, Open ROPS, S/N: A3P016496, Tracks 90% ....................................................$36,500

2013 SANY SRC865, 575 Hrs, Cummins QSB6.7, 250HP, 113' Four Section main boom, 30.2'-52.5' extension ........................$189,500

2013 Freightliner Cascadia DD13, Super 10, 245k Mi, New Demo Box w/Hyd Gate, New Tarp Sys, Carb Compliant ..........................................................................................................$92,500

1999 Gradall 534D-10-45, 320 Hrs, New Hour Meter, Outriggers................................$24,500

2016 Case 586H, 2777 Hrs, 6000 Lb Cap...... ............................................................$37,500

1992 Cat RC60, 5328 Hrs, 6K, Perkins Dsl, SS, 4SPD, Forward & Reverse Shuttle, 21’ HI ............................................................$17,500

2012 Deere 310J, 4in1 Bkt, 4WD, ROPS, Dsl, 70-97 HP, Extendahoe........................$39,500

Grassroots Program Spurs Paving Preservation Work MORAGA from page 6

Signage also was important, including contractor equipment and workers identifying Measure K funding, neighborhood entrances identifying Measure K funding, and lawn signs urging Shop Moraga First to support Chamber of Commerce’s endorsement of Measure K, and to enhance sales tax receipts. “The three-year intensive pavement program effectively stopped the hemorrhaging of the town’s failing pavement network,” Kwan said. “Through being good stewards of the local sales tax revenue, the leveraged funds raised the town’s network PCI significantly, from 49, a network at risk, to 70, a network in good condition.” Another aspect of the education process also explained why applying the “right treatment, in the right place, at the right time” is better than the fixing the “worst case first.” 

Previous FP2 Award Winners FP2 awards given 2005-2007 were called the Pavement Preservation Excellence Award. In 2009, it was renamed James B. Sorenson Award for Excellence in Pavement Preservation. 2005 — Los Angeles, Calif. 2006 — Frederick County, Md. 2007 — Nashville, Tenn. 2009 — California Department of Transportation

2010 — County of Rockland, N.Y., department of highways 2013 — New Hampshire Department of Transportation 2014 — Charleston County, S.C. 2015 — Bureau of Street Services of Los Angeles 2016 — Ohio Department of Transportation 2019 — Town of Moraga


Page 12 • January 19, 2020 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide

Granite Embarks on $33M Highway Reconstruction Job

Granite has been awarded a contract by the California Department of Transportation (Caltrans) for the reconstruction of four miles of State Route 99 (SR 99) near Kingsburg.

Semi - Custom Rebuilt Vocational Trucks

2005 International 4300…$24,000 W001778, 2,000 Gallon Tank, Manual

2011 International 4400……$64,000 W002646, 4,000 Gallon Tank, Automatic

2011 International 4300…$35,000 W002121, 5,500 Hours, 2000 Gallon

2009 International 4300 …$24,000 W002048, 2000 gallon, DT466 210hp

Two locations in California to Serve You!

14635 Valley Blvd. Fontana, CA 92335

909.822.2200

10918 Shoemaker Ave. Santa Fe Springs, CA 90670

www.scottequip.com

C A L L U S T O D AY !

562.777.0775

Granite has been awarded a contract by the California Department of Transportation (Caltrans) for the reconstruction of four miles of State Route 99 (SR 99) near Kingsburg. A primary source of funding for this project is Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 that is expected to invest $54 billion over a 10-year period to improve California’s roads, freeways and bridges. Granite booked the $33 million contract in the fourth quarter of 2019. This four-mile project includes recon-

structing two lanes in both directions of SR 99 with continuously reinforced concrete pavement as well as reconstructing ten offand on-ramps with hot-mix asphalt. “We are proud to be partnering with Caltrans on another SB 1-funded project to improve SR 99 through the heart of the Central Valley,” said Jim Radich in a press release, vice president of Granite’s California operations. Construction is expected to begin in the second quarter of 2020 and scheduled for completion in the third quarter of 2021.

Owner-Operators Struggle With Strict Rules of AB5 When the California Supreme Court signed Assembly Bill 5 (AB5) into law, things began to look grim for California owner-operators working for trucking companies. AB5, which goes into effect on Jan. 1, 2020, puts strict rules into place regarding the independent contractor status. The status is determined by the ABC Test, which states the following three components: A: that the worker is free from the control and direction of the hiring entity in connection with the performance of the work, both under the contract for the performance of the work and in fact; B: that the worker performs work that is outside the usual course of the hiring entity’s business; and C: that the worker is customarily engaged in an independently established trade, occupation, or business of the same nature as the work performed. Opponents of the law explain that the “B” component will put California’s owner-operators out of business because it is impossible for an independent driver working for a trucking company to be performing outside

of the hiring entity’s business. This, opponents say, will bring down the many thousands of drivers who have built their businesses following the traditional independent contractor model. These are people who have invested hugely in their businesses, many of whom have been working for decades. Indeed, many owner-operators in California have already received notification from the carriers they work for, putting the burden of how to proceed on their shoulders. Options given have included, getting their own authority, an expensive endeavor; becoming company drivers which many say, will decrease their income substantially; or move out of the state. The California Trucking Association (CTA) has sued the State of California to block use of the ABC Test for truckers. The lawsuit is waiting for review in federal court. In addition, the CTA is reaching out to owner-operators and encouraging them to take action by contacting their state representatives to explain how AB5 is negatively effecting their lives.  CEG


Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • January 19, 2020 • Page 13

NEXT ISSUE CLOSES: February 6, 2020


Page 14 • January 19, 2020 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide

Reconstruction Begins to Make Highway Commute Easier FLATIRON from page 10

bridge can be utilized. For the second half of the year, Flatiron will rebuild the median pavement sections and place a new median barrier. There will be some landscaping and hardscape improvements in 2021.” On Jan. 13, crews began the demolition of an overhang with an existing barrier on the Hobart Yard Bridge. “We have to remove the existing overhang barrier and build a bridge deck closure pour to tie the existing structure together,” said Lee. “We’re coordinating with BNSF to secure the work windows where we can go in. A temporary platform is being built to help catch all the concrete rubble that will fall down so that it doesn’t damage the tracks.” Mike Roe, Flatiron’s project manager, also is dealing with the restrictions of a tight work zone and constant traffic. “We try to provide a 30-and-40 ft. work zone for the crews,” said Lee. “For the weekend closures, K rails are placed and for weeknights, cones are placed. We close the ramps on weekends and this is where crews access the work area and bring in construction materials.” Relations between Caltrans and Flatiron are excellent. “We have a good team,” said Lee. “Flatiron is a seasoned and experienced contractor in Southern California and we don’t have any disputes as of today. We have developed great partnering relationship and trust in our team and the project is ahead of schedule. We also have weekly meetings with BNSF to coordinate the upcoming construction work.” Much of the lane reconstruction is done on weekends. “We’ve learned a lot as the work has progressed because there is only so much that you can do on weekends,” said Lee. “You cannot do more than you planned, because once you’re committed, you have to finish what you started and the freeway closure has to be opened for the Monday morning commute.” Multiple crews remove the concrete and the soil beneath it, going down directly to the subgrade. “It’s a brand new roadway and

construction projects,” said Menjivar. “Residents and local businesses nearest to the freeway may notice noise, vibrations and dust associated with the batching operation. We’re making every effort to mitigate noise associated with construction activities by installing a noise reduction barrier around the plant location.” Noise levels do not exceed state, federal and city regulations; water trucks are being used to minimize dust during working hours; and dump truck drivers are minimizing backing up operations to reduce back-up alarm noise.

Some of the ongoing road construction involves crews building new lanes for I-710. that requires a lot of planning and coordinating,” said Lee. “We stop paving on Sunday afternoon so that motorists can use the new lane on Monday morning. Because they excavate down 3 feet, the material they run into can be a bit tricky — claylike or soupy dirt and soil, which is a challenge for the crews.” Between 3,000 and 4,000 ft. of new lanes can be constructed on weekends. One of the challenges for the Hobart Yard Bridge work are the CIDH — cast in drilled hole concrete foundations. “These pilings are 80 feet deep and we’re working on them next to train traffic,” said Lee. The drainage system is being installed as the new roads are being constructed. “Last winter it rained more than previous years in Southern California and Flatiron had to provide many temporary drainage systems — channeling and diverting stormwater around the work area — while the new pipes, inlets, and GSRD were placed,” said Lee. Peak days have 80 Flatiron and subcontractor employees on site. The subcontractors are Statewide Traffic Safety & Signs; BC Traffic Specialist; CGO Construction Company; Advanced Concrete Sawing & Sealing; All American Asphalt; Ace Fence Company; Velarde Concrete Construction;

Using a roller, the ground is being compacted for a new section of road. Penhall Company; Griffith Company; Ferreira Construction; Don H. Mahaffey; Diversified Landscape Co.; Coral Construction Company; Cooper Engineering; Con-Fab California LLC; CMC Commercial Metals; LSM Transport; and Pre-Con Products. What’s Being Removed Materials being removed include 30,000 cu. yds. of concrete, 3,000 tons of asphalt, and 5,000 tons of steel. New materials

to be brought will see 40,000 cu. yds. of concrete, 10,000 tons of asphalt, and 10,000 tons of steel, and 30,000 cu. yds. of base materials. Flatiron set up a batch plant at the Bandini Blvd. off-ramp in Vernon to produce concrete for the repaving, which is using concrete removed from the existing structures, barriers and pavement. “In keeping with our efforts to enhance the environmental sustainability, concrete is being recycled and used for this and other

What’s Being Used Flatiron is using a large amount of equipment, including: cranes — a Link-Belt RT-8065 and an RTC8080 SER II 80 ton RT, and Terex 75-ton RTs and a T-340-XL; backhoes — a John Deere 410G, and Cat 430Es and a Cat 430E; excavators — a Cat 308E2 CRSBs, M322Ds, 321Cs 328D, 330CLs; and 345Cs; rollers — a Bomag 3-5 ton DBL, a Cat CS563, and a Dynapac CA260D; air compressors — Ingersoll Rand 185s and 250s; light towers — I-R and Magnum; loaders — Cat 938G IIs, 950Hs, 950Gs, 950 HQs, and 950Ks; skidsteers — a Volvo MC 90 B, a John Deere 325 LDR, and a Cat 259D CCE; forklifts — Hyster H80FT 8Ks and H360HDs, XTREME 11Ks and 12Ks; paving equipment — an Air Screed 58LF, a Multiquip screed, GOMACO RTP - 500 placer. an E2 Systems converyer placer, Bidwell BR201s and 4800s, GOMACO 2800, 4000, and Commander III pavers, GOMACO T600 cure tnm machines; batch plants — a Rexcon and a Strayer M-11; volumetric mixer trucks — Mack/Global 10 yds. and Peterbilt 14s; a variety of Ford and Dodge trucks; and various Sterling, Ford, Dodge, Peterbilt, and Kenworth mechanics trucks. Mechanics are on site to do rapid repairs to maximize the work hours. Flatiron purchased and rented equipment from many regional Los Angeles dealerships, which are helping with the project by providing spare parts and servicing machine under warranty.  CEG


Construction Equipment Guide • California State Supplement • www.constructionequipmentguide.com • January 19, 2020 • Page 15

WORLD’S SMALLEST BACKHOE NOW WITH TRACKS – JCB-1CXT

Max Dig Depth: 10 ft 1 in / Gross Engine Power 49 HP / Loader Bucket Breakout: 1,466 lb JCB 1 CXT, a TRACKED BACKHOE is a versatile machine, offering skid-steer and mini excavator performance in one package. The 1CXT provides superior maneuverability, an optional handheld tool auxiliary, as well as a universal quick hitch that is compatible with most of your skid steer attachments. Standard full cab with integrated heating & air-conditioning. Due to its compact size and under 10,000 lbs weight, the 1 CXT is easy to tow in a trailer without a CDL (where local regulations allow). NO DPF / DEF AFTERTREATMENT. Operators environment friendly with easy to use controls and all daily checks and greasing can be carried out at ground level on a JCB backhoe. To learn more about JCB 1CXT, visit www.jcb.com/en-us/products/backhoe-loaders/1cxt

/ /JCBNA

@JCBNA

w w.jcb.com .jcb.com JCBNA www

QMC Central California Power JCB 19487 Broken Ct, Shafter, CA 93263 (661) 589-2870 www.ccp-jcb.com

Meridian JCB 1315 Vinci Avenue Sacramento, CA 95838 916-880-5776 www.meridianutility equipmentsales.com/jcb

SoCal JCB

QMC JCB

14675 Valley Blvd., Fontana, Ca. 92335 866-522-7225 www.socaljcb.com

3820 S. K Street, Tulare, CA 93274 (559) 686-1579 961 E. 3rd Street. Hanford, CA 93230 (559) 582-9393 www.quality-mc.com

1960 Highway 20 Colusa, CA 95932 (530) 458-2166

www.nstractor.com

827 North Tehama St Willows, CA 95988 (530) 934-3382

2173 Blossom Street Dos Palos, CA 93620-2313 (209) 392-2161

1340 W. Charter Way Stockton, CA 95206 (209) 944-5500

3056 Colusa Highway Yuba City, CA 95993 (530) 923-7675

600 S. State Highway 59 Merced, CA 95341-6928 (209) 383-5888

1215 West Glenwood Ave Turlock, CA 95380-5703 (209) 634-1777

N&S Tractor

Terms & Conditions: Pictures shown with optional accessories. For towing policy please consult with your local state transportation office. Offers may change without notice and may not be combined. Additional terms and conditions may apply, please contact your local JCB dealer for details. JCB dealer reserves the right to withdraw, alter or decline any product from sale or any offer without prior notice. Price, if shown, does not include government fees, taxes, dealer freight/preparation, dealer document preparation charges or any finance charges (if applicable). Final actual sales price will vary depending on options or accessories selected.


Page 16 • January 19, 2020 • www.constructionequipmentguide.com • California State Supplement • Construction Equipment Guide

Visit us at ConExpo BL414

NOW AVAILABLE

2 YEARS

OR 2000 HR WARRANTY Quality Machines You Can Count On

Dealer for California & Nevada

0% Interest Financing for 36 Months Easy In-House Financing $29,600

$55,900

$115,500 $44,500

$26,500

$54,500

$46,500

hablamos en español • Call Mike (909) 821-5448 Call us today for your Purchase & Rental needs: Excavators • Skid Steers • Dump Trucks • Wheel Loaders • Asphalt Rollers • Water Trucks • Water Trailers • Light Towers • Telescopic Forklifts

SUNWARD DEALER OF CALIFORNIA Michael Madrid SO CAL SALES AND RENTAL “We Sell & Rent Opportunity”

202 W. Minthorn Street • Lake Elsinore, CA 92530

(951) 471-2037 or Call Michael Direct 24/7 at (909) 821-5448

www.socalequipmentinc.com

Visit us at ConExpo BL414


Turn static files into dynamic content formats.

Create a flipbook
California 2 January 19, 2020 by Construction Equipment Guide - Issuu