Huntsville
20 Decatur
State Supplement sponsored by:
231
65
72 Florence
2
72
565 59
43 231
31
5
ALABAMA STATE EDITION
431
Gadsden
78 59
A Supplement to:
Anniston
20
Birmingham Bessemer
82 Tuscaloosa
65 280
20 82 Auburn
80
85
Selma
Phenix City
Montgomery
82 65
231
43 84 431 331
84
84 52
SHIP WITHIN 48 HOURS
Dothan
31
45 65 98
SAME DAY PARTS AVAILABILITY
Mobile
10
®
May 20 2020
24 HOUR TECHNICAL SUPPORT BACKED BY A 75 YEAR BUSINESS Thousands in Service!
Vol. XXI • No. 11
“The Nation’s Best Read Construction Newspaper… Founded in 1957.” Your Alabama Connection • Rich Olivier, Atlanta, GA • 1-800-409-1479
Affordable Price. Premium Service.
CALL 800-367-4937 *On approved credit • Financing Available
W 210Fi Pair Wins Big on Alabama Race Circuit
Mill It Up staff on the project (L-R) includes Cody Butler, CFO; Kim Butler, president and owner; and Gary Wise, vice president.
Right out of the gate, the first W 210 Fi mills in North America won big as they cold-planed the famous Barber Motorsports Park outside Birmingham, Ala. There, in summer 2019, Mill It Up LLC, Warrior, Ala., — as milling subcontractor for Granite Construction Co. — was using its two brand-new W 210 Fi mills to remove aged asphalt from the race track with 7-ft.,3-in. drums and a HT22 cutting tool holder system with 8 mm spacing from Wirtgen. According to Wirtgen, the W 210 Fi is the most capable of the new technologically advanced “F series” of large milling machines, which also includes the W 200 Fi and W 207 Fi. They're now available in North America. Their flexible milling widths range from 4.9 to 8.2 ft. (1.5 to 2.5 m), cut up to depths of 13 in. (33 cm), and handle a wide range of applications, from surface course rehabilitation to complete removal to fine milling. The largest power plant of the series is rated at up to 755 hp (563 kW), depending on the model. In automatic mode, the Mill Assist operating system see BARBER page 2
Joint Venture Working to Rebuild, Widen Lanes Along I-65 The crews started from the north end for the grading and paving operations.
By Irwin Rapoport CEG CORRESPONDENT
The joint-venture of Dunn Construction Co. Inc. and Wiregrass Construction Company are looking to deliver the Alabama Department of Transportation’s (ALDOT) $68 million widening of four miles of I-65 (south of I-459 from exits 238 to 242) by this July. The work, occurring in Shelby County near the City of Pelham (20 miles south of Birmingham), began in February 2018 and is also upgrading the existing two lanes in each direction. The widening has two lanes being placed in the grass median and a new lane on either side of the north-south highway. Planning for the project has been in the works for many years as sections to the north of the project have already been widened to four lanes in each direction. “This is a continuation of that project,” said Gary Smith, ALDOT construction engineer, who noted that widening of the section north of the
one under construction was completed in 2012. The widening improves safety for motorists who will no longer have to merge into a smaller highway. The new road infrastructure was designed by ALDOT and Stantek Inc. “There were no significant design or engineering challenges,” Smith stated. “We had to widen some bridges, so staged construction for them was a challenge for that aspect. We had to do some cross-slope correction that was part of the rebuilding of the existing lanes. We had to get traffic off those lanes, stage them over into new lanes in the median and come back and reconstruct the correct cross-slope of the existing lanes. Since we had a place to move traffic, it wasn’t impossible by any means.” The expected lifespan of the new and upgraded lanes is approximately 20 years before having to resurface the top layers of the roadway again. The new lanes have a 12-in. base and a 17-in. asphalt buildup. There were few utility issues to tackle. Crews had a few see I-65 page 10