Creekside, Deptford.


























































![]()
































































































Creekside, Deptford.
























































































































































Creekside, Deptford.
















































































































































































































B - 50% of Cradles installed on North elevation in readiness for start of works
B - No refurbishment works to East, South and West elevations
B - Crash deck scaffolding erection and cradles installed to North elevation










A - Refurbishment works to North elevation facades complete
A - Refurbishment works to South elevation including balconies and rendered soffits complete
A - Refurbishment works to West elevation 50% complete. Balconies complete




B - Refurbishment works to North elevation facades 50% complete. Balconies complete.


B - Crash deck scaffolding installed


































































A - Refurbishment works to West elevation complete. Cradles and crash decking removed














































































































































A - Crash deck scaffolding erection to West











































































A - Refurbishment works to North elevation facades 85% complete

A - Refurbishment works to South elevation 50% complete
A - Cradles installed on South elevation in readiness for start of works
A - 50% of Cradles installed on West elevation in readiness for start of works



A - Refurbishment works to North elevation balconies complete
A - Refurbishment works to South elevation balconies 70% complete










A - Remediation to North elevation rendered soffits complete






















A West elevation
No refurbishment works to West elevation
Crash deck scaffolding erection to West elevation
50% of Cradles installed on West elevation in readiness for start of works























B - Crash deck scaffolding erection and cradles installed




































































































































A - Refurbishment works to North elevation facades complete

A - Refurbishment works to South elevation including balconies and rendered soffits complete
A - Refurbishment works to West elevation 50% complete. Balconies complete



A - North elevation crash deck and cradles removed
A - South elevation crash deck and cradles removed















B - Refurbishment works to North elevation facades 50% complete. Balconies complete.



B - Crash deck scaffolding to East elevation installed







A - Refurbishment works to West elevation complete. Cradles and crash decking removed.






B - Refurbishment works to North elevation facades and balconies complete. Crash deck and cradles removed
B - Cradles installed. Refurbishment works 80% complete.

















B


















































A - Refurbishment works to West elevation complete. Cradles and crash decking removed
Creekside, Deptford.


































































B - Crash deck scaffolding erection and cradles 50% installed

















B - Refurbishment works to North elevation facades and balconies complete.
B - North elevation crash deck and cradles removed.
B – East elevation cradles installed.
B – East elevation refurbishment works 80% complete.
B - Crash deck scaffolding erection and cradles 50% installed










A - Refurbishment works to West elevation complete.
A - West elevation cradles and crash decking removed.






Refurbishment works east elevation complete.




































































Creekside, Deptford.



































































- Refurbishment works to South elevation 50% complete. Balcony refurbishment complete.















Block B South Elevation
B - Refurbishment works east elevation complete.
B - Refurbishment works to South elevation 50% complete.
B - South elevation balcony refurbishment complete.

Block B West Elevation
B - Crash deck and cradles installed to west elevation B – Render replacement to roof areas complete















B - Refurbishment works West elevation complete. Soffit works 50% complete.





























































B – Render replacement to roof areas complete










































































B - Refurbishment works to South elevation complete. Cradles and crash deck removed.


C - Crash deck and cradles installed to East elevation















Block B West Elevation
B - Refurbishment works West elevation complete.
B - West elevation soffit works 50% complete.
B – Render replacement to roof areas complete
B - Refurbishment works to South elevation complete.
B - South elevation cradles and crash deck removed.

Block C East Elevation
C - Crash deck and cradles installed to East elevation



































































































B - Soffit works complete. Crash deck and cradles removed from west elevation C - Refurbishment works to East elevation 50% complete.



























































C - Refurbishment works to East elevation 50% complete. C – No works to South and West elevations










Block C North

C - Crash deck and cradles 50% installed to North elevation








C - Crash deck and cradles installed to North elevation






























































































































C - Refurbishment works to East elevation complete. Crash deck and cradles removed.
















C - Refurbishment works to East elevation complete.
C - East elevation crash deck and cradles removed.

C – No works to South and West elevations











C - Crash deck and cradles installed to North elevation
























































































































































C - Crash deck and cradles installed to South elevation
C – No works to West elevations










C - Refurbishment works to facades on North elevation 50% complete.
C - Refurbishment works to balconies on North elevation 50% complete.






C - Crash deck and cradles installed to West elevation


C - Refurbishment works to facades and balconies on North elevation complete. Cradles and crash deck removed.





























































































































C – Remediation works to East elevation balconies completed


C - Refurbishment works to South elevation facades and balconies 50% complete.
















C - Crash deck and cradles installed to West elevation
C - Refurbishment works to facades and balconies on North elevation complete.
C - North elevation cradles and crash deck removed.
C – Remediation works to East elevation balconies completed








C – No works to South and West elevations


Block C South Elevation

C - Refurbishment works to South elevation facades 50% complete.
C - Refurbishment works to South elevation balconies 50% complete.


























D - Crash deck and cradles installed to North elevation







































C - Refurbishment works to West elevation facades and balconies 50% complete. Crane location to lift cradles onto roof of block D.








































































C - Refurbishment works to South elevation facades and balconies complete. Refurbishment to soffits 50% complete.


















C - Refurbishment works to West elevation facades 50% complete.
C - Refurbishment works to West elevation balconies 50% complete.
C - Refurbishment works to South elevation facades and balconies complete.
C - Refurbishment to South elevation soffits 50% complete.











Block D North Elevation

D - Crash deck and cradles installed to North elevation






C - Refurbishment works to West elevation facades and balconies complete. Crash deck and cradles removed.






D - Refurbishment works to North elevation facades and balconies 50% complete.





























































































































C - Refurbishment to soffits complete. Crash deck and cradles removed.




D - Crash deck and cradles installed to East elevation













C - Refurbishment works to West elevation facades complete.
C - Refurbishment works to West elevation balconies complete.
C - West elevation crash deck and cradles removed.




C - Refurbishment to soffits complete. Crash deck and cradles removed.
D - Crash deck and cradles installed to East elevation




















































































































































D - Crash deck and cradles installed to South elevation
D - Refurbishment works to East elevation facades 50% completed and balconies complete.







Dto North elevation facades complete. Dto North elevation balconies complete.











D - Refurbishment works to North elevation soffits 50% complete. D - Refurbishment works to East elevation facades complete. Crash deck and cradles removed.













































































































































D - Refurbishment works to South elevation facades and balconies 50% complete
D - Refurbishment works to East elevation facades complete. Crash deck and cradles removed.






D - Refurbishment works to North elevation soffits 50% complete.

D - Crash deck and cradles installed to 50% of West elevation











D - Refurbishment works to North elevation soffits complete. Crash deck and cradles removed.





























































































































D - Crash deck and cradles installed to West elevation. Refurbishment works to West elevation 30% complete.


D - Refurbishment works to South elevation facades and balconies complete. Works to soffits 20% complete.















D - Refurbishment works to South elevation facades complete.
D - Refurbishment works to South elevation balconies complete.
D - South elevation Works to soffits 20% complete.
D - East elevation complete.






D - Refurbishment works to North elevation soffits complete.
D - North elevation crash deck and cradles removed.

D - Crash deck and cradles installed
D - Refurbishment works 30% complete.








































































































































D - Refurbishment works to West elevation 60% complete.




D - Refurbishment works to South elevation soffits complete. Crash deck and cradles removed.













D - South elevation Works to soffits complete.
D - South elevation crash deck and cradles removed.
D - East elevation complete.






D - North elevation complete.

D West elevation
D - Refurbishment works to West elevation 60% complete.