CRL Contract 3 Aotea Utility Relocation Work Trees and Vegetation Delivery Work Plan CRL-AOT-RME-LKA-PLN-800011

Revision: 0 30 August 2019

Page 1

| Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan

Trees and Vegetation Delivery Work Plan CRL-AOT-RME-LKA-PLN-800011 This document is uncontrolled when printed. This document should be printed in colour

Revision Status Revision

Issue Date

Major Changes

Changed By

0

30 AUG 2019

Issue revision

A. Chaffe

Approval Status Name/Title Prepared by:

Angelina Chaffe Environmental Scientist

Reviewed by:

Alisdair Simpson Senior Planner

Controlled by:

Fiona Davies Associate Director - Environment

Approved by:

Peter Roan Consents lead – Link Alliance

Page 2

| Trees and Vegetation Delivery Work Plan

Signature

Date

Approved By


Trees and Vegetation Delivery Work Plan

Table of contents 1. Introduction ................................................................................................4 1.1

Purpose and Scope ............................................................................................................ 4

1.2

Designation Condition Requirements................................................................................ 5

2. Utility Relocation Overview ........................................................................6 2.1

Utility Relocation Description............................................................................................ 6

2.2

Utility Relocation Works.................................................................................................... 6

2.3

Construction Methodology................................................................................................ 8

2.4

Project Programme............................................................................................................ 9

2.5

Hours of Operation............................................................................................................ 9

2.6

Site Layouts ....................................................................................................................... 9

3. Roles and Responsibilities...........................................................................9 4. Affected Trees and Vegetation .................................................................10 4.1

Trees requiring Removal.................................................................................................. 10

4.1.1.

Transplanting of Removed Trees............................................................................... 11

5. Mitigation Measures.................................................................................12 5.1

Trees Requiring Permanent Removal .............................................................................. 12

5.2

Tree Replacement ........................................................................................................... 12

5.3

Tree Requiring Replanting ............................................................................................... 13

6. Consultation..............................................................................................13 7. Conclusion.................................................................................................14

Page 3

| Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan

1. Introduction The City Rail Link (CRL) project comprises the construction, operation and maintenance of a 3.4km twin-tunnel underground passenger railway, running between Britomart Station and the North Auckland Line (NAL) in the vicinity of Mt Eden Station. The proposed works include the construction of two underground stations, with a depth of up to 42 metres below ground. It will transform the downtown Britomart Station into a two-way through-station, allowing it to double in capacity. In 2017, City Rail Link Limited (CRLL) submitted an outline plan for works under CRL Designation 1 (Auckland Unitary Plan ref. 2500-1) to enable canopy removal and utility relocation works within the Aotea Station area, along the western side of Albert Street between Victoria Street West and Wellesley Street West. This outline plan was accepted by Auckland Council without changes (ref. OPW60310921). Canopy removal works are currently being undertaken. Additional utility works are required beyond the footprint of the approved works. As such, CRLL is seeking authorisation for the works beyond that which are currently authorised. This Trees and Vegetation Delivery Works Plan (TV DWP) has been prepared by AECOM New Zealand Limited (AECOM) and forms part of the Construction Environmental Management Plan (CEMP) for the additional utility relocation works. The trees within the utility relocation works area are required to be removed to allow the works to be undertaken.

1.1

Purpose and Scope

The existing network of underground utilities around the proposed Aotea Station will need to be permanently relocated prior to construction of the station. It is proposed to undertake the utility relocation works in 3 stages. For all stages the main element of the works is the formation of temporary trenches within footpaths to allow installation of new ducts and pipes for utility services. Once the ducts and pipes are installed the trenches will be backfilled and the footpath reinstated. The trenches will generally be 1m to 1.8m wide with an average depth of 1.5m to 3m. The utility relocation works will relate to electrical, telecommunication, gas, potable water, stormwater and wastewater assets. The purpose of this TV DWP is to describe the processes and practices to be implemented to manage adverse effects resulting from the removal of trees and vegetation associated with the utility works beyond that which are authorised. Condition 55.2 of CRL Designation 1 states that the objective of a TV DWP is to avoid the removal of scheduled trees as far as practicable. While there are no scheduled trees within the works area, construction works will require the removal of trees and it is necessary to mitigate the adverse effects of construction on trees. This TV DWP identifies: 路 路 路 路

Page 4

Trees that will require removal within the Project area; Trees requiring protection from construction works; Mitigation and planting plans; and Monitoring and reporting requirements.

| Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan A Community Liaison Group (CLG) meeting for Aotea Stage 1-3 Utility Relocation works was held on Monday 5th August 2019 from 4pm – 5:30pm. No comments were received from the CLG in relation to the TVDWP. A record of consultation outcomes (CLG and Independent Peer Review) is included in Appendix A:.

1.2 Designation Condition Requirements Table 1 identifies the conditions of CRL Designation 1 that specify what is to be addressed by the TV DWP, and in turn which sections of the TV DWP address these conditions. Table 1 TV

DWP conditions and the relevant sections of this document

Condition Number

Condition

55.1

A Trees and Vegetation DWP shall be prepared to manage the adverse effects from the removal of trees and vegetation during the construction of the City Rail Link or any part of it.

55.2

The objective of the Trees and Vegetation DWP is to avoid the removal of scheduled trees as far as practicable. Where trees are identified for removal in surface works the Requiring Authority will remedy or mitigate the adverse effects of construction on trees and vegetation.

55.3

To achieve the above objective the following shall be included in the Trees and Vegetation DWP and implemented as required:

Page 5

Relevant Section

1.1

(a) Confirmation of the trees to be removed due to surface construction works and whether it is appropriate and feasible to relocate or store these trees for replanting. The removal of scheduled trees which form a significant group should only be undertaken as a last resort;

4.1

(b) A list of trees, which due to being in proximity to construction works, have root systems and / or foliage within and / or overhanging the surface designation footprint, and the methods to be used, where practicable, to protect these trees from construction works;

4.1

(c) Cross references to the Urban Design DWP and the proposed mitigation of any tree / vegetation removal through replanting trees at a 1:1 ratio, re-instatement of the area, and other methods. In preparing the Trees and Vegetation DWP, the Requiring Authority shall seek input from the Auckland Council Parks Department with regard to tree species / vegetation selection, tree pit construction where deemed necessary, and the positioning of replacement trees and from directly affected land owners with regards to preferences for any replacement planting for vegetation / trees removed from private property or for any replacement planting on private property;

5

(d) Other methods to be used to monitor and report on the management of the adverse effects from tree / vegetation removal;

5

(e) Cross references to the specific sections in the Communication and Consultation Plan which detail how the Auckland Council Parks Department, mana whenua (see condition 8) are consulted, and communication with the general public on the management of the adverse effects relating to the removal of trees and vegetation.

6

| Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan

2. Utility Relocation Overview This section presents a summary of the utility relocation works in relation to the matters required to be addressed by the TV DWP. A detailed description of the construction works is provided in the CEMP.

2.1 Utility Relocation Description The project site applicable to this DWP is located in Auckland City Centre, within the road corridors of Albert Street, Victoria Street West and Kingston Street (as illustrated in Figure 1). The site adjoins the project area of the existing outline plan for canopy removal and utility relocation works (OPW60310921). Figure 1 Site Location

The area surrounding the project site is a dense urban environment with a built form comprised of medium to high rise buildings. Common land uses in the project area include commercial offices and services, residential apartments, retail, civic, hospitality, hotel accommodation and car parking. Along Albert Street multiple active construction sites are present, including works related to the CRL project as well as other private developments. Buildings adjoin much of the project site boundary (road corridor) forming active frontages that provide access to private property and businesses. The project site accommodates high volumes of pedestrian and vehicle movements, both for residential and business purposes. Albert Street and Victoria Street West are classified as a primary arterial roads and Kingston Street and Durham Street West are classified as local roads. Due to the CRL works, Albert Street is subject to temporary traffic management procedures, and is currently operating with one lane in each direction.

2.2 Utility Relocation Works The existing network of underground utilities around the proposed Aotea Station will need to be permanently relocated prior to construction of the station. It is proposed to undertake the utility relocation works in 3 stages.

Page 6

| Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan For all stages the main element of the works is the formation of temporary trenches within footpaths to allow installation of new ducting and pipework for utility services. Once the ducting/pipework is installed the trenches are to be backfilled with the footpath reinstated. The trenches will generally be 1m to 1.8m wide with an average depth of 1.5m to 3m. The utility relocation works will relate to electrical, telecommunication, gas, potable water, stormwater and wastewater assets. Table 2 provides a summary of works proposed for each stage. Table 2 Proposed works

Stage Stage 1

Stage 2

Stage 3

Details of Works

Duration of Works (approximate)

Works will be located along the footpaths of Albert Street, between Wyndham Street and Victoria Street, extending into part of Kingston Street and Victoria Street and on the northern slip lane from Albert Street to Durham Street. Trenching along Victoria Street will be to a depth of 1.5m. All other trenches will be around 2.5m to 3m in depth. The total length of trenches constructed will be approximately 340m resulting in approximately 1350m³ of spoil being removed. Works will be located along the footpath of Victoria Street, between Albert Street and Elliott Street (on the south side of the street) with trenching being around 1.5m in depth. Between Victoria Street and Kingston Street, on the western side of Albert Street, trenching will be around 2.5m in depth. A support site compound will be provided in part of the car park of Bledisloe House (details provided below). The total length of trenches constructed will be approximately 160m resulting in approximately 480m³ of spoil being removed. Works will be located along the east side footpath of Albert Street (between the top of the ramp from Durham Street to the corner of Victoria Street) and the north side footpath of Victoria Street, between Albert Street and Elliott Street. Works will also be undertaken on the north side of Victoria Street, between Federal Street and Albert Street. The total length of trenches constructed will be approximately 180m resulting in approximately 585m³ of spoil being removed. Total length of 680m of trench resulting in approximately 2,415m³ of spoil being removed.

3 months (September 2019 – November 2019)

2 months (November 2019 – December 2019)

1.5 months (December 2019 / January 2020 – March 2020)

Approx. 6 months

In addition, a temporary construction site compound (Figure 2 Indicative layout of the Stage 2 Site Compound) will be formed on the corner of Wellesley Street and Mayoral Drive in part of the Bledisloe House car park. This compound will be within the project designation boundary and will be established approximately from October 2019 (Stage 2), until March 2020. This site compound will be occupied by storage containers, the objective of the site compound is to provide a site that can be used as a rest area for workforce staff, and house equipment and vehicles during the works. Temporary fencing will be used to delineate the site, along with Link Alliance branded mesh scrim. Vehicle access will be via the existing entrance off Mayoral Drive and through the gate as marked on the plan. Containers are likely to include machinery equipment and a total of up to 1,200L (6x 20L drums) of diesel in bunds.

Page 7

| Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan

Figure 2 Indicative layout of the Stage 2 Site Compound

Detailed site layouts for each stage of the works have been provided in Appendix C of the CEMP addendum which also informs the location of the construction site compound.

2.3 Construction Methodology The construction methodology to be used for the proposed works will generally be based on the methodology approved for the utility relocation works along the west side of Albert Street, between Victoria Street and Wellesley Street (OPW60310921). Full details on the construction methodology is provided in the Construction Environmental Management Plan (CEMP) addendum. In summary, it is proposed to undertake utility relocation works for electrical, telecommunication, gas, potable water, stormwater and wastewater assets. Temporary trenches are to be formed in the footpath to a depth of around 1.5m to 3m with a width of 1m to 1.8m. Once the trench is formed, bedding will be placed in the trench, with the new utility ducting/pipework installed. Once installed, the trench will be backfilled with the surface of the footpath reinstated. The table below provides a summary of the activities and equipment for the works. Table 1 Construction methodology summary Activity

Equipment and Materials

Identify and mark-out position of trenches

Truck, hand held service locator, survey equipment

Saw cut and remove existing pavement/ hardstanding.

Concrete saw, handheld concrete breaker (only where necessary), excavator, truck

Expose and support existing services to 1.5m depth.

Hydro vac, excavator, normal excavator, truck

Lay new power and communication ducts, place and compact trench backfill

Trucks, plate compactor (no vibrating rollers)

Page 8

| Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan

2.4 Project Programme The Project is anticipated to take approximately 6 months to complete based on knowledge of underground services. Should complexity or additional services be encountered during the course of the Project, then the Project duration will extend beyond the 6-month time period, by around 3 months.

2.5 Hours of Operation It is anticipated that construction work will be undertaken between 0700hrs to 1900hrs Monday to Saturday. Limited construction works may be undertaken beyond 1900hrs, however this would not be a general occurrence and will be done in accordance with the Project conditions.

2.6 Site Layouts Detailed site layouts for each stage of the works have been provided in Appendix C of the CEMP addendum. The site layout shows the location of works, construction vehicle access points, traffic management layouts, position of worker amenity buildings, pedestrian access, and access points for properties surrounding the work site.

3. Roles and Responsibilities The key personnel responsible for this TV DWP are identified in Table 2. All site personnel are also responsible for following the requirements of the TV DWP. A suitably qualified and experienced practitioner in the safe removal of trees has been appointed for environmental controls and monitoring programmes relevant to affected trees. This will be undertaken by JFC Limited. Sam Lockie is the main point of contact for JFC Limited; Email sam.lockie@jfcltd.co.nz, phone 027 261 4580. Table 2 TV DWP responsibilities Organisation Construction Contractor (Link Alliance)

Role Project Director/ Construction Manager

Environmental Sustainability Planning Manager (ESP)

Engagement and Communications Manager Environmental and Sustainability Manager (ESM) Page 9

| Trees and Vegetation Delivery Work Plan

Responsibilities · Construction delivery · Ensuring Site personnel adhere to the CEMP and delivery work plans. · Providing project progress/milestone information to Link Alliance for briefings and CLG meetings. · Leading the response to issues management and crisis management. · Ensuring that subcontractors adhere to the Project communication protocols and procedures. · Leading the process and providing expertise in specialist areas. · Alerting the Engagement and Communication Manager to stakeholder groups, individuals or issues that need attention. · Providing technical information to Link Alliance for briefings and CLG meetings. · Liaise regularly with the project affected community. · Weekly Inspection, auditing and checking of environmental management practices and procedures.


Trees and Vegetation Delivery Work Plan Project and Site Engineers

¡

Daily Site Inspection (including environmental monitoring).

4. Affected Trees and Vegetation A Tree Assessment1 was prepared in August 2012 and formed part of the Notice of Requirement (NoR) for the CRL designation. The report found that while the Project will affect a number of trees that are located within the surface designation area, most of the affected trees are exotic street trees. There are no scheduled trees within the Project footprint, or in proximity. Eight trees identified on Albert Street, between Victoria Street and Kingston Street, and Victoria Street West will be impacted by the proposed utility relocation works. These are primarily comprised of evergreen magnolias (Magnolia grandiflora).

4.1 Trees requiring Removal The tree numbering system used in this plan is consistent with that used in the Tree Assessment1 and TV DWP prepared for the Contract 2 works2. This includes five trees on Albert Street which were considered in the Tree Assessment1 (Trees T29-33) and three additional trees on Victoria Street West (X3-5) which were not included in the original assessment. These are shown in Figure 3.

Figure 3 Trees impacted by proposed utility relocation works

Due to the nature of the utility relocation works, all trees that are within the construction footprint are required to be removed. This includes trees T29, T30, T31, T32, T33, X3, X4 and X5. These are described in Table 3.

1

Boffa Miskell. (2012). City Rail Link Tree Assessment. Report prepared for Auckland Transport, dated August 2012. 2 AECOM. (2016). Enabling Works Contract 2: Trees and Vegetation Delivery Work Plan. Report prepared for Auckland Transport, dated June 2016. Page 10

| Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan Table 3 Trees impacted by the Project

Tree ID

Common Tree Name

Botanical Name

Scheduled

Tree Condition

Estimated height (m)

Project Effect

T29

Evergeen Magnolia

Magnolia grandiflora

No

Good

10

Remove

Transplant not possible. Tree to be cut down and replaced through urban redesign

T30

Evergeen Magnolia

Magnolia grandiflora

No

Fair

8

Remove

Transplant not possible. Tree to be cut down and replaced through urban redesign

T31

Evergeen Magnolia

Magnolia grandiflora

No

Good

9

Remove

Transplant not possible. Tree to be cut down and replaced through urban redesign

T32

Evergeen Magnolia

Magnolia grandiflora

No

Good

9

Remove

Transplant not possible. Tree to be cut down and replaced through urban redesign

T33

Oriental Plane

Plantanus orientalis

No

Poor

12

Remove/ transplant

X3

Evergeen Magnolia

Magnolia grandiflora

No

Fair

7

Remove

Transplant not possible. Tree to be cut down and replaced through urban redesign

X4

Evergeen Magnolia

Magnolia grandiflora

No

Good

10

Remove

Transplant not possible. Tree to be cut down and replaced through urban redesign

X5

Evergeen Magnolia

Magnolia grandiflora

No

Good

10

Remove

Transplant not possible. Tree to be cut down and replaced through urban redesign

Mitigation Measures

Temporary transplant and replant at existing location following completion of works

4.1.1. Transplanting of Removed Trees Consideration has been given to transplanting all eight of the impacted trees to a new location as an alternative to cutting them down; however, due to the size of the trees it is likely that the root mass of most of these trees are tangled with the underground utilities (power, water, communications, sewage, etc.). As a result, it is generally considered impractical and unsafe to attempt to extract the intact root ball of each tree. Due to the difficulties associated with the removal of intact root balls, all except one of the eight identified trees scheduled for removal in Table 3 are required to be cut down to allow careful excavation and relocation of underground utilities. While tree T33 is considered to be in poor condition1 and transplanting (essentially meaning ‘relocation’) is not recommended, due to community values associated with this tree, provisions will be made to attempt the temporary transplantation of T33 and replanting at its current location following the completion of works. Referred to as ‘The Harvey Tree’, this Oriental Plane (Plantanus orientalis) was planted by a local landowner around the 1970s and is accompanied by a plaque. The tree is not otherwise scheduled or identified as notable in the Auckland Unitary Plan Operative in Part (AUP(OP)). It is understood that the Harvey Tree has importance within the local community for Page 11

| Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan its location on the corner of Albert Street and Victoria Street West (known as ‘Martha’s Corner’) and due to being planted from a cutting transported from France by Mr. Les Harvey in the 1970’s. For these reasons the tree has been identified for relocation rather than removal. Although not on any heritage schedule, the tree is considered to form part of Auckland’s history. Refer to Section 5.3 for the required mitigation measures. The methodology and management plans accompanying the proposed relocation works for the Harvey Tree will be detailed through an Outline Plan of Works Waiver and falls outside of the scope of this TVDWP. It is noted a cutting of the Harvey Tree has been successfully propagated and will provide a suitable replacement tree, should the relocation process fail.

5. Mitigation Measures Due to the requirements to remove trees throughout the Project footprint, an adverse effect on the local treescape would result if no mitigation measures are implemented. In addition, mitigation measures will be put in place to allow tree T33 to be transplanted following completion of works.

5.1 Trees Requiring Permanent Removal The removal of trees T29, T30, T31, T32, X3, X4 and X5 should be undertaken by a suitably qualified and experienced arborist. The approach used will be informed by the arborist in accordance with site observations, such as surrounding the proximity of surrounding buildings, tree size and overall condition. The methodologies implemented may include: · · ·

Removal should be staged whereby the outer limbs are removed first, followed by inner limbs and the main trunk. Depending on the location of utility lines, tree stumps should either be dug out or ground in situ. Removed tree debris will either be mulched onsite or removed for mulching offsite, depending on which is more practicable.

The methodology for removing tree T33 is provided for in Section 5.3.

5.2 Tree Replacement Replacement planting will be required for seven of the eight trees identified for removal in Figure 2. A replanting plan will be identified in the Urban Design DWP for the reinstatement of the area and will include (but may not be limited to) the following: · · · ·

· Page 12

Replanting of semi-mature trees at least 1:1 ratio. Trees will be inspected and approved by the Community Facilities Arborist prior to planting. The area required to be reinstated. The opportunity to include appropriate native species in the replacement and landscape plantings. Documentation of the input from the Auckland Council Parks Department with regard to tree species / vegetation selection, tree pit construction and positioning of replacement trees. An outline of the maintenance periods and responsibilities (i.e. the Requiring Authority for a period of five years for specimen trees and 3 years for all other landscape planting). | Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan ·

Consultation outputs (refer Section 6 of this TV DWP).

5.3 Tree Requiring Replanting To ensure the safe and successful transplanting of tree T33, the removal and transplantation should be undertaken by a suitably qualified and experienced arborist. The methodologies employed are to be informed by the arborist and will be subject to the condition of the tree and root system following further investigation. As previously outlined, the tree transplant works will be detailed through an Outline Plan of Works Waiver. This Outline Plan of Works Waiver is accompanied by a proposed Tree removal and maintenance (for offsite storage) methodology by Jeff Fell (Arborist at Specimen Trees Limited), a temporary traffic and parking memo, a construction noise and vibration memo and an erosion and sediment control plan memo. The methodologies implemented should include the following (where practical): ·

· · ·

Prior to removing the tree an interim receptor site should be identified, either within or outside the Project Area. If this is not practicable, the trees should be properly maintained at a transit nursery. In order to reduce stress on the tree, removal and replanting at its current location should be undertaken in autumn after the leaves have fallen or in spring before new buds develop. Prepare the tree for removal by digging a trench around the root ball and tying up lower branches to protect them. Outer roots should be trimmed as required. Following removal from its current location the root ball should be wrapped in damp hessian. The tree should be replanted immediately; however, if this is not possible the tree should be kept in a cool, shaded place and the roots kept moist until it can be replanted.

The methodologies employed should follow industry best practice for the transplanting of mature trees. Prior to the removal and replanting of tree T33, discussions should be held with interested parties (such as Auckland Council’s Heritage Advisor and adjacent land owners affected by the works) to determine the significance of the tree and appropriate management measures. As previously indicated, a cutting of the Harvey Tree has been successfully propagated and will serve as a replacement tree should the Harvey Tree should not survive the temporary transplant and replanting process.

6. Consultation A Communication and Consultation Plan (CCP) has been prepared for the Project works (Appendix K of the Project CEMP). Section 6 of the CCP outlines the procedure undertaken in order to ensure that the Link Alliance undertakes consultation with the Auckland Council Parks Department and mana whenua. It also details the general communication that will be undertaken with the general public on the management of the adverse effects relating to the removal of trees within the Project area. Where agreed, the feedback from this consultation process will be incorporated into the Urban Design Delivery Work Plan for the reinstatement of the public realm following construction of the CRL in this location. Where feedback has been considered, but not incorporated into the Urban Design Delivery Work Plan, reasons must be provided to the interested party as to why specific suggestions could not be incorporated into reinstatement plans. Page 13

| Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan

7. Conclusion Eight trees identified on Albert Street, between Victoria Street and Kingston Street, and Victoria Street West will be impacted by the proposed utility relocation works. These are primarily comprised of evergreen magnolias. Due to the requirements to remove or transplant trees throughout the Project footprint, an adverse effect on the local treescape would result if no mitigation measures are implemented. This plan describes the strategies needed to manage these adverse effects.

Page 14

| Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan

List of Appendices Appendix A: Record of CLG and independent peer review comments .................... 16

Page 15

| Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan

Appendix A: Record of CLG and independent peer review comments CLG Comments A Community Liaison Group (CLG) meeting for Aotea Stage 1-3 Utility Relocation works was held on Monday 5th August 2019 from 4pm – 5:30pm. No comments were received from the CLG in relation to the TVDWP. Comment ID

Date

Time

Forum

5/08/2019

1600 - 1730hrs

CLG

Contributor

Comment

Resolution

No comments recorded.

No Change to DWP

Independent Peer Review Page no.

DWP section

Paragraph/ sentence

Comment

Resolution

11

Table 3

X 3) comments within table)

Tree condition details ‘Good’ A recent assessment of the tree revealed that the health is fair.

DWP (Table 3) updated to reflect Fair health status.

11

4.1.1

Consideration has been given to transplanting all eight of the impacted trees to a new location as an alternative to cutting them down; however, due to the size of the trees it is likely that the root mass of most of these trees are tangled with the underground utilities (power, water, communications, sewage, etc.). As a result, it is generally considered impractical and unsafe to attempt to extract the intact root ball of each tree. Due to the difficulties associated with the removal of intact root balls, all except one of the eight identified trees scheduled for removal in Table 3 are required to be cut down to allow careful excavation and relocation of

Notwithstanding the ‘heritage’ value of T33, why is it impractical and unsafe to remove the 8 Magnolia trees when T33 is the larger tree of the group and is growing in the same conditions. Surely the removal of T33 will find the same obstacles, challenges and will require the same removal methodologies that would be required to remove the 8 other trees.

No change to DWP. None of the trees are really suitable for transplanting, however given the requests from community relating to the heritage issue, more extreme efforts will be made with this tree than what would normally be done. The other trees are not notable and are not native and have no community attachment. Therefore the best approach is considered to replace them with a 1:1 ratio.

Page 16

| Trees and Vegetation Delivery Work Plan


Trees and Vegetation Delivery Work Plan underground utilities. 12

5.2. first bullet point

·

Replanting of trees at least 1:1 ratio. Trees to be 4-5m height in ground, with single clear trunk to minimum 1.6m, trunk to be no less than 50mm in diameter at 300mm above ground, in good robust health with suitably sized root ball.

I don’t think such a standard should or could be ingrained into any conditions.

Update DWP. Replace wording with: ‘Replanting

No change to DWP as this is what the conditions state and the text reflects the conditions.

13

First bullet point on page and last paragraph

The use of the Auckland Council Parks Department.

Correct me if I’m wrong, is it not Community Facilities – the Parks Department doesn’t exist anymore.

13

5.3 – 2nd paragraph

As previously outlined, the tree transplant works will be detailed through an Outline Plan of Works Waiver. This Outline Plan of Works Waiver is accompanied by a proposed Tree removal methodology by Jeff Fell (Arborist at Specimen Trees Limited), a temporary traffic and parking memo, a construction noise and vibration memo and an erosion and sediment control plan memo.

Tree removal methodology Should be expanded to include maintenance methodology while the tree is being stored off site.

of semi-mature trees at least 1:1 ratio. Trees will be inspected and approved by the Community Facilities Arborist prior to planting.’

Update DWP text to: ‘This Outline Plan of Works

Waiver is accompanied by a proposed Tree removal and maintenance (for offsite storage) methodology by Jeff Fell (Arborist at Specimen Trees Limited).’

13

5.3 – 2nd bullet point

·

In order to reduce stress on the tree, removal and replanting at its current location should be undertaken in autumn after the leaves have fallen or in spring before new buds develop.

Need to check if this is possible as the staged works may fall outside of this required timeframe.

No change to DWP. Although the works are staged, the tree removal and replanting can be planned around the works that are programmed if needed to meet these requirements.

13

5.3 – 3rd bullet point

·

Prepare the tree for removal by digging a trench around the root ball and tying up lower branches to protect them. Outer roots should be trimmed as required. Sufficient time should be

Will there be sufficient time from when the rootball is formed and roots cut for the tree to develop new roots before uplifting? I would suggest

DWP text updated to read: ‘The methodologies implemented

Page 17

| Trees and Vegetation Delivery Work Plan

should include the following (where practical): And ‘Prepare the tree for removal by digging a trench around the root ball and tying up lower branches to protect them. Outer roots


Trees and Vegetation Delivery Work Plan

13

Page 18

5.3 – 4th bullet point

¡

allowed between preparation and final lifting of the tree to enable the development of new roots capable of sustaining and continuing growth following removal.

that the preparation of the rootball and uplifting of the tree will be undertaken in a very short timeframe.

should be trimmed as required. ‘

Following removal from its current location the root ball should be wrapped in damp hessian. The tree should be replanted immediately; however, if this is not possible the tree should be kept in a cool, shaded place and the roots kept moist until it can be replanted.

Unlikely that the tree will be replanted immediately and a cool, shaded area is not necessary.

No change to DWP. Comment noted, but we think this is the best advice.