Normanby Road Early Works Social Impact and Business Disruption Delivery Work Plan CRL-MTE-RME-LKA-PLN-800009

Revision: 001 Date: 21 February 2020

Page 1

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

Social Impact and Business Disruption Delivery Work Plan CRL-MTE-RME-LKA-PLN-800009 This document is uncontrolled when printed. This document should be printed in colour

Revision Status Revision

Date

Version details

Prepared By

Approved By

A00

19/11/19

CLG Review

John Daly Hilary Konigkramer Duncan Whyte

Peter Roan

A01

26/11/19

Auckland Council/IPR Review

John Daly Hilary Konigkramer

Kim Hardy

000

17/12/19

Final for submission

John Daly Hilary Konigkramer

Kim Hardy

001

21/02/20

Final

John Daly Hilary Konigkramer

Kim Hardy

Approval Status Name/Title

Signature

Date

Prepared By

John Daly Principal Author Principal Planner & Social Scientist

18/12/19

Prepared by:

Hilary Konigkramer – Co-author Social Scientist

18/12/19

Reviewed and controlled by:

Kim Hardy Technical Director SIBD Discipline Lead

18/12/19

Approved by:

Peter Roan Consenting Lead – Link Alliance

18/12/19

Page 2

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

Table of contents 1. Introduction ................................................................................................ 6 1.1

Overview of CRL works in Mt Eden .................................................................................... 6

1.2

Cumulative SIBD Effects..................................................................................................... 7

1.3

Purpose of the SIBD DWP .................................................................................................. 7

2. SIBD Methodology and CRL Designation Conditions .................................. 8 2.1

SIBD DWP Authors............................................................................................................. 8

2.2

IAIA Guidance for Assessing and Managing Social impacts of Projects (2015) ................... 8

2.3

International Association for Public Participation ............................................................. 9

2.4

CRL Designation Conditions ............................................................................................... 9

2.5

SIBD DWP Review and Updates ....................................................................................... 13

3. Normanby Road Early Works .................................................................... 14 3.1

Overview of Works .......................................................................................................... 14

3.2

Construction Methodology .............................................................................................. 15

4. SIBD Assessment and Community Profile ................................................. 17 4.1

CRL NOR Social Impact Assessment Summary ................................................................. 17

4.2

The Impacted Community Profile .................................................................................... 18

4.2.1.

The SIA Description of the Social Environment.......................................................... 18

4.2.2.

Mt Eden Local Profile ................................................................................................ 18

4.2.3.

Demographic Profile ................................................................................................. 19

4.2.4.

Local Community Planning........................................................................................ 21

4.2.5.

Uptown Business Association ................................................................................... 22

4.2.6.

CRL Media Coverage ................................................................................................. 22

5. Consultation and Engagement .................................................................. 23 5.1

Introduction .................................................................................................................... 23

5.2

Establishing the Affected Community.............................................................................. 24

5.3

Engagement with Affected Parties .................................................................................. 25

5.4

Face to face Engagement with Affected Parties............................................................... 27

5.4.1.

Engagement Material ............................................................................................... 28

6. The Affected Community’s Feedback ....................................................... 29

Page 3

6.1

Uptown Business Association .......................................................................................... 30

6.2

Mt Eden Corrections Facility ............................................................................................ 30

6.3

Tram Lease Limited.......................................................................................................... 30

6.4

Dilworth Trust Board ....................................................................................................... 30

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan 6.5

Residential Properties ..................................................................................................... 31

6.6

Noise and Vibration Sensitive Receptors ......................................................................... 31

6.7

Open Information Sessions.............................................................................................. 32

6.8

Community and Business Liaison Group .......................................................................... 32

6.9

Summary of Key Issues .................................................................................................... 33

7. Summary of Issues Identified and Response Provided in Technical Assessments .................................................................................................... 34 8. Mitigation Implementation Plan............................................................... 36 8.1

Introduction .................................................................................................................... 36

8.2

Roles and Responsibilities ............................................................................................... 36

8.3

Compliance with Designation Conditions ........................................................................ 36

8.4

Continuous Up to Date Engagement................................................................................ 37

8.5

Development Response Plan (DRP) ................................................................................. 37

8.6

Contractor Briefings......................................................................................................... 37

8.7

Noise and Vibration Disruption ....................................................................................... 38

8.8

Transport Access and Parking Disruption ........................................................................ 38

8.8.1.

Vehicular Access and On Street Parking .................................................................... 38

8.8.2.

Pedestrian and Cyclist Access ................................................................................... 39

8.8.3.

Public Transport ....................................................................................................... 39

8.8.4.

Transport Disruption Communication Plan ............................................................... 39

8.8.5.

Construction Traffic .................................................................................................. 39

8.9

Utility Disruption ............................................................................................................. 40

8.10 Air Quality ....................................................................................................................... 40 8.11 Amenity ........................................................................................................................... 40 8.12 Community Safety ........................................................................................................... 40 8.13 Health and Wellbeing ...................................................................................................... 41 8.14 Business Disruption ......................................................................................................... 41

9. Issues and Public Enquiries ....................................................................... 43 9.1

Introduction .................................................................................................................... 43

9.2

Queries and Complaints Process ..................................................................................... 43

9.3

Disputes Resolution ......................................................................................................... 43

9.3.1.

Public Works Act 1981 .............................................................................................. 43

10. Reporting .................................................................................................. 45 10.1 SIBD Monitoring Plan ...................................................................................................... 45 Page 4

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan 10.1.1.

Community and Business Liaison Group Reporting ................................................... 45

10.1.2.

Regular Engagement................................................................................................. 45

10.1.3.

Data Sources ............................................................................................................ 45

10.2 Monthly Reporting to Auckland Council .......................................................................... 46 10.3 Annual Report ................................................................................................................. 46

Appendix A: Affected Community Feedback .................................................. 47 Appendix B: Meeting Response Recording Sheet with Questions .................. 56 Appendix C: Information Factsheet and Calling Cards .................................... 58 Appendix D: Record of CLG, Independent Peer Review and Auckland Council Feedback ......................................................................................................... 62 D1. CLG Comments .......................................................................................... 62 D2. IPR Comments ........................................................................................... 63 D3. Auckland Council Comments .................................................................... 72 Appendix E: Development Response Measures ............................................. 75 Appendix F: Project Roles and Responsibilities .............................................. 76 Appendix G: SIBD Monitoring Plan ................................................................. 78

Page 5

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

1. Introduction The City Rail Link (CRL) project comprises the construction, operation and maintenance of a 3.4 km underground passenger railway, running between Britomart Station and the North Auckland Rail Line (NAL) in the vicinity of Mt Eden Station. The CRL also involves the construction of two new underground stations at Aotea and Karangahape and a redeveloped Mt Eden Station (refer to Figure 0-1) The design and construction of the CRL infrastructure between Aotea and Mt Eden Stations is being delivered by the Link Alliance. This Social Impact and Business Disruption Delivery Work Plan (SIBD DWP) has been prepared in relation to early works along and in the vicinity of Normanby Road, hereafter referred as the ‘Normanby Road early works’.

Figure 0-1: CRL Route and Location

1.1 Overview of CRL works in Mt Eden The CRL works in the Mt Eden area involve the construction of the southern section of the tunnel structures and the tie-in to the existing NAL, including the construction of the redeveloped Mt Eden Station. The Mt Eden Active Construction Zone (ACZ) and Construction Support Areas (CSA) for the NAL Mt Eden section is generally located between State Highway 1 (SH1) to the east and Dominion Road to the west. The works in this area include: • • • •

Page 6

Construction of an underground grade separation structure near Mt Eden Station; A new Mt Eden Station building incorporating passenger linkages; Modifications to the existing Mt Eden Station platforms; Road over rail bridges at Mt Eden Road, Normanby Road and Ruru Street with sections of road realignment;

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan • • •

Grade separation structures and the east- and west-facing connections for the existing and new rail lines to pass-over and connect with each other; Pedestrian and cyclist bridge structures at Fenton Street and Porters Avenue; and New road linkages within the reinstated area post-construction.

Given the nature and scale of CRL works in Mt Eden, construction will be undertaken in a staged manner. This SIBD DWP only relates to the Normanby Road early works, as described in Section 3 below.

1.2 Cumulative SIBD Effects The CRL construction works in the Mt Eden Station area are occurring in a staged manner, the scale and location of the combined construction activities do have the potential to generate cumulative SIBD effects that may be perceived as being greater than the individual works package. In recognition of the potential cumulative nature of these impacts, the overall scope of the CRL project has been acknowledged and will be further addressed in the DWPs prepared for the construction activity related to the main works in Mt Eden. SIBD subject matter experts (SMEs) have been cognisant of affected community feedback received for Aotea, Karangahape and Mt Eden Stations, and particularly the feedback collected for the Mt Eden early works SIBD DWP.

1.3 Purpose of the SIBD DWP This SIBD DWP has been prepared to identify measures that will be implemented to mitigate and manage the potential adverse effects on businesses, residents and community services/facilities during the Normanby Road early works. The objective of the SIBD DWP is: •

“to avoid, remedy or mitigate the adverse effects arising from disruption to businesses, residents and community services/facilities so far as reasonably practicable.” It identifies mitigation measures that will be undertaken with regards to the following potential adverse social impact and business disruption effects: • • • • •

Disruption to access for residents and businesses; Temporary loss of street parking during construction; Disruption effects that result or are likely to result in the loss of customers to businesses as a result of the construction activities; Business disruption due to interruption in electricity and communications utilities; and Loss of amenity (as a result of potential dust, noise and vibration, and traffic impacts) for residents, community services and businesses as a result of construction activities.

This SIBD DWP has been prepared in consultation with the community, business owners, affected parties and affected in proximity parties. This SIBD DWP addresses the requirements of CRL designation Condition 61 and will be implemented throughout the construction period. The SIBD DWP has been prepared by Link Alliance and forms part of the Construction Environmental Management Plan (CEMP) for the Normanby Road early works. Page 7

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

2.

SIBD Methodology and CRL Designation Conditions 2.1 SIBD DWP Authors

This SIBD DWP has been prepared by John Daly, Hilary Konigkramer and Duncan Whyte, and has been reviewed by Kim Hardy (technical reviewer). John holds a MA (Hons) in Sociology and a MSc in Urban and Regional Planning. He is a Chartered Member of the Royal Town Planning Institute and a member of the New Zealand Association for Impact Assessment. John has 12 years of professional experience including the preparation of Town Centre Impact Assessments, Environmental Impact Assessment Screening and Statements of Community Involvement for commercial, industrial and hotel development in London, UK; community consultation and engagement for residential development and to inform planning guidance in Scotland and London, UK. Hilary holds a Bachelor of Social Science (Honours) in Environmental Management and has practised as an environmental and social consultant for over 18 years. As a Social Impact Assessment (SIA) specialist, she is skilled in public, community and stakeholder engagement and gained extensive experience in South Africa producing SIAs in a range of sectors including infrastructure, renewable energy, mining, and industrial. Since her relocation to New Zealand in 2019, Hilary has continued her social science career by providing advisory support in the mining sector and conducting a social impact assessment for a component of the Northern Corridor Improvements Project. Duncan holds a Bachelor of Arts (Hons) in History and Geography and a Master of Regional and Resource Planning. Duncan is a Full Member of the New Zealand Planning Institute. Duncan has 24 years of professional experience including consultation and engagement and Environmental Impact Assessment for infrastructure projects in New Zealand and Australia. Kim holds a MSocSci (Hons) in Human Geography and Resources and Environmental Planning. She has been a practising planner for 28 years and is experienced in public and stakeholder engagement, assessing social and cultural impacts of land development and infrastructure projects. Kim completed her Masters Thesis on ‘Effective Public Participation and the Resource Management Act 1991’. She has 10 years’ experience as an Independent Hearings Commissioner and Chairperson and is an experienced statutory planning decision maker. She holds full IAP2 Australasia Certification in Engagement. Kim has been a Full Member of the New Zealand Planning Institute for 24 years and is a member of the New Zealand Association for Impact Assessment.

2.2 IAIA Guidance for Assessing and Managing Social impacts of Projects (2015) To ensure effective and robust practices the ‘International Association for Impact Assessment Social Impact Assessment: Guidance for Assessing and Managing the Social Impacts of Projects’ has informed the preparation of this SIBD DWP. This states: ‘Social Impact Assessment (SIA) is now conceived as being the process of identifying and managing the social issues of project development and includes the effective engagement of affected communities in participatory processes of identification, assessment and management of social impacts. Although SIA is still used as an impact prediction mechanism and decision-making tool in regulatory processes to consider the social impacts in advance of a permitting or licencing decision, Page 8

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan equally more important is the role of SIA in contributing to the ongoing management of social issues throughout the whole project development cycle, from conception to post closure.’1

2.3 International Association for Public Participation To ensure effective communication and consultation practices the International Association for Public Participation engagement spectrum2 has been taken into account for the purposes of engagement with the affected community. Table 2-1 below identifies examples of how the Link Alliance’s approach aligns with the IAP2 spectrum. Those in bold have been employed directly in the preparation of this SIBD DWP. Table 2-1: Alignment with IAP2 Public Participation Spectrum

Inform

Consult

Involve

Collaborate

Website updates

Social media

Social impact assessments

Community information pop-up hub

Mana Whenua Forum

Project newsletters and factsheets

Community and Business Liaison Group (CLG)3

Local Business Association

Local Boards

Opportunities to collaborate may be identified through ongoing engagement, particularly with the Development Response Plan.

Project enquiry email and phone line

Construction notifications

Stakeholder workshops, presentations and briefings

Advisory Boards / Steering Groups

Refer to the Communication and Consultation Plan (CCP) for further details regarding stakeholder identification and consultation.

2.4 CRL Designation Conditions Table 2-2 outlines the CRL designation conditions relevant to the SIBD DWP and where they are addressed in the document. Table 2-2: CRL Designation conditions and location in this SIBD DWP

Condition No.

Condition

Section where addressed in this DWP

61.1

The Requiring Authority shall prepare a Social Impact and Business Disruption DWP. The objective of the Social Impact and Business Disruption DWP is to avoid, remedy or mitigate the adverse effects arising from disruption to

This document

Matter Addressed in another Project DWP

1

International Association for impact Assessment Social impact Assessment, Guidance for Assessing and Managing the Social Impacts of Projects, April 2015, page iv. 2 https://www.iap2.org.au/About-Us/About-IAP2-Australasia-/Spectrum 3

The designation conditions reference the Community Liaison Group (CLG), while the resource consent conditions reference the Community and Business Liaison Group. CLG has been used through this DWP as a common reference for the same group. Page 9 | Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

Condition No.

Condition

Section where addressed in this DWP

Matter Addressed in another Project DWP

businesses, residents and community services/facilities so far as reasonably practicable. 61.2

To achieve this objective the Requiring Authority shall engage a suitably qualified specialist(s) to prepare a Social Impact and Business Disruption DWP to address the following specific issues: a)

61.3

How disruption to access (including pedestrian, cycle, passenger transport and service/private vehicles) for residents, community services and businesses as a result of construction activities will, so far as is reasonably practicable, be avoided, remedied or mitigated;

Section 8.8

b) How the disruption effects that result or are likely to result in the loss of customers to businesses as a result of construction activities will, so far as is reasonably practicable, be avoided, remedied or mitigated;

Section 8.14

c)

n/a4

How the loss and/or relocation of community facilities and the loss or change to catchments associated with these facilities as a result of the property acquisition process particularly to the Chinese Community Centre and Life Centre Church and the temporary loss of car parking at Hopetoun Alpha will be mitigated; and

d) How loss of amenity for residents, community services and businesses as a result of construction activities will be or has been mitigated through the CEMP and other DWPs.

Section 8.11

The Social Impact and Business Disruption DWP shall be prepared in consultation with the community, community facility operators, business owners, affected parties and affected in proximity parties to:

Section 4 and Section 5

a)

Understand client and visitor behaviour and requirements and operational requirements of community facilities and businesses;

Section 4 and Section 5

b) Identify the scale of disruption and adverse effects likely to result to businesses, residents and community services/facilities as a result of construction of the City Rail Link;

Section 4 and Section 5

c)

Section 4 and Section 5

Assess access and servicing requirements and in particular any special needs of residents, community facilities and businesses; and

d) To develop methods to address matters outlined in (b) and (c) above, including:

4

Section 2.1

Section 8.8

Transport, Access and Parking (TAP) DWP

The Chinese Community Centre is no longer located at 101 Mt Eden Road; the Life Church as relocated to another property du e to the pending demolition of the building as part of the C3 works; and Hopetoun Alpha is not in the area to be impacted by the CRL project. Page 10 | Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

Condition No.

61.4

Page 11

Condition

Section where addressed in this DWP

Matter Addressed in another Project DWP

TAP DWP

i.

The measures to maximise opportunities for pedestrian and service access to businesses, residents and social services/facilities that will be maintained during construction, within the practical requirements of the Transport, Access and Parking conditions (Conditions 25 to 30) and the Transport, Access and Parking DWP;

ii.

The measures to mitigate potential severance and loss of business visibility issues by way-finding and supporting signage for pedestrian detours required during construction;

Section 8.14

iii. The measures to promote a safe environment, taking a crime prevention through environmental design approach;

Section 8.12

iv. Other measures to assist businesses and social services/facilities to maintain client/customer accessibility, including but not limited to client/customer information on temporary parking or parking options for access;

Section 8.8

TAP DWP

v.

Section 8.8

TAP DWP

Other measures to assist residents, businesses and social services/facilities to provide for service delivery requirements;

vi. The process (if any) for re-establishment and promotion of normal business operation following construction;

n/a

vii. If appropriate and reasonable, requirements for temporary relocation during construction and/or assistance for relocation (including information to communities using these services and facilities to advise of relocations); and

n/a

viii. The measures to remedy and mitigate the disruption impacts to the community as a result of any closure and/or relocation of community services and facilities required by the Project.

n/a

The Social Impact and Business Disruption DWP shall include: a) A summary of the findings and recommendations of the Social Impact Assessment report (2013);

Section 4

b) A record of the consultation undertaken with the community including specific access and operational requirements of individual businesses and residents including, if relevant, consultation on the necessity for, and the feasibility of, options and requirements for temporary relocation during construction and/or assistance for relocation);

Section 5

c)

Section 8

An implementation plan of the methods to mitigate the disruption effects (as developed in 61.3 above);

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

Condition No.

Condition

Section where addressed in this DWP

Matter Addressed in another Project DWP

d) Reference to any site/business specific mitigation plans that exist (though these may not be included in the DWP);

Section 7 and Section 8

Construction Noise and Vibration (CNV) DWP – Site Specific CNV Management Plans

e) Cross reference to detail on how the CEMP and DWPs have responded to the issues of resident, business and social service/facility accessibility and amenity;

Section 7 and Section 8

f)

Details of on-going consultation with the local community through the Community Liaison Groups to provide updates and information relating to the timing for project works and acquisition;

Section 6.8 and Section 10

g)

Details of best endeavours steps undertaken with regard to acquisition and/or relocation of the Chinese Community Centre and Life Centre Church under the Public Works Act 1981; and

n/a

h) The process for resolution of any disputes or complaints in relation to the management / mitigation of social impacts (including business disruption impacts).

Section 9

61.5

In relation to the site at 32 Normanby Road, the Requiring Authority shall consult with sub-lessees in the presence of the landowner and head lessee when developing site/business specific mitigation plans, unless the sublessee(s) request otherwise.

Section 6.3

61.6

The Social Impact and Business Disruption DWP shall be implemented and complied with for the duration of the construction of the City Rail Link and for up to 12 months following the completion of the Project if required.

Section 8.3

61.7

Suitably qualified independent specialists for the social impact and business disruption mitigation (whose appointment shall be agreed by the Council) shall peer review the Social Impact and Business Disruption DWP pursuant to Condition 11.

Appendix D

61.8

The Requiring Authority shall prepare an annual report on the identification, monitoring, evaluation and management of the effects outlined in the Social Impact and Business Disruption DWP together with a summary of matters raised by the community, and how these have been responded to. The report shall be presented to the Community Liaison Groups.

Section 10 / Appendix G

Page 12

| Normanby Road Early Works

CCP


Social Impact and Business Disruption Delivery Work Plan

2.5 SIBD DWP Review and Updates This SIBD DWP is a live document that will be reviewed as a result of a material change to the project, or to address unforeseen adverse social impact and business disruption effects arising from construction, unresolved complaints or as an outcome from SIBD Monitoring. The review will take into consideration the following: • • • • • • • •

Page 13

Compliance with the designation or consent conditions, the CEMP, DWPs and EMPs (including site specific plans) and material changes to these plans Any significant changes to construction activities or methods Key changes to roles and responsibilities within the Project team Changes in industry best practice standards Changes in legal or other requirements (social and environmental legal requirements, consent conditions, relevant policies, plans, standards, specifications and guidelines) Results of the SIBD Monitoring Plan, and other inspections, monitoring and reporting procedures associated with the management of adverse effects during construction Comments or recommendations from Auckland Council regarding the CEMP, DWPs and EMPs Unresolved complaints and any response to complaints and remedial action taken to address the complaint.

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

3.

Normanby Road Early Works 3.1 Overview of Works

The Normanby Road early works involve demolition of the building at 11 Water Street, establishment of a Construction Support Area (CSA), construction of a temporary pedestrian bridge across the NAL and diversion of temporary and permanent utilities (such as water, wastewater, stormwater, gas, electricity and communications) along and in the vicinity of Normanby Road. The early works are required in advance of the main construction works to provide adequate clearance between the CRL works and network utilities to enable construction of retaining walls, the Normanby Road grade separation bridge and the realigned Normanby Road / Boston Road / Nugent Street roundabout. The Normanby Road early works are planned to extend over seven months, between March 2020 and September 2020. Figure 2.1 shows the area of these works.

Figure 3-1: Extent of the Normanby Road early works area

Refer to the CEMP for a detailed description of the works.

Page 14

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

3.2 Construction Methodology The Normanby Road early works will be divided into stages as described in the CEMP and the Construction Staging Plans dated 10 October 2019 in Appendix B of the CEMP. A summary of the stages is presented in Table 3-1 below. Table 3-1: Normanby Road Early Works - Construction Staging

Stage

Description

Dates

Approximate Duration

Normanby Road Stage 1 – Tree Removal and Utility Relocation

• Establishment of CSA at 14-22 Boston Road, 11 Water Street and partly within 28 Mt Eden Road. • Establishment of alternative car park at 14-22 Boston Road for premises at 32 Normanby Road. • Demolition of northern boundary fence and kerb, tree removal and construction of retaining walls at 32 Normanby Road. • Excavation of utility trench and installation of permanent south sewer line and stormwater line along Normanby Road, 22-24 Normanby Road and 32 Normanby Road. • Installation of private stormwater connections from premises at 32 Normanby Road to the public stormwater line. • Regrade car park area at 32 Normanby Road.

March – April 2020

2 months

Stage 2 – Utility Relocation and Temporary Pedestrian and Utility Bridge

• Construction of piling platforms and piling for the temporary bridge at 32 Normanby Road and 14-22 Boston Road. • Construction of pile caps and removal of piling platforms upon completion. • Complete installation of permanent stormwater line at 32 Normanby Road. • Excavation and installation of permanent north sewer line across 14-22 Boston Road, 11 Water Street and 8-10 Boston Road. • Reinstatement of car park surface and line marking at 32 Normanby Road.

April – May 2020

2 months

Stage 3 Temporary Pedestrian and Utility Bridge, Retaining Wall and Utility Diversion

• Construction of temporary bridge foundations at 1422 Boston Road and 32 Normanby Road. • Construction of retaining wall at the south-western corner of the Normanby Road / Boston Road / Nugent Street roundabout. • Installation of span columns and span truss (with temporary utilities attached) across the NAL rail corridor. • Installation of temporary utilities on span columns.

April – July 2020

4 months

Page 15

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

Stage 4 – Utility Diversion

Page 16

• Excavation of utility trench and installation of temporary gas, water, power and communication lines from the temporary bridge to existing lines. Reinstatement of pavement. • Installation of screens on the temporary bridge.

| Normanby Road Early Works

August – September 2020

2 months


Social Impact and Business Disruption Delivery Work Plan

4. SIBD Assessment and Community Profile 4.1 CRL NOR Social Impact Assessment5 Summary A Social Impact Assessment (SIA) was submitted in support of the Notices of Requirement (NoR) for the CRL designations and is referenced in designation Condition 1. The purpose of the NoR SIA was to provide an assessment of the likely social consequences (benefits and dis-benefits) that may arise because of the CRL project as a whole. The four key areas of potential adverse social impacts arising from construction of the CRL were identified in the NoR SIA as including: 1. Loss or disturbance of community facilities and social services as a result of the proposed works could disrupt people’s way of life and community cohesion. 2. Severance between communities, facilities, residents and businesses, particularly during construction, could impact on people’s way of life and community cohesion. 3. Physical impacts of construction works could impact on people’s health and wellbeing (e.g. as a result of nuisance or disturbance from construction noise, vibration or other discharges, or from the uncertainty/frustration arising from changes in accessibility for people living and working in the areas affected by the construction activity). 4. Impacts on individual tenants and landowners, resulting from issues associated with property purchase, relocation and/or displacement. Additionally, the Traffic Impact Assessment (TIA) referred to in the SIA identified that the adverse temporary effects all relate to the management of the existing road transport network during construction. The key adverse temporary effects include disruptions or inconvenience to: •

Emergency service vehicles;

Bus operators and users (private and public);

Private vehicles;

Couriers and delivery vehicles;

Freight vehicles; and

Cyclists and pedestrians.

The Noise Assessment referred to in the SIA identified that the disruptive and adverse temporary effects relate to construction related noise generated in the areas where surface works are occurring, particularly when works are undertaken at night. The NoR SIA identifies the need for the mitigation of potential adverse impacts. To address social impacts the development of a Social Impact Management Plan was recommended, in conjunction with on-going consultation with key stakeholders and communities of interest. This SIBD DWP has been prepared to address this requirement with regard to the Normanby Road early works. Wider communication will be led by the Link Alliance’s Communications and Engagement team and will align with the CCP. The TAP DWP and the CNV DWP have been prepared to address transport effects and noise and vibration affects respectively.

5

City Rail Link Notice of Requirement: Social Impact Assessment Prepared for Auckland Transport by Beca Carter Hollings and Ferner Ltd 18 April 2013 [also dated 19 April 2011]. Page 17 | Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan The NoR SIA also identified a number of positive effects associated with CRL once the line and stations are operational. These include: • • •

Increased train capacity improving accessibility and connectivity for people, Increased commuter access stimulating economic development and enhancing commuter well-being. Being a catalyst for inner city redevelopment, resulting in land use intensification and regeneration of central city areas. With positive effects including improved quality of environment, economic opportunities and opportunities for increased community development in the city centre area.

It is however acknowledged that these effects may not be apparent or tangible to the affected community during the construction of the Normanby Road early works.

4.2 The Impacted Community Profile 4.2.1. The SIA Description of the Social Environment A desktop scoping and profiling exercise was undertaken as part of the NoR SIA. The findings are summarised below, and a further profiling exercise was undertaken for this early works SIBD DWP as discussed below. A summary of the NoR SIA Land Use Survey results characterised the Mt Eden area as: • •

The most commonly occurring land use identified in this area was Retail (including shops and cafes), followed by Commercial Office. ‘Other’ activities (such as educational facilities and car parks) as well as the Chinese Community Centre also featured in this area.

The NoR SIA identified social infrastructure within the Mt Eden area. On review it was confirmed that none of the social infrastructure identified lies within the area that will be affected by the Normanby Road early works. The works will not compromise access to social infrastructure for the surrounding areas. The SIBD team undertook a further assessment to ensure the Link Alliance’s understanding of the potentially impacted community profile is accurate and specific to the location of the proposed Normanby Road early works. A desktop scoping and profiling exercise was undertaken in order to identify the affected community and to identify the social and business environment prior to undertaking face to face meetings and site visits. This desktop exercise was further refined with the findings from meetings and discussions with the business and residential community.

4.2.2. Mt Eden Local Profile The Mt Eden suburb is characterised by residential units and apartments; commercial buildings; and retail operations (including shops and cafés). The area is home to the historic Mt Eden Corrections Facility and New Zealand’s largest sports stadium, Eden Park. It is in close proximity to SH1 and public transport options (such as the western train line, Mt Eden and Grafton Railway Stations and bus routes). For businesses located in this area, convenient access to major roads supports both a local and regional customer base. Mt Eden is an established suburb. It is attractive to residents as it is in close proximity to schools (being in the catchment of Auckland Grammar School and Epsom Girls Grammar School), close to the CBD and within walking distance of restaurants and cafés. Page 18

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan Overview The area is characterised by both residential and commercial properties, with the Mt Eden Corrections Facility is located within the affected community area. With the exception of the residential apartments located at 22-24 Normanby Road and 25-27 Enfield Street, the area is predominately commercial in character. A range of commercial and retail businesses operate within the area adjacent to the area associated with the Normanby Road early works, the larger of these include Office Max and Cory’s Electrical Head Office. There are a number of restaurants located on or accessed from Normanby Road, including Sen Vietnamese Kitchen & Bar, Wok N Noodle Bar and The Good Home. The team noted a low number of pedestrians utilising the pavement area along Normanby Road.

4.2.3. Demographic Profile Desktop research was undertaken of the Waitematā and Albert-Eden Local Board Area Demographics Report Card 2016 and New Zealand Census data to further inform the Link Alliance’s understanding of the community profile. The NAL forms the boundary between the two local board areas within the area where the Normanby Road early works are proposed to take place. The majority of the early works area falls within the Albert-Eden Local Board Area. As a small portion of the early works area, including a few properties identified as affected, falls within the Waitemata Local Board Area this was included in the review for completeness. Albert-Eden Local Board Area Demographics Report Card 2016 The key facts contained in the Albert-Eden Report Card include: •

• • •

Page 19

The area houses several significant facilities including Greenlane Clinical Centre, Alexandra Park Racecourse, Epson campus of the University of Auckland, UNITEC, Eden Park and St Lukes Shopping Centre. In 2013, there were 31,815 households in the Albert-Eden Local Board area, 7% of the regional count. As at February 2015, the area accounted for 6% of all employment and 7% of all businesses in Auckland. The largest sector of employment is the health care and social assistance sector (20%) followed by the education and training sector (13%), professional, scientific and technical services sector (12%) and the retail sector (11%). In comparison to the regional population, the area’s local population is slightly overrepresented in the working age population (15-64 years), with slightly smaller proportions of the younger (0-14 years) and older (65+ years) age groups. More than a third (36%) of residents were born overseas, and of that group, 45% had been in New Zealand for less than ten years. The largest group born overseas was from the People’s Republic of China, followed by India and England.

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan Waitematā Local Board Area Demographics Report Card 2016 The key facts contained in the Waitematā Report Card include: •

• • • •

The area houses a large tertiary and private education sector, the Ports of Auckland, the Auckland City and Starship Children’s Hospitals, Westhaven Marina, Britomart Transport Centre and a range of tourist and recreational attractions. In 2013, there were 31,650 households in the Waitematā Local Board area, 7% of the regional count. The area is a significant centre of employment which is mostly concentrated in the City Centre. It accounts for 24% of all employment and 15% of all businesses in Auckland. The largest sector of employment in the local board area is the professional, scientific and technical services sector (22%), followed by the financial and insurance services (10%). The area is under-represented in older and younger age groups and over-represented in age groups between 20 and 34 years, resulting in a median age of 30.4 years compared to a regional median of 35.1 years; More than a third (43%) of local residents were born overseas, and of that group, 63% had been in New Zealand for less than ten years, and 47% for less than five years. The largest group born overseas was from the People’s Republic of China and the United Kingdom, with smaller groups from India and Korea.

New Zealand Census data The 2018 Census data has been released which shows that the population of the Albert-Eden Local Board area has increased by 4.1% (3,927 people) to 98,622 since the 2013 census. There has been a slight increase of 180 occupied private dwellings to a total of 32,142. The median age in Albert-Eden was 34.2 years in 2018, compared with the Auckland average of 34.7 years. 2018 Census data shows that the population of the Waitemata Local Board area has increased by 5,730 to 82,866 people since the 2013 census. The number of occupied private dwellings has also increased by 2,730 to 35,007 and that the median age was 31.4 years, compared with 34.7 years in Auckland. The Albert-Eden and Waitematā Demographics Report Card data and the available 2018 census data relates to a significantly larger area than the Normanby Road early works. The 2013 Census data was reviewed to provide a more localised understanding of the early works area and affected community. This showed that the area has a population of 411 people and 87 households with an average age of 27.9 (Table 4-1; Figure 4-1). Table 4-1 Census Mesh block data for early works area

Mesh Block MB 0542700 (Boston Rd including Mt Eden Corrections Facility) MB 0542600 (Mount Eden Rd, Boston Rd, Normanby Rd, Enfield St) MB 0543000 (Normanby Road to Clive Road, including Auckland Grammar) Totals / Average Page 20

| Normanby Road Early Works

Population

Median Age

Households #

210

31.5

0

147

29.8

69

54

22.5

18

411

27.9

87


Social Impact and Business Disruption Delivery Work Plan

Boston Road

0542700 0542600

0543000

Figure 4-1: 2013 Census Mesh Blocks for Project area

4.2.4. Local Community Planning The key local planning document is the ‘Newton and Eden Terrace Plan 2016-2046’ which was developed jointly by the Albert-Eden Local Board and the Waitematā Local Board. The purpose of the Newton and Eden Terrace Plan is to provide a clear planning framework to guide how the area could grow and change over the next 30 years. The document identifies five key moves that are integral to change in the area: 1. Establish Newton as a prominent centre for business, residents and visitors with its own unique identity. 2. Create a great place for people within Newton and Eden Terrace through the provision of good quality interconnected public spaces and community facilities. 3. Enhance pedestrian and cyclist amenity and provide for public transport movement through and within Newton and Eden Terrace. 4. Integrate new development whilst protecting the historical and cultural character of Newton and Eden Terrace. 5. Promote the City Rail Link and public transport improvements as the catalysts for new investment and growth in the area. The Normanby Road early works are required to enable the construction of CRL at Mt Eden. The changes to Mt Eden Station and surrounds are a key part of the overall strategy for the Newton and Eden Terrace Plan 2016-2046. Page 21

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

4.2.5. Uptown Business Association The Uptown Business Association area is the area bounded by Mt Eden Road, Khyber Pass Road, Symonds Street, Newton Road, and New North Road. The association has some 700 businesses as members. Its stated mission is: “The mission of the Association is to preserve and enhance Uptown as a vibrant, innovative and attractive urban place. We support the success of existing and future businesses”.6 The Uptown Business Association is a partner with Auckland Council in its city-wide Business Improvement District (BID) Programme. The Uptown Business Association: • • • • • •

Promotes the precinct identity and activity through marketing activity. Encourages business collaboration and cross-promotion with networking activity. Advocates the interests of Uptown businesses to local bodies over major development works in the area. Delivers enhanced security services to protect businesses and monitor/report damage to public property. Provides a catalyst to improve the area’s “sense of place”. Provides a link between businesses and the resident community.

4.2.6. CRL Media Coverage A review of recent news articles was undertaken in order to obtain an understanding of the issues raised in the media in respect of the CRL works, and more specifically the works in the Mt Eden area. Concerns including depreciating property values, noise, vibration, dust, demolition and traffic disruptions were raised by affected community representatives in the Mt Eden area were reported on recently (10 December 2019, New Zealand Herald). These matters are addressed within this DWP.

6

https://www.uptown.co.nz/about/business-association/ Page 22 | Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

5. Consultation and Engagement 5.1 Introduction Consultation and engagement were undertaken to inform the SIBD DWP, particularly the Mitigation Implementation Plan (Section 8). This engagement was structured and informed by an understanding of CRL Designation 6, the proposed works, the affected community and the early works area. The consultation methodology is set out in Table 5-1 below: Table 5-1 Consultation methodology summary

Task 1

Activity Develop an understanding of the Project, Mt Eden, the cumulative effects of the demolition and enabling works and the affected community. Confirm properties that will potentially be affected / affected in proximity by the early works.

• • •

• • • •

Reviewed the Designation NoR SIA Report and AEE; Reviewed public submissions on the NoR to see who made comment from the Mt Eden area; Reviewed the SIBD DWP for the Mt Eden demolition work (Auckland Council Outline Plan ref. OPW60335715) and early works (currently with Auckland Council); Undertook a site walkover; Undertook an aerial assessment and property database assessment to understand the ownership and occupancy structure of the impacted area; Reviewed business websites to understand the scope of services offered and to confirm their proximity to the proposed works. Compiled a list of directly affected and affected by proximity properties and map them.

Liaise with the Link Alliance Communications and Engagement team

3

Engagement Programme

Door knocking, arranged meetings, Community Liaison Group (CLG) and feedback from information hub sessions – refer to Table 5-4 for a breakdown of the engagement process.

4

Discussion with other SMEs and review of other DWPs

Discussion with SMEs on potential impacts and any engagement undertaken. Established a coordinated approach to engagement. Reviewed draft DWPs.

Consultation on draft DWPs

2

5

• •

• •

Page 23

| Normanby Road Early Works

Clarification of existing relationships with property owners and occupiers. Review of previous engagement and discussion on key issues.

With other SMEs to ensure a joined-up approach to mitigation and identification of impacts. CLG; and Independent Peer Reviewer.


Social Impact and Business Disruption Delivery Work Plan

5.2 Establishing the Affected Community The methodology adopted for determining the affected and affected in proximity parties was: 1. Consideration of the construction staging plans (Appendix B of the CEMP) in order to conceptualise the proposed works in relation to surrounding properties. 2. A desktop assessment of the sites with proximity to the location of the physical works and with potential property access impacts associated with the works (these were identified as the directly affected areas); 3. A desktop assessment of the activities within proximity of the works where limitations on the road network may impact accessibility to their site (these were identified as the proximity affected areas). 4. Confirmation of the parties affected by the works occurred during the door knocking exercise. The focus of engagement has been on the affected community as shown in the yellow areas (affected parties) and the blue areas (affected in proximity parties) in Figure 5-1 below. Refer also Tables 5-2 and 5-3 for identification of these parties.

Figure 5-1: Engagement Map Showing Affected Parties and Affected In Proximity Parties Table 5-2 Affected Parties for the Normanby Road Early Works

No.

Affected Parties

1

5-7 Water Street – IMeasureU

2

8 Boston Road – Aspec Construction, Saturday, MSA Architects

3

10 Boston Road – Float Culture; Aspec Construction

Page 24

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

4

12 Boston Road – RGIS

5

32 Normanby Road – OfficeMax, AHS Security Hardware, Active Electrical Suppliers

6

22-24 Normanby Road – Normanby Mews

7

26 Normanby Road – Sen Vietnamese Restaurant and Bar

8

51-63 Normanby Road – Cory’s Electrical; Big Colour, Wok ‘n Noodle, Sabato

9

49 Normanby Road – Normanby Road Vet Clinic

10

45-47 Normanby Road – Restaurant Association, Blue Fitness, Van Roon Martial Arts, CLE Electrical, PCL Electrical, Davy Chapman Creative Agency, UBIQ, Robert A Conagham’s, A.L Byrne Waterways

11

1 Lauder Road – Mt Eden Corrections Facility

Table 5-3 Affected In Proximity Parties for the Normanby Road Early Works

No.

Affected in Proximity Parties

12

37 Normanby Road – The Good Home Mt Eden and mixed tenants

13

20 Normanby Road - BLOC

14

25 Enfield Street – Miro Apartments

15

71 Boston Road - The Project, Mediaworks

5.3 Engagement with Affected Parties Affected parties were contacted via face to face communications. The engagement took place between September and November 2019 and included: •

• •

Page 25

Arranged meetings for those with existing and ongoing CRLL and Link Alliance relationships took place with the following key parties: o Mt Eden Corrections Facility, located at 1 Lauder Road o Tram Lease Limited and associated tenants at 32 Normanby Road o Dilworth Trust Board and associated tenants at 51-63 Normanby Road Door knocking for those with no established relationship and who were being approached for the first time. Follow up meetings were arranged on request. SIBD SMEs attended four information sessions held at an information hub established at 16 Nikau Street on: o 11 September 2019, 0800 hours to 1000 hours o 11 September 2019, 1700 hours to 1900 hours o 18 September 2019, 1700 hours to 1900 hours o 25 September 2019, 1700 hours to 1900 hours The information sessions were aimed at the community as a whole and were attended by local residents, employees of local businesses and passers-by; Engagement has been undertaken with interested and affected parties at the CLG meeting held on the 25 November 2019. The meeting was attended by a variety of SMEs, including the SIBD DWP team. | Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan For affected parties not successfully contacted during the engagement period for preparation of this SIBD DWP, calling cards (Appendix C) were left to provide an opportunity for affected parties to obtain a briefing and further information about the project. The SIBD SMEs also undertook a site visit to the affected community, which provided an opportunity to gain an understanding of the potential impacts of the works on the resident, business or community organisations. Further engagement with these parties for the purpose of keeping them informed of the timing, scope and progress of the enabling works progress will be led by the Mt Eden Communications and Engagement Team. Engagement will be attended by SMEs, including the SIBD DWP team. Feedback will inform the ongoing work on the Mitigation Implementation Plan and Development Response Plan (DRP) set out in Section 8. The approach to engagement with the affected community is set out in Table 5-4 below. Table 5-4 Consultation and engagement process

Relationship Existing Relationship

Activity • Compile contact database based on information gathered from Tasks 1 and 2 contained in Table 5-1. • Feedback questions developed. • Contact made to request a meeting. • Attendance at meetings. • Feedback documented.

No Existing Relationship

• • • • •

• • Information Hub

CLG Members

Page 26

• •

Compile contact database based on information gathered from Tasks 1 and 2 contained in Table 5-1. Feedback questions developed. Door Knocking Exercise with Property Managers and/or Business Owners. Feedback documented. OR Follow up meetings if requested or if Managers and/or Business Owners not available on first visit; or phone calls / emails if affected party contact not apparent during door knocking to arrange meeting. Attendance at meetings. Feedback documented.

• •

Feedback questions developed. Arranged for other SMEs and the construction contractor to attend following a review of feedback received from the affected community to date. SIBD specialists attended the Info Sessions. Feedback documented.

• • •

Feedback questions developed. SIBD specialists attended the CLG. Feedback documented.

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan The engagement meetings where CRLL or Link Alliance had ‘no existing relationship’ were led by Hilary Konigkramer and a member of the Mt Eden Communication and Engagement Team. Where specific areas of concern were identified such as noise and traffic, the SIBD DWP team undertook to facilitate a follow up visit with the relevant expert to address the specific issues of concern. A summary of consultation is provided in Section 6, with more detail contained within Appendix A.

5.4 Face to face Engagement with Affected Parties The purpose of the face to face engagement (arranged meetings, door-knocking, information hub sessions, and CLG meetings) was to: 1. Establish positive working relations between the community affected by the Normanby Road early works and the Link Alliance, being the consortium delivering these early works and the wider CRL Mt Eden works; 2. Inform potentially affected parties of the early works and the proximity to their premises. This discussion and information sought to ensure affected parties understood the work prior to seeking feedback; 3. Obtain feedback from affected parties on the matters identified in CRL designation condition 61.3, i.e. the type and scale of disruption, specific access and servicing requirements, and client and visitor behaviour and requirements, and to gain an understanding of the extent of impacts the affected community may experience; and 4. Develop avoidance, remediation and/or mitigation measures to address the issues and concerns identified, as far as reasonably practicable. To ensure a level of consistency and that the matters set out in the designation conditions were addressed during the engagement interviews, a series of questions were asked relating to the operation of the business/residential accommodation and specifically about social impacts / business disruption resulting from the Normanby Road early works. Operational Questions: • • • •

What are your trading days / hours? What are the access arrangements for residents, customers, staff, deliveries? What are the servicing / bin store arrangements? Any other operational / business requirements?

Managing disruption and social impacts to your business / residential property in relation to: • • • • • •

Any special access and servicing requirements or special needs Effects on customers / business / residential occupier Effects on amenity (e.g. dust, noise, visual appearance, traffic issues) Business visibility and wayfinding Health and Safety Any other comments on the potential social impacts or business disruption

A copy of the meeting response recording sheet with questions is included in Appendix B. A summary of consultation is provided in Section 6, with more detail contained within Appendix A. Page 27

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

5.4.1. Engagement Material The SIBD DWP team received a detailed brief and set of plans on the Normanby Road early works prior to commencing engagement. The team took these plans on site to brief the affected community. Copies of the Normanby Road early works information factsheet and / or the calling cards (both attached in Appendix C) were left with each affected party, which included contact details for the Link Alliance Mt Eden Community and Engagement Team and were provided to owners/occupiers not present at the time of door knocking.

Page 28

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

6. The Affected Community’s Feedback Feedback, via scheduled meetings and a door knocking exercise, was received from owners or occupiers (affected parties) of 25 properties within the affected community. This feedback exercise was spread across the geographical area of the works and was obtained predominantly from business owners or managers and residential property managers. Further feedback was obtained from residents, members of the public and local businesses via the Information Hub (refer to Section 6.6), and CLG meetings (Appendix D). In addition to meeting affected parties, an understanding of the impacts has been gained from a review of the other SIBD DWPs prepared for CRL activities and discussion with the SMEs, including transport and acoustic specialists, and the feedback received as part of the SIBD DWP prepared for the Mt Eden enabling works (October 2019). Figure 6-1 below provides an overview of the key concerns and the location of the parties consulted. The majority of affected parties are concerned about a combination of issues. The two most prevalent concerns were access for both staff and customers and ensuring that deliveries and servicing for business properties is maintained. Appendix A identifies the affected parties and summaries the individual feedback received.

Figure 6-1: Overview of Key Concerns within the Affected Community – Normanby Road early works

The level of engagement is considered appropriate and enabled the SIBD DWP team to identify social impact and business disruption concerns and issues. The concerns and issues raised by affected parties are discussed further below. Page 29

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

6.1 Uptown Business Association The Link Alliance’s SIBD team met with the Uptown Business Association on 29 August 2019. The purpose of this meeting was to draw on the expertise and insight that the business association has of the Mt Eden area, the wider area, and the community. Given that the Normanby Road early works are located within the Uptown Business Association area, the feedback obtained from this meeting, relevant to the works, is outlined below: •

Uptown Business Association members concerns relating to CRL include disruption to parking and traffic flows, and that the best support would be advanced communication and regular updates Hoardings are unlikely to be needed for wayfinding, but images and updates of what is being developed would be preferred.

The General Manager of the Uptown Business Association is a member of the CLG. The Mt Eden Communication and Engagement Team meet monthly with the General Manager to provide an update on project matters.

6.2 Mt Eden Corrections Facility The SIBD team met with the Department of Corrections representatives of Mt Eden Corrections Facility. The key issues and areas of concern raised regarding the Normanby Road early works were: • • •

Access for delivery vehicles and prison escort bus essential Loss of utilities, in particular communications, is of significant concern Importance of continued communication regarding the CRL works

6.3 Tram Lease Limited A meeting was held with Tram Lease Limited, owner of 32 Normanby Road, with the property management company (Morton Property) and tenant representatives present on the 17 October 2019. Designation Condition 61.5 stipulates consultation requirements in respect of the site at 32 Normanby Road. When scheduling a meeting with the owner of 32 Normanby Road, their preference in respect of engaging with their tenants was established. The preference was one meeting with both the owner and tenant representatives present was held. The meeting included attendance by key CRL SMEs. Contact details were provided to facilitate direct engagement between occupiers and the Link Alliance, and further engagement will be in line with the CCP. The key issues and concerns raised during the meeting can be summarised as follows: • • •

Access for deliveries, customers and trades people Loss of parking Importance of continued communication

6.4 Dilworth Trust Board A meeting was held with Dilworth Trust Board, owner of 51-63 Normanby Road, with property manager and tenant representatives present. Page 30

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan The key issues and concerns raised during the meeting are summarised as follows: • • •

Effects on business deliveries and customer movements Potential loss of trade due to traffic disruptions Importance of good communication

6.5 Residential Properties Residential properties likely to be affected by the works include: • •

22-24 Normanby Road – Normanby Mews Apartments 25 Enfield Street – Miro Apartments

Engagement to date has occurred with a property representative, typically the building managers or body corporate chairperson, and not with individual apartment residents. Both the owner and building manager for Miro Apartments had no significant concerns regarding the early works. The only concern that residents were likely to have was regarding noise associated with night works. The body corporate representative for Normanby Mews did not want to discuss the early works. The preferred method for distributing information to apartment owners and tenants was discussed during engagement with the property representative. Further engagement with these parties for the purpose of keeping them informed of the timing, scope and progress of the enabling works progress will be led by the Mt Eden Communications and Engagement Team. Engagement will be attended by SMEs, including the SIBD DWP team. Feedback will inform the ongoing work on the Mitigation Implementation Plan and DRP set out in Section 8.

6.6 Noise and Vibration Sensitive Receptors One of the key SIBD issues identified for the properties affected by the Normanby Road early works is the potential noise impact. The acoustic team have confirmed that Site Specific Construction Noise Management Plans (SSCNMP) and Site-Specific Construction Noise and Vibration Management Plans (SSCNVMP) have been prepared for the following residential and commercial / retail properties: • • • • • • • •

71 Boston Road (The Project, Mediaworks) (SSCNVMP) 12 Boston Road (SSCNMP) 5-7 Water Street (SSCNMP) 25 Enfield St (SSCNMP) 22/24 Normanby Road (SSCNMP) 26 Normanby Road (SSCNMP) 32 Normanby Road (SSCNVMP) 55-63 Normanby Road (SSCNMP)

Face-to-face engagement took place with the above listed properties, with the exception of 71 Boston Road and 22-24 Normanby Road. The Mediaworks site at 71 Boston Road was identified by the SMEs as it is considered a ‘notable receiver’ (due to the television recording activities undertaken at this property) within 100m of the Page 31

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan designation footprint. As the SIBD and noise and vibration teams had recently engaged with Mediaworks extensively, email communication with Mediaworks was undertaken, with an offer of further consultation if required. Numerous attempts were made to engage with the body corporate of Normanby Mews, the residential apartments located at 22-24 Normanby Road. The body corporate advised they did not want to discuss the early works. Further engagement with residents will be led by the Mt Eden Communications and Engagement Team in line with the CCP. Engagement will be attended by SMEs, including the SIBD DWP team. Feedback will inform the ongoing work on the Mitigation Implementation Plan (Section 8) and SIBD Monitoring Plan (Section 10) The SSCNVMP and SSCNMP’s identify the ‘best practicable option’ for managing construction noise and vibration in relation to these properties, taking into account the specific activities undertaken on each property.

6.7 Open Information Sessions The Link Alliance held information sessions as part of its wider engagement strategy. These sessions were held initially at 16 Nikau Street and are now taking place at 97K Mt Eden Road. The SIBD DWP team provided details of the information sessions as part of its door knocking exercise and freestanding signage was displayed to attract passers-by. The information sessions were promoted by the Mt Eden Communication and Engagement Team to local stakeholder by email and on the CRL website and social media channels. The information sessions were held between 5:00pm and 7:00 pm on a Wednesday evening over the SIBD DWP engagement period. These sessions continue to be held by the Link Alliance. The feedback received from the information sessions was largely positive. The local community was primarily interested in understanding more about the broader programme of works for Mt Eden, rather than specifically concerned with the Normanby Road early works. No concerns or comments were made in respect of the Normanby Road early works. SIDB representatives were present at some of the information sessions and were available to discuss SIBD implications of the broader project.

6.8 Community and Business Liaison Group The Mt Eden CLG consists of members from a cross-section of the community, including residents, property owners, businesses and interest groups. This group is concerned with all aspects of the CRL Mt Eden works. The CLG has the following role: • • • •

an avenue for local community representatives to understand and share what’s happening in their area during construction. monitor and give feedback on the effects of construction on their community. provide input into the preparation of the CEMP, DWPs and MPs designed to help manage the impacts of construction. reviews of the CEMP, DWPs and MPs, including this SIBD DWP.

A CLG meeting was held on 25 November 2019 to provide an opportunity to discuss the Normanby Road early works and present the summaries of the DWPs. Hilary Konigkramer attended this Page 32

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan meeting to listen first hard to the issues raised by members of the CLG in relation to the potential SIBD impacts, and to provide a summary of the outcomes of the SIBD DWP. The CLG meeting commenced with an introduction to the CRL team members in attendance and a presentation was provided which covered the following: •

• •

Mt Eden enabling works update (Thibaut L’Hopital) o Station area o Upcoming works for early 2020 Overview of Normanby Road Early Works (Phil Young) Management plan process for Normanby Road early works (Maree Drury) o Construction Environmental Management Plan (CEMP) o Air Quality o Communication and Consultation o Contaminated Land o Social Impact and Business Disruption o Traffic, Access and Parking o Trees and Vegetation

Following the presentation, a breakout session with management plan specialists was provided to allow CLG members to interface with the various specialists. The CLG members raised questions and comments in respect of the following: • •

• • •

Duration of traffic and parking disruption on Normanby Road: whilst work will take 6 months the work will be undertaken in sections for 2-3 week periods. Users of street parking on Normanby Road: it was suggested that if used by employees of businesses on Normanby Road, AT could provide complimentary HOP cards for the duration of the disruption Clarification on the duration of street parking loss: parking will be removed in sections as work progresses, which each section affected or 2-3 weeks at a time. Auckland Transport to consider offering resident parking permits to owners and occupiers affected by the CRL works. Clarification on why the Flame Tree is classed as ‘notable’: specified in the Unitary Plan.

6.9 Summary of Key Issues The key issues raised during the face to face meetings from feedback summarised in Appendix A are: • • • • • •

Page 33

Access for customers and deliveries Loss of street parking during construction Access to on-site car parking Potential loss of trade due to traffic disruption Noise and vibration impact during construction Disruption in utilities as a result of construction and utility connections

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

7. Summary of Issues Identified and Response Provided in Technical Assessments In addition to this SIBD DWP, the Normanby Road early works Outline Plan is supported by a range of other DWPs and Management Plans. A number of these documents identify mitigation methods which are also relevant to mitigating social impact and business disruption impacts, albeit from a specific subject matter perspective. Table 7-1 summarises the issues raised from the affected community and identifies the relevant DWP/MP. For a complete overview of the DWPs and MPs refer to the CEMP. Table 7-1: Summary of Issues

Issue

DWP / MP

Objective

Relevant Section

Air Quality and Dust

Air Quality Delivery Work Plan (AQ DWP)

Sections 4: Monitoring Requirements Section 5: Operating Procedures

Car parking (on-site and on-street), Construction Traffic and Impact on Road, Loading Bays and Services and Deliveries

Transport, Access and Parking Delivery Work Plan (TAP DWP)

Communication and ongoing updates

Communication and Consultation Plan (CCP) and further consultation requirements identified in the DWPs

The objective of the AQ DWP is to detail the best practicable option to avoid dust and odour nuisance being caused by construction works and to remedy any such effects should they occur. The objective of the TAP DWP is to so far as is reasonably practicable, avoid, remedy or mitigate the adverse effects of construction on transport, parking and property access. The objective of the Communication and Consultation Plan is to set out a framework to ensure appropriate communication and consultation is undertaken with the community, stakeholders, affected parties and affected in proximity parties during the construction of the City Rail Link. The objective of a CNV DWP is to detail the best practicable option to avoid, remedy or mitigate adverse effects on a receiver resulting from construction noise that does not comply with the Project Noise Standards.

Noise and Vibration

Construction Noise and Vibration Delivery Work Plan (CNV DWP)

Noise and Vibration

Site Specific Construction Noise

Page 34

| Normanby Road Early Works

The objective of a SSCNMP or SSCNVMP is to detail the best practicable option to

Sections 6: Proposed Traffic Management Section 7: Assessment of Effects

Section 6: Communication Approach Section 7: Protocols, Processes and Contract Details Specific engagement / consultation identified within the relevant DWPs.

Sections 6: Predicted Levels Section 7: Mitigation and Management Section 8: Communication Section 9: Monitoring Section 10: Effects in Buildings Appendix C: Site Specific Management Plans Appendix C: of the CNV DWP


Social Impact and Business Disruption Delivery Work Plan Issue

DWP / MP

Objective

Management Plan (SSCNMP)

avoid, remedy or mitigate adverse effects on a receiver resulting from construction noise or noise and vibration that does not comply with the Project Standards.

Site Specific Construction Noise and Vibration Management Plan (SSCNVMP)

Page 35

| Normanby Road Early Works

Relevant Section


Social Impact and Business Disruption Delivery Work Plan

8. Mitigation Implementation Plan 8.1 Introduction Social impact and business disruption effects will be mitigated through the suite of DWPs and MPs required under the CRL designation and resource consent conditions. This section of the SIBD DWP summarises the mitigation actions to be implemented in relation to the Normanby Road early works These have been informed by the feedback from the affected community. Additionally, mitigation of the specific concerns raised by individual affected parties is set out in Appendix A.

8.2 Roles and Responsibilities The key Link Alliance personnel responsible for the delivery of the actions and recommendations in this SIBD DWP are identified in Error! Reference source not found. below. Refer to the CEMP for further detail on roles and responsibilities. To ensure the commitments made through the proposed mitigation measures, key staff will be informed of their obligations and responsibilities. In addition, all site personnel including subcontractors are responsible for implementing the requirements of this SIBD DWP. Table 8-1: Roles

Role Mt Eden Station Project Manager Mt Eden Station Construction Manager Environmental and Sustainability Manager Communications & Engagement Manager Mt Eden Community Manager Social Impact and Business Disruption Lead Mt Eden Development Response Manager

Name Thibaut L’Hopital Dave Harris Sarah Sutherland Rachel Blundell Sonya Leahy Kim Hardy /John Daly Natalie Donzé (interim)

The contact details and responsibilities of the Mt Eden Community Manager, Social Impact and Business Disruption SMEs and Development Response Manager are detailed within Appendix F. Refer to the CEMP for further detail on the roles, responsibilities and contact details of other key personnel. The general public contact details for the Mt Eden Enabling Works are as follows: • •

CRL Hotline: 0800 CRL TALK (0800 275 8255) Mt Eden Station email address: mteden@linkalliance.co.nz

8.3 Compliance with Designation Conditions The Link Alliance are required to comply with all relevant designation and resource consent conditions. This will be achieved via the implementation of the CEMP, DWPs and management plans that form part of the Outline Plan for the Normanby Road early works. Page 36

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan The affected community can stay informed about the Planning process through the CRL website. The Planning section of the website includes explanations of key planning terms, the designation and resource consent decision notices and consent documentation for each station area. The Mt Eden Communications and Engagement Team promotes the website as a key source of information for the public to keep up to date with the project’s progress.

8.4 Continuous Up to Date Engagement The need for early, continuous and up to date engagement was raised by a number of parties. This will be undertaken by the Mt Eden Communication and Engagement Team including: a) Courtesy visits and /or email updates to businesses and residents to check in with parties regarding the Project. The purpose being to obtain feedback on any issues of concern and identify pathways for their resolution in liaison with the appropriate team. b) Progress meetings with businesses and residents, to confirm the programme of the early works and when scheduled works will take place. c) Providing advance notice to businesses and residents on the scope of works on a regular basis. This is necessary to ensure businesses can plan ahead and advise customers in advance of their arrival. d) Engagement with the affected community, via: • Works notification letters • Local drop-in sessions • Monthly email newsletters • On-site signage for key traffic shifts • Digital communications including website updates and social media updates • Advertising and campaigns for major traffic shifts • Regular CLG meetings • Regular meetings with key stakeholders

8.5 Development Response Plan (DRP) A range of DRP measures are set out in Appendix E and the responsibilities of the Development Response Manager are set out in Appendix F. The DRP measures will be implemented alongside the construction works, where appropriate and practical, to mitigate SIBD impacts on affected parties. The DRP will link to the DRP for the Mt Eden early works were practicable. The DRP measures have and will continue to be developed in consultation with the affected community.

8.6 Contractor Briefings The Construction Manager will brief all contractors prior to their arrival on site and ensure they are fully aware of the project obligations to stakeholders within the area of the construction works (refer to the CEMP for further details regarding inductions and training). This will include a requirement to treat adjoining businesses as ‘project neighbours’ and ensure that, as far as practicable, the contractor’s day to day actions around the periphery of the site and their interface with the public areas is as considered as possible. This includes, for example, staging work to Page 37

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan minimise disturbance, that works are co-ordinated on an area basis and that re-work and consequential additional disruption is not required. The Contractor Briefings will be updated to respond to feedback from the continuous engagement with the affected community.

8.7 Noise and Vibration Disruption Construction noise, including night noise, and vibration will be managed, monitored and mitigated through the Construction Noise and Vibration (CNV) DWP prepared for the Normanby Road early works. Mitigation measures are set out in Section 7 of the CNV DWP and include the following: • • • • • •

Training Contractor hours Mechanical plant selection General mitigation measures Noise barriers and enclosures Measures identified specific to concrete and paver cutting, concrete and rock breaking and piling activities

The SSCNMPs and SSCNVMPs provided in Appendix C of the CNV DWP will be implemented as required. Refer to the CNV DWP for parties requiring a SSCNMP or SSNVMP to be prepared. Affected parties will be provided with advance notice of construction works commencing and an understanding of noise levels. This engagement will be led by the Mt Eden Communication and Engagement team in conjunction with the noise and vibration SMEs.

8.8 Transport Access and Parking Disruption Disruption to transport, access and parking will be managed, monitored and mitigated through the Transport, Access and Parking (TAP) DWP. The TAP DWP includes a detailed assessment of transport related effects and the mitigation measures as summarised in the sections below. In addition to the mitigation measures that are set out in the TAP DWP, ongoing and proactive communication will be maintained to inform the affected community of traffic management changes and to allow them to plan ahead for works. Communication will also be key to avoiding or reducing uncertainty about the nature of the traffic management changes.

8.8.1. Vehicular Access and On Street Parking A key transport mitigation method will be the development of a number of temporary Traffic Management Plans (TMPs) which will be implemented for the works, with evolving traffic management requirements and lane configurations as required. During consultations it was confirmed that two-way vehicle access will be maintained to all business accessways as far as possible. Access will be maintained for deliveries and customers. During all stages of the works, all existing traffic movements between public streets will continue to be available. Traffic management provisions proposed will ensure that vehicular access will be maintained as far as practicable.

Page 38

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan Kerbside parking on both sides of Normanby Road (approximately 180m) will be temporarily removed for the installation of the permanent south sewer line. The majority of this parking demand will be displaced to neighbouring roads. The affected community and the Uptown Business Association will be given advance notice of the traffic management and car parking measures prior to their implementation.

8.8.2. Pedestrian and Cyclist Access Pedestrian and cyclist access will be maintained throughout the construction area at all times. In accordance with Condition 30.1(o), a 1.8m wide footpath will be maintained on the northern side of Boston Road. Safe temporary pedestrian crossing facilities will be provided at either extent of the Boston Road works. Where works will occupy the footpath on one side of the road, then pedestrians will be directed to the footpath on the opposite side of the road. Appropriate sign-posting and crossings will be provided.

8.8.3. Public Transport Neither Normanby Road or Boston Road serve as a bus route. The nearest bus route is Mt Eden Road. The construction traffic movements for the Normanby Road early works are not anticipated to generate any noticeable adverse effects on public transport services and facilities on Mt Eden Road.

8.8.4. Transport Disruption Communication Plan Link Alliance will implement a Disruption Management Communications Plan for the Mt Eden Station closure (not directly associated with Normandy Road Works, but it is recognised that the closure will be concurrent to the works). The Plan will clearly identify and effectively communicate how disruption will impact on all stakeholders, such as public transport users and motorists, businesses, residents and visitors to the area. Link Alliance will work with Auckland Transport to develop and implement proactive communications for all transport users notifying them of the disruption and planned mitigations, including details of ATs accessible travel7 and travel plan8 resources. These measures will also help mitigate the loss of on street car parking. Wider communication and engagement will be led by the Mt Eden Community Manager with input from SMEs as appropriate. This includes regular meetings with employers to ensure that they are aware of the works and the impact on the traffic network and can pass this information on to staff, visitors and employees.

8.8.5. Construction Traffic Construction related vehicles for the early works are anticipated to be less than 40 vehicles per day. Most of the construction traffic relates to travel of site personnel and the delivery of materials to site, both of which are planned to occur outside of commuter peak hours.

7

https://at.govt.nz/bus-train-ferry/accessible-travel/ https://at.govt.nz/driving-parking/ways-to-get-around-auckland/working-with-businesses/workplace-travelplanning/travel-plan-resources/ Page 39 | Normanby Road Early Works 8


Social Impact and Business Disruption Delivery Work Plan The potential effect on the operations of Normandy Road, Water Street and Mt Eden Road are considered to be very minor and communication on the timing and nature of track will build knowledge within the community (and as such mitigate any uncertainty in the affected community around construction traffic levels). The existing Mt Eden Station will be closed to commuters from June 2020 while works are completed in the rail corridor and the redeveloped Mt Eden Station is constructed. Consultation with AT is underway regarding the operation of the public transport network.

8.9 Utility Disruption Minimising impacts on Network Utility Operators’ services will be achieved through collaboration with the local community, regarding the installation of the respective new networks and switch over from old to new. Supply outages have the potential to have a significant effect on people and their ability to conduct business. Therefore, advanced communication of planned network service suspension or outages needs to be advised to the affected community, so that backup arrangements can be put in place e.g. water storage. Network Utility Operator procedures for utility disruption will be followed in the event that an unplanned utility disruption occurs as a result of the Project.

8.10 Air Quality An Air Quality (AQ) DWP has been prepared by the Link Alliance for the Normanby Road early works. This identifies that due to the proximity of pedestrians, sensitive receptors, and businesses to the works, all locations within 100m of the early works are considered sensitive9 to the effects of dust that may result from the works. In order to minimise and avoid impacts on the surrounding community, dust and odour mitigation measures are recommended in conjunction with ongoing monitoring and engagement with the community. The measures are set out in detail in the AQ DWP.

8.11 Amenity Ongoing compliance and the implementation of the CEMP and DWPs, alongside the engagement measures outlined in Section 8.4 will ensure that the amenity impacts of the enabling works are managed, and that the affected community understand the nature, scale and timing of works.

8.12 Community Safety The proposed Normanby Road early works will take place over an estimated seven months and are not anticipated to have an impact on the safety of the community. Crime prevention, however, will be ensured through the following: • •

9

Provision of barrier within construction areas and security lighting in the CSA as appropriate; Replacement of street lights with temporary lighting wherever impacted;

The MfE has defined the sensitivity of different land uses in its Good Practice Guide for Assessing and Managing Odour in New Zealand. These definitions apply equally to the effects of dust, with both high density residential and commercial/retail areas considered to have high sensitivity. Page 40 | Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan • • • •

Clear identification of entry/exit points for work areas and Construction Support Area at 1122 Boston Road; Ensuring work areas are well managed to discourage antisocial behaviours, defacement or vandalism of construction areas (such as through graffiti) or crime; Providing well-defined and well-lit pedestrian routes with clear sight lines to promote convenient and safe movement within and adjacent to the area of works; and Providing legible and informative wayfinding signage within and around the works area as appropriate to the construction staging.

Further detail on the above is provided within the CEMP.

8.13 Health and Wellbeing It is recognised that the social impacts and business disruption resulting from the enabling works could affect the health and wellbeing of the affected community with concerns also raised by some parties during the door knocking. The Link Alliance will support businesses by providing pro-active communication on construction timing and scope of work to minimise risk of anxiety and stress around uncertainty. This will be a key action for monitoring and review to understand what may need to be updated during the enabling works and inform the preparation of subsequent SIBD DWPs and DRPs. Link Alliance will provide information on how to contact practical help agencies - including external helplines, local mental health services, counselling and support agencies. This information will be made available in pamphlet form using multiple channels such as info@cityraillink.govt.nz, the CRL project website, and local project information centres. Link Alliance will continue to work with the affected community, and through the CLG it will offer workshops for affected parties to address topics such as coping with stress, resilience, staying positive through difficult times, looking after self, and strategies for managing challenging situations. These workshops would be facilitated by appropriately qualified professionals such as counsellors, psychologists, and business advisors.

8.14 Business Disruption Potential loss of trade was raised as a concern at the meeting with Dilworth Trust and their tenants. Construction activity and traffic management measures may reduce the visibility of some businesses and result in the loss of through traffic and customer street parking. The Link Alliance are preparing a DRP, in conjunction with SIBD DWP specialists and other SMEs, the Uptown Business Association and affected businesses (refer to Section 8.5 and Appendix E). This plan will address the issue of visibility and actions to be undertaken to enhance visibility for the duration of the works. The NoR SIA stated that the CRL Project will generate both economic opportunities and impacts. The Assessment of Environmental Effects for the CRL NoR process prepared in 2012 stated that “a key purpose and driver of the CRL is to make the city centre more accessible, resulting in an anticipated increase in economic performance, and create changes in land use, development opportunities, and intensification (particularly around stations)”.

Page 41

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan Whilst the CRL project will in the longer term generate positive outcomes both locally and regionally, the businesses consulted to date have identified a number of concerns with the impacts of the construction works on them. These concerns are set out in detail in Appendix A. The mitigation identified is set out above. A summary of these concerns is set out in Table 8-2 below together with the recommended actions. Table 8-2: Business Disruption Issues and Actions

Issue Identified

Actions

Loss of on street car parking.

Businesses will be notified of car parks being lost. Wayfinding signage to alternative parking location (if appropriate). Maintain access to businesses and consider measures to ensure truck movements allowed for. Traffic Management Plan prepared on a site specific and area basis, as requested. The Link Alliance will support businesses and residents by providing pro-active communication on construction timing and scope of work to minimise risk of anxiety and stress around uncertainty.

Impacts from construction traffic including business and customer access, servicing and deliveries, and traffic congestion Support community health and wellbeing

Refer to Section Error! Reference source not found. of this SIBD DWP

Visibility of businesses

Regular communications on construction staging and timing and what to expect on weekly, monthly and longer-term basis

Provide opportunities for face to face communications. Development response measures including: ‘Open for business’ publicity Wayfinding for pedestrians and motorists Hoarding signage Supporting events in conjunction with Uptown Business Association Implementation of ongoing pro- active Communications and Consultation Plan to assist with forward planning.

Consideration of timing of works to avoid busy periods for businesses

Review of construction staging and timeframes for commencement of works in proximity to key businesses.

Minimise impediments and ease of pedestrian access to premises along roads

Pedestrian access to be maintained at all times to all properties. Any disruption to be minimised and communicated in advance. Pro-active pedestrian movement planning – DRPs, including hoarding design and wayfinding signage.

Page 42

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

9. Issues and Public Enquiries 9.1 Introduction Public enquiries are managed by the Link Alliance Communications and Engagement Team and will be handled in line with the Communication and Consultation Plan (CCP). SMEs, including the SIBD DWP team will be consulted for input to answer public queries as appropriate.

9.2 Queries and Complaints Process Anyone can make a general enquiry via the CRL email info@cityraillink.govt.nz and freephone 0800 CRL TALK (275 8255). Additionally, parties affected by the works will be able to make enquiries via the mteden@linkalliance.co.nz email which was provided during the consultation exercise undertaken for this SIBD DWP. A record will be kept of queries and complaints received to inform the review of this SIBD DWP. It will capture additional impacts identified. It will also ensure documentation of mitigation measures undertaken to address issues arising from the project on affected parties, and that alignment is achieved with other DWPs. This record will include: −

A description of the complaint;

The issues of concern to the complainant;

Remedial actions undertaken in response to the complaint;

Who is responsible for mitigation of the complaint;

Timeframes for addressing the complaint, including when the complaint is resolved; and

− Any affected parties. In addition, an update meeting will be held with the CLG at least every three months, through which social impact and business disruption concerns can be raised with the SIBD DWP team and other SMEs (refer to Section 6 of the CCP).

9.3 Disputes Resolution Disputes may arise where a stakeholder affected by an issue considers their complaint has not been resolved. In the context of this SIBD DWP, disputes may arise relating to: • •

Social impacts and business disruption Claims of financial loss due to construction effects on businesses in proximity to the works

With respect to SIBD related complaints/disputes these will be handled in line with the complaints process set out in Section 7 of the CCP.

9.3.1. Public Works Act 1981 Financial compensation under the Public Works Act 1981 is outside the scope of this SIBD DWP, however any claims received by the Link Alliance will be forwarded to CRLL. A claim for financial compensation under the Public Works Act 1981 is a possibility for affected parties who are significantly affected by the project. The Public Works Act entities affected parties to compensation for ‘substantial injurious affection’, which may include damage to property or losses to a business. Page 43

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan To pursue any claim under the Public Works Act for financial compensation as a result of the project, an affected party will need to lodge their claim with CRLL directly. Further information on the Public Works Act is available on the CRLL website10.

10

https://www.cityraillink.co.nz/public-works-act

Page 44

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

10. Reporting 10.1 SIBD Monitoring Plan Whilst the early works will take place over a limited timeframes, the works will be monitored to allow for relevant changes and updates to be made to the mitigation plan. The Link Alliance will monitor SIBD impacts throughout the construction process through ongoing engagement with the affected community, via the CLG, business forum and direct engagement, and from a variety of primary and secondary sources as detailed in the SIBD Monitoring Plan (Appendix G). SIBD Monitoring will be undertaken to: • • • •

Monitor the affected communities experience and perception of SIBD impacts Monitor the effectiveness of the identified Mitigation Measures. Monitor for any changes in the community profile of the area. Complaints and Public Enquiries Monitoring

10.1.1. Community and Business Liaison Group Reporting The CLG will meet regularly, at least every three months, over the course of the construction works and will be an opportunity for the CLG member to ask question or to raise social impact and business disruption concerns. SIBD SMEs will monitor feedback received at CLG meetings to measure SIBD impacts and the effectiveness of the mitigation measures. Mitigation measures will be reviewed in light of CLG feedback.

10.1.2. Regular Engagement Regular engagement will be carried out in line with the CCP but will include the Business Forum and the weekly drop-in information session and ‘meet the project team’ events. These events will provide an opportunity for the affected community to comments on the construction works and the mitigation measures. In addition, the Development Response Manager and Mt Eden Community Manager will liaise

with affected parties on a frequent basis in relation to the DRP and wider mitigation and will seek to resolve issues with the construction team. An SIBD focused engagement exercise will be carried out to inform the annual report. This will collect feedback from the affected community on their experience and will for the experience and perception of SIBD impacts to be measured against the feedback received as part of the engagement for this SIBD DWP.

10.1.3. Data Sources A range of primary sources will be reviewed to monitor for changes in the profile of the affected community, the extent of impacts and the effectiveness of the mitigation measures. These measures include: • • Page 45

Census and local board data Transport data

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan • •

Area based spending data and street frontages vacancy rates CPTED Audits

10.2 Monthly Reporting to Auckland Council The Link Alliance will provide monthly reporting to Auckland Council, demonstrating how the works continue to be undertaken in accordance with all the relevant management plans and CRL consent conditions. If issues raised are significant and require a revision to this SIBD DWP, including the mitigation implementation plan, the DWP will updated and submitted to Auckland Council for approval.

10.3 Annual Report The SIBD SMEs will prepare an annual report on the identification, monitoring, evaluation and management of the effects outlined in this DWP, along with a summary of any comments or complaints raised by the community, including how these have been addressed. The annual report will be informed by the SIBD Monitoring Plan and this will be made available on the CRLL website.

Page 46

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

Appendix A: Affected Community Feedback Address/Occupier 32 Normanby Road Tram Lease, Morton Property (property manager) and tenants (OfficeMax; AHS Security Hardware; Active Electrical Suppliers)

22/24 Normanby Road Page 47

Themes Access Concerns raised regarding access and loss of parking for customers and trades people. Approximately 50% of the carparking at the property is used by staff, the remaining 50% by customer/trade pick up and drop off. Important that high priority traffic (customers and trades people) can park within the property. OfficeMax will be open on the Saturday morning over Easter 2020 weekend, disruption to be reduced as far as possible. Servicing and deliveries Active Electrical Suppliers have regular deliveries: 5 large trucks per day, and consistent trade/customer movements throughout the day. OfficeMax and AHS have less frequent movements. Waste collection occurs within the property (as and when required), bins may need to be relocated to ensure ease of collection during construction period. Security/cleaners do require access to the building after hours (usually before 10pm). Communication Meeting requested prior to works commencing (Feb 2020) to provide detailed update on proposed works. Amenity No significant amenity concerns, potential noise impacts were discussed. Other comment Night works supported i.e. between 17:00 – 20:00 to ensure limited impact on business operations. Other comment

| Normanby Road Early Works

Mitigation Provision of alternative staff parking area at 14-22 Boston Road. Maintain access. TAP DWP – Sections 4.6, 4.10 5.5, 5.6, 5.7, 5.9 and 5.11.

TAP DWP – Sections 4.6, 4.10 5.5, 5.6, 5.7, 5.9 and 5.11.

Mt Eden Communication and Engagement Team to facilitate Feb 2020 meeting. Ongoing information sharing to take place via email. CNV DWP – SSCNVMP (C31) Appendix C.


Social Impact and Business Disruption Delivery Work Plan Address/Occupier Normanby Mews Residential Apartments

Themes Contact was made with the body corporate representative. They refused the opportunity to engage on the project and see no need to communicate to their residents.

26 Normanby Road Sen Vietnamese Kitchen and Bar

Access Access off Normanby Road to parking (5 staff car parks) and delivery area. Main entrance to restaurant on Normanby Road. Customers use street parking; some concern raised that street parking will be lost during construction period. Servicing and deliveries Restaurant deliveries take place 10:00 – 12:00, 4 days a week. Kerbside waste collection Tues, Thurs and Sat (between 6-9am) Customer/ Business Effects Important to ensure customer access to restaurant maintained, as well as access for deliveries and staff parking. Other comment All residents from apartments at 22-24 Normanby Road place their waste bins in the road on collection days; these remain there all day. This obstructs the road edge and would be in the way of construction work. Access No significant concerns regarding access, as long as this is maintained during construction period. Servicing and deliveries Delivery vehicles move in and out of the Prison daily. Larges vehicle is the prison escort bus which moves in and out the site 2 x week. Waste collection vehicles collect waste from within the prison property. Customer/ Business Effects Concern regarding impacts on utilities interruptions. Any impact on water supply and power would need to be managed, however most concerning would be an interruption in communications. Advanced notice essential to allow contingency plans to be put in place.

1 Lauder Road Mt Eden Corrections Facility

Page 48

| Normanby Road Early Works

Mitigation Mt Eden Communication and Engagement Team to identify measures to communicate with residents directly, giving them an opportunity to register their interest in the project so they can be kept informed. Maintain access.

Maintain access.

TAP DWP – Section 5.6.

Maintain access TAP DWP – Section 5.6. Maintain access TAP DWP – Sections 5.6 and 5.8.

Advanced notice of utility interruptions


Social Impact and Business Disruption Delivery Work Plan Address/Occupier

51-63 Normanby Road Dilworth Trust and tenant representative, including representatives from Cory’s Electrical, Big Colour, and Sabato.

Page 49

Themes Communication Request for a meeting end November 2019 to discuss the details around the planned works, particularly impact on utilities to ensure contingency plans can be prepared. Other comment Co-ordination regarding sewer tie-in at time of low flow (i.e. 12:00 – 03:00) Access Access and customer movements of concern. Link Alliance suggested the potential to widen access to the site to provide improved temporary access. Servicing and deliveries Sabato receive 26 container deliveries per year (mostly in Oct and Nov but a few throughout the year). If notice is given, containers can be scheduled around early works construction period. Other smaller deliveries taking place all the time. Big Colour have limited customers, mostly service vehicles that come and go. All other companies on the property have customers regularly. No circular traffic movement i.e. trucks and large vehicles arriving need to turn or reverse out of the entrance. Customer/ Business Effects Potential loss of trade due to disruptions. They have previous experience of this with past works (GPT works). Request made for additional signage for businesses. Communication Importance of correct lines of communication was emphasised, and appreciations for adhering to the requirement to meet Dilworth Trust with their tenants. Other comment Concern around longer term closure of Normanby Road for construction of permanent bridge. Clarity given regarding timeframe of closure (~6 months) and that Mt Eden road will be open when Normanby Road is

| Normanby Road Early Works

Mitigation Mt Eden Communication and Engagement Team to facilitate meeting end November 2019.

Maintain access Potential widening of main entrance to be considered. Maintain access TAP DWP – Sections 5.6 – 5.8.

Business visibility mitigation

Maintain communication as project progresses.


Social Impact and Business Disruption Delivery Work Plan Address/Occupier

49 Normanby Road Normanby Road Vet Clinic 45 Normanby Road Restaurant Association 45A Normanby Road Blue Fitness

45B Normanby Road Van Roon Martial Arts

Page 50

Themes closed. Query as to whether the impact on Enfield Road has been considered. Learnings from previous work: (i) obtain necessary agreements to work on Dilworth property; (ii) undertaken pre- and post-conditions reports; (iii) reinstate driveway; (iv) contractors to stay within the work area. Query regarding when Prison construction work will be complete. Business owner (vet) not available. Calling card left.

Mitigation

Managers not available. Calling card left.

Mt Eden Communications and Engagement team to email early works information to relevant managers.

Access Business has 8 off-street car parks. Customers do not use street parking. 2 deliveries occur every day. Servicing and deliveries Regular deliveries, important that access is maintained Communication Contact details obtained for owner and manager for future correspondence. Other comment As long as access for customer and deliveries is maintained, then no concerns. Access Clients use off-street parking. Other comment Business owner didn’t have much time to discuss the project but had no concerns. Communication Contact details obtained for owner and manager for future correspondence.

| Normanby Road Early Works

Mt Eden Communications and Engagement team to email early works information to business owner.

Maintain access. TAP DWP – Section 5.6. Maintain access. TAP DWP – Sections 5.6 and 5.8. Mt Eden Communication and Engagement Team to add contact details to the database for future engagement and notifications.

Maintain access.

Mt Eden Communication and Engagement Team to add contact details to the database for future engagement and notifications.


Social Impact and Business Disruption Delivery Work Plan Address/Occupier 45C Normanby Road Caldwell Levesque Electrical

45D Normanby Road PCL Electrical

45D Normanby Road Davy Chapman Creative Agency 45E Normanby Road UBIQ

Page 51

Themes Access Business has 85 vehicles in total, majority of staff are out during the day servicing customers. Customers do not visit the premises. Deliveries take place through the day. Customer/ Business Effects Disruption in utilities was raised as a concern. Communication Contact details obtained for owner and manager for future correspondence. Access Customers visit the premises regularly and use off-street parking. Multiple deliveries occur every day. Total number of staff is 28. Other comments Negative past experience regarding how AT managed the relocation of their business (as part of earlier CRL contract). Communication Contact details obtained for owner and manager for future correspondence. Other comments No interest in discussing the project as they are part of the Uptown Business Association and receive information through this forum. Relocating from premise in 2 months’ time (Dec 2019) Access There are 13 permanent staff, during busy times of the year this can increase to 23 staff. There are 4 off-street car parks. June/July is a very busy time of year (university semester), many customers come to collect books. Servicing and deliveries Kerbside waste collection only. Deliveries (courier) occur 2-3 times a day. Large pallet deliveries arrive from printers in June/July.

| Normanby Road Early Works

Mitigation Maintain access. TAP DWP – Section 5.6.

Notification of utility interruptions Mt Eden Communication and Engagement Team to add contact details to the database for future engagement and notifications. Maintain access TAP DWP – Section 5.6.

Mt Eden Communication and Engagement Team to add contact details to the database for future engagement and notifications.

Maintain access TAP DWP – Section 5.6.

TAP DWP – Sections 5.6 and 5.8


Social Impact and Business Disruption Delivery Work Plan Address/Occupier

47 Normanby Road Robert A Conagham’s Fishing and Tackle

47A Normanby Road A.L. Byrne Waterways Ltd

20 Normanby Road BLOC

37 Normanby Road The Good Home Page 52

Themes Communication Contact details obtained for owner and manager for future correspondence. Access Limited customers (2-3 per day). Off street parking outside premise for customers and staff. Servicing and deliveries Kerbside waste collection only. Communication Contact details obtained for owner and manager for future correspondence. Access: Customer collections occur regularly, as well as approximately 5 couriers per day. Customer/ Business Effects Disruption in utilities was raised as a concern. Communication Contact details obtained for owner and manager for future correspondence. Other comment Support for the greater project, in particular the grade separation at Normanby Road will improve congestion that currently occurs at the level crossing. Other comment Off-street parking for staff and customers off Enfield Street. Any loss of parking in the area would be of concern. Contact details obtained for managers, information to be sent through to them. Other comment Owner has no concerns regarding proposed works. Operating hours are Mon-Thurs: 11:00 – 23:00; Fri-Sat: 11:00 – 01:00; Sun: 11:00 – 22:30.

| Normanby Road Early Works

Mitigation Mt Eden Communication and Engagement Team to add contact details to the database for future engagement and notifications. Maintain access.

Mt Eden Communication and Engagement Team to add contact details to the database for future engagement and notifications. Maintain access.

Notification of utility interruptions Mt Eden Communication and Engagement Team to add contact details to the database for future engagement and notifications.

Mt Eden Communication and Engagement Team to send early works information and to add contact details to the database for future engagement and notifications. Mt Eden Communication and Engagement Team to add contact details to the database for future engagement and notifications.


Social Impact and Business Disruption Delivery Work Plan Address/Occupier 25 Enfield Road Miro Apartments

5-7 Water Street IMeasureU

10 Boston Road Float Culture

Page 53

Themes Amenity Past experiences with noise (night works related to work on the rail line). The only concern residents are likely to have is regarding noise disruption associated with night works. Communication Owner advised that it would be best to communicate with the building manager. Building manager happy to assist with information distribution to residents. Other comment Spoke to owner (10/10/2019) and building manager (17/10/2019); no concerns regarding the early work. 94 apartments within the property. Spoke to building manager on 17/10/2019, he has no concerns regarding early work. 95 % of the residents are apartment owners (i.e. limited rentals) Customer/ Business Effects Cameras are used during the business operations, that need to be calibrated regularly. Communication Contact details for managers obtained Other comment Advised of potential noise from dismantling of adjacent warehouse, no significant concerns regarding this. Access Main access to the business from carpark in Water Street. 7-8 staff members. 5 car parks for staff: 2 immediately outside business, and 3 in the parking area adjacent (other side of Water St). Servicing and deliveries Waste collection 1 x week. Deliveries from Water Street (2 x week) Customer/ Business Effects

| Normanby Road Early Works

Mitigation CNV DWP – SSCNMP (C28) in Appendix C.

Mt Eden Communication and Engagement Team to add contact details to the database to ensure future information is shared.

CNV DWP – SSCNMP (C27) in Appendix C. Mt Eden Communication and Engagement Team to add contact details to the database to ensure future information is shared.

Maintain access

TAP DWP – Sections 5.6 and 5.8.


Social Impact and Business Disruption Delivery Work Plan Address/Occupier

8 Boston Road Saturday

8 Boston Road MSA Architects

8-10 Boston Road Aspec Construction

Page 54

Themes Operating hours are Mon-Fri: 08:00 – 22:00; Sat-Sun: 07:30 – 22:30 Business sensitive to noise and vibration. Concern as a result of past experience with previous work. Other comment Left a factsheet to be handed to the owner, Anton Kuznetsov, who was on leave. Access Front access to the business from Boston Road. Total of 10 staff, parking for 5 staff provided in the parking area off Water St (behind the building). Remaining staff use street parking / drop off. Customers visit regularly and use street parking, which is often challenging. Concern regarding any loss of parking in the area, as well as any loss of parking for staff in Water St parking area. Servicing and deliveries Kerbside waste collection 1 x week. Customer/ Business Effects April – Oct very busy time of year for the business Other comment Appreciated information shared. Tenants of Boston8. Access 3 staff members, all use street parking. Other comment No concerns regarding the project. Appreciated information shared, has attended information session. Tenants of Boston8. Access Total of 45 staff. Fleet of 75 vehicles. 31 carparks in the Water St car park. Used to have a lease for parking in CRLL parking area on adjacent side of Water St. Constant vehicle movements throughout the day. Customer/ Business Effects

| Normanby Road Early Works

Mitigation CNV DWP – SSCNMP (C26) in Appendix C.

Maintain access.

TAP DWP – Sections 5.6 and 5.8. TAP DWP – Sections 5.4, 5.6, 5.7 and 5.10. Informed of information sessions.

TAP DWP – Sections 5.6 and 5.7.

Maintain access.


Social Impact and Business Disruption Delivery Work Plan Address/Occupier

12 Boston Road RGIS

71 Boston Road The Project, Mediaworks

Page 55

Themes Regular operating hours are 07:00 – 17:00, however some staff begin as early at 05:00. Other comment They have resource consent in place for a 3-storey building (Water St car park area). Main sewer line directed in Water Street approximately 5 years ago. Private sewer still remains. Access RGIS staff do not use the carpark behind the building (off Water Street). Access to the building and off-street parking from Boston St. Amenity No concern regarding potential noise impact. Other comments Operating hours from 9:00 – 20:00 (Mon-Fri). Other comment Mediaworks identified by Marshall Day as a sensitive noise and vibration receptor. Due to recent and ongoing engagement with Mediaworks, an email communication was deemed sufficient to advise them of the Normanby Road early works.

| Normanby Road Early Works

Mitigation TAP DWP – Sections 5.4, 5.6, 5.7 and 5.10.

Advised of information sessions.

CNV DWP – SSCNMP (C26) in Appendix C.

CNV DWP – SSCNMP (C24) in Appendix C.


Social Impact and Business Disruption Delivery Work Plan

Appendix B: Meeting Response Recording Sheet with Questions CRL C3 – Community Consultation Form – SIBD Person Name

Role: Manager /Owner Date /Time

Address Unit Number

Contact

Building Name

Other

Type of business Operating hours

Monday – Friday:

Saturday:

Sunday:

What are your access arrangements for customers, staff, deliveries?

Do you have any fit out or alterations planned during the works?

Does anyone need out of hours access (e.g. Security/cleaners)?

What is the Servicing / Bin Store Arrangements?

Any other Operational / Business Requirements?

We would like to talk to you about the potential social impacts and business disruption to your residential property / business / community organisation in relation to: Access (including pedestrian, cycle, passenger transport and service/private vehicles) Servicing and Deliveries / Loading Bays

Page 56

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan Any special access and servicing requirements or special needs

Effects on residents / customers / businesses

Effects on amenity (e.g. dust, noise, visual appearance, traffic issues)

Business visibility and wayfaring

Safety

Any other comments:

Page 57

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

Appendix C: Information Factsheet and Calling Cards

Page 58

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

Page 59

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

Page 60

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

Page 61

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

Appendix D: Record of CLG, Independent Peer Review and Auckland Council Feedback D1. CLG Comments A CLG was held at 97 Mt Eden Rd on the 25 November 2019. An overview of the key social issues identified from consultation with affected parties, and the mitigation identified to address these, was provided. The importance of ongoing communication was reiterated and will be provided in line with the CCP. No SIBD specific concerns were raised.

Page 62

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

D2. IPR Comments Independent Peer Review Comments Consistency with CEMP 1) On pp.56-57 of the CEMP the SIBD DWP is well summarised. Section 6.8 of the SIBD DWP outlines the key issues raised and this is consistent with the CEMP. However, the CEMP states that “engagement with residents, communities and businesses located adjacent to and in proximity to the Normanby Road early works area was carried out between September and November 2019” (p.56). This is not reflected by the SIBD DWP which states in Section 5.3 that affected parties were engaged between 10-17 November 2019 and feedback received from the CLG meeting of 25 November 2019. The correct engagement dates should be clarified and amended in both of these documents. Early Works Project profiling (Section 3) 2) As noted in the above comment, compared to previous SIBD DWPs (for K Rd and Aotea Stations) the SIBD DWP under review provides only a high-level summary of the proposed works for the Normanby Road Early Works. It does not include any detail of the construction methodology, hours of operation, or construction workforce. These are essential details that shape social and business disruption impacts (positive and negative) on the affected community, but are absent from the SIBD analysis and assessment. Whilst the SIBD states “refer to the CEMP for a detailed description of the works” (p.14), I feel it imperative that detailed description of the work methodology is better summarised so as to reflect the type and hours of the proposed work. I only received the CEMP on 6th December 2019. 3) Firstly, not being to review the CEMP until the last minute is a concern to the peer reviewer as the CEMP provides a detailed description of the works that is to impact the affected community and should drive the identification and planned mitigation and management of the SIBD effects. Secondly, I have had to rely on a review of the TAP DWP and CCP as a means to better understand the detail of the proposed early works until the CEMP was made available (5th December). The TAP DWP provides a comprehensive overview of the proposed works, and I do not understand why the SIBD DWP does not reflect such an adequate level of detail too, given that effects are upon people living and working and commuting within the project area, which will inform traffic management mitigation strategies. I suggest that a more detailed summary of the proposed early works Page 63

| Normanby Road Early Works

Response Section 5.3 of the SIBD DWP has been amended to reflect that SIBD engagement took place between September and November 2019.

In order to avoid duplication between the CEMP and sub-plans the approach has been amended to fully detail the works in the CEMP and summaries for the works within the sub-plans. Table 3.1 within Section 3 provides a detailed summary of each of the stages associated with the Normanby Road early works, including timeframes and duration of activities.

Refer to 2) above.


Social Impact and Business Disruption Delivery Work Plan must be included in the SIBD DWP so that the profile of the project is comprehensive and thoroughly outlined so as to enable a more logical understanding of potential effects. 4) For example, from the TAP DWP, I note there will be night works undertaken to construct the “installation of the temporary utility and pedestrian bridge across the NAL between the hours of 9:30pm to 5:30am in late July 2020” (TAP DWP, p. 16). As far as I can understand, this work will continue throughout at least 5 of the 7 months of the early works and will likely have an impact on resident’s in particular, but is not mentioned in the SIBD DWP (nor the CEMP), even though night works are listed as a concern among some affected party feedback. Section 8.7 of the SIBD DWP notes that construction noise and vibration will be managed, monitored and mitigated through the CNV DWP and associated SSCNMPs and SSCNVMPs. However, I have not been able to review the CNV DWP and am unable to verify whether the impact of night works on residents has been identified and will be appropriately managed. As I note below, residents (Normanby Road and Enfield Street) do not appear to have been adequately engaged and, therefore, perceived effects of the night works noise and vibration upon them has not been identified and assessed in this SIBD DWP. Hence, there is also no cross-referencing to a mitigation and monitoring plan of the impacts of this particular issue in the SIBD DWP, presenting a significant gap in analysis. I suggest the issue of noise and vibration impacts on residents be clarified and their management and mitigation and monitoring be appropriately assessed and cross-referenced in the SIBD DWP.

Isolated night works are required for the Normanby Road early works. These are limited to 1 night for the sewer tie in (March/April); 1 night for installation of stormwater lines at 32 Normanby Road (March/April); and 1 night for lifting the bridge span into place (with contingency made for a second night for each of the activities listed). The noise effects, including night noise, have been considered and mitigated within the CNV DWP and associated SSCNMPs which has been subject to review, including Independent Peer Review. It is also recognised that management of noise via the CNV DWP alongside proactive communication is key to managing SIBD effects resulting from construction noise. The SIBD DWP references the CNV DWP in respect of mitigation and monitoring of noise impacts (Section 7 and 8). Reference to the type of mitigation measures identified in the CNV DWP has been added to Section 8.7 of the SIBD DWP. In addition, the Link Alliance will proactively communicate the timing and nature of noise works.

5) It would also be advisable for this SIBD DWP to clarify its relationship to other CRLL works happening in the Mt Eden project area. I have referred above to general comments about the closure of the Mt Eden Station as a significant SIBD effect of the CRLL Project. The closure of the station at the time of the Normanby Road enabling works will impact on volumes of traffic, parking requirements and pedestrian movements within the affected area of the Normanby Road works, as commuters living and working in the area will have to Page 64

| Normanby Road Early Works

The relationship between the Normanby Road early works and the broader CRLL works is outlined in Section 1. The purpose of this SIBD DWP is to identify mitigation and management measures to address the potential SIBD effects


Social Impact and Business Disruption Delivery Work Plan adapt to alternative transport modes to conduct their everyday lives. These effects and others will all occur amidst the construction works at Normanby Road (and Mt Eden), but do not appear to have been acknowledged by the CEMP and SIBD DWP. I acknowledge that closure is not part of the scope of this SIBD DWP, but it will likely have significant impacts upon residents and businesses, as well as workers, visitors and patrons of businesses and residents in the Normanby Rd and Mt Eden construction support areas (CSA) and active construction zones (ACZ). There is a need for the CEMP and SIBD DWP to acknowledge this closure as part and parcel of the overall project and clarify how it might impact residents and businesses as part of the scope of these Normanby Rd works and whether the SIBD DWP will address these and/or why not.

associated with the Normanby Road early works with separate SIBD DWPs prepared for each phase of work.

6) Similarly, I note that references to the cumulative nature of the project impacts, stated in other SIBD DWPs (MT Eden Enabling Works, Aotea station enabling works and K Road enabling works) has been removed from this SIBD DWP. As per Designation Condition 19.1 “The objective of the CEMP and DWPs is to so far as is reasonably practicable, avoid, remedy or mitigate any adverse effects (including cumulative effects) associated with the City Rail Link construction.” I contend that the cumulative nature of works that are and will occur in the Mt Eden area are significant, particularly as the construction zones at Normanby Road and west of Mt Eden Road are in very close proximity to one another. Despite, the CEMP statement in Section 3.3 that “Methods to address cumulative effects are outlined for specific activities within the relevant sub-plans. Most notably these include construction noise and vibration; transport, access and parking disruption; air quality (dust) effects; and social impacts and business disruption. Monitoring includes methods so that the effects from the construction activities are well understood”, the SIBD DWP fails to acknowledge that residents and businesses in-between and in proximity to both of these construction zones will be affected significantly by the cumulative works. It is erroneous to assume that the Normanby works exists in vacuum, separate and distinct from the Mt Eden Enabling Works, including the station closure. The community will unlikely see these projects as separate and distinct; they will be subject to impacts from both regardless of the CRLL’s project management boundaries. The existence of cumulative impacts is demonstrated in

The section on Cumulative SIBD Effects has been inserted into Section 1.2. This sets out the approach to cumulative effects and how these will be further addressed in the SIBD DWP for main works in Mt Eden.

Page 65

| Normanby Road Early Works

However, the wider works and cumulative effects are acknowledged within this SIBD DWP refer to: • Section 1.2 for an overview of the approach to cumulative effects and how these will be further addressed in the SIBD DWP for main works in Mt Eden. • 8.5 which sets out that the DRP will link to the DRP for the Mt Eden early works were practicable, and • Section 8.8.4 for an overview of the Transport Disruption Communication Plan for the wider works.

The CRL works in the MT Eden area are being taken forward in a staged manner, however the scope of the early work packages are limited in terms of the scope and timeframe of the works. The Affected Community identified for the Normanby Road works reflects the scope of these works and the nature of the impacts that will be experienced in the early works construction period. However, the SIBD SMEs are cognisant of the feedback received as part of the preparation of separate SIBD DWPS, including for the Mt Eden early works. The SIBD DWP for the Mt Eden main works will consider the nature and extent of impacts and the extent of the affected community for those works. The independent peer reviewer’s comments will assist that exercise.


Social Impact and Business Disruption Delivery Work Plan the comments of a small number of parties engaged (listed in Appendix A) who have raised concerns with previous/ ongoing CRLL works. Whilst businesses on Mt Eden Road have been engaged as part of the Mt Eden Enabling Works, their lack of inclusion in this SIBD DWP process for Normanby Road works is problematic. I find this situation to be a significant failing of the SIBD DWP that must be remedied. 7) On p.7 of the SIBD DWP it states this “SIBD DWP only relates to the Normanby Road Early Works, as described in Section 2 below”. The project works profile is summarised in Section 3 of the SIBD DWP. Please amend to refer to the correct section of the SIBD DWP. Community Profiling 8) As I have commented before, for good practice and consistency purposes, I feel that the profile of the affected community is somewhat disappointing, relying too heavily on outdated statistics, and should be improved to describe the local context – business types and patronage, property ownership and lease data, how people get around, where residents work and commute to, how employees travel to work in the area, its look and feel, cohesion and sense of ‘community’, and ongoing development and change. My site visit on 1st December 2019 revealed that this is an area in process of multiple developments, gentrification and change as enabled by the Unitary Plan and other local development programmes. It is this local context that the Normanby Rd enabling works are being undertaken in and should be reflected in the SIBD DWP. A more comprehensive approach and understanding of the local community profile is required. 9) Firstly, I note that the Normanby Road works is located within walking distance (some 2060m east) of the Mt Eden Demolition and Enabling works and create a second construction site by which the businesses and residents along Mt Eden Road (between Boston Road and Enfield Street) in particular, are now surrounded by. Water Street will provide access to construction traffic into the CSA. However, properties and businesses on the corner of Boston, Mt Eden Rd and Water street have not been identified as affected parties. For example, the furniture business on the corner of Boston and Mt Eden Road has closed down, and whether or not this decision is an impact of the cumulative works is not acknowledged in any of the documentation. The exclusion of businesses along Mt Eden Road between Boston Road and Enfield Street from the list of directly or in-proximity affected parties is not explained in the SIBD DWP and needs to be. Page 66

| Normanby Road Early Works

The section reference has been amended.

The profile of the affected community was developed from a number of sources of information, including site visits to the area and engagement with the affected community. Insights into the local context were collected as part of the doorknocking engagement which has informed the development of the SIBD DWP. Section 4.2.3 has been updated to include reference to the 2018 census data.

The affected community for this SIBD has been informed by an understanding of the nature and scope of the Normanby Road early works and the associated construction impacts. The SIBD DWP for the Mt Eden main works will consider the nature and extent of impacts and the extent of the affected community for those works. The independent peer reviewer’s comments will assist that exercise.


Social Impact and Business Disruption Delivery Work Plan 10) Secondly, residents and businesses along the north side of Boston Road (between Mt Eden Road, Burleigh Street and Nugent Street) are also now adjacent to these two construction zones. The draft SIBD DWP, however, does not consider these areas as part of the affected community, which I feel is an error, particularly when 71 Boston Road, 5-7 Water Street, and 8, 10, 12 Boston Road premises have been selected as affected or in proximity parties.

71 Boston Street was identified as an affected party given the nature of the property (recording studio) being a notable receiver. The other properties listed (5-7 Water Street and 8, 10 and 12 Boston Road) were identified on there is the potential for noise and associated amenity effects as a result of minor sewer works to take place within these properties. The properties adjacent were not identified as likely to experience noise and vibration effects.

11) Thirdly, my site visit identified that there are affected in-proximity parties (residents and businesses) on both sides of Enfield Street (from Mt Eden Road to Normanby Road) that should be included in the scope of the SIBD DWP. This issue was also raised in feedback (Appendix A), but not addressed in the SIBD DWP. The SIBD DWP draws a boundary to include residential properties along the north (rail) side of Enfield Street as affected inproximity parties, but does not include new residences and businesses on the southern, opposite side of the street, nor the Horse and Trap pub. The SIBD DWP should preferably include these parties within the community profile or qualify why they are omitted from the scope of the analysis.

This SIBD acknowledges that during the Normanby Road early works there will be disruption to customers, visitors, and commuters. Strategies have been identified to ensure that people moving through this area during the early work have clear signage and wayfinding to ensure they are able to access the businesses and properties without too much inconvenience. The impact of access to the prison has been identified to be minor within the TAP DWP.

12) There are also stakeholders and affected parties who are not resident or business owners, such as office staff, workers, visitors, commuters, patrons, suppliers, shoppers and clients of the few cafes, restaurants and bars who will be impacted by the project. These are affected parties and should be acknowledged and the mitigation strategies in place be reviewed to ensure they are informed and can access the businesses and residents in the project area. For example, whilst I note that SIBD DWP engagement with Mt Eden prison has taken place, the draft has not noted the impact of the works on visitors by car, bus and rail to the prison. Consultation and Feedback (Section 5) 13) In light of my comments above, it is a significant concern that not only the affected community profile is limited, but that residents within the affected community profile (Miro Page 67

| Normanby Road Early Works

Refer to 8.8.5 for details of the Transport Disruption Communication Plan which the Link Alliance will implement, alongside communication by AT. The SIBD acknowledges that during the Normanby Road early works there will be disruption to customers, visitors, and commuters. Strategies have been identified to ensure that people moving through this area during the early work have clear signage and wayfinding to ensure they are able to access the businesses and properties without too much inconvenience. The impact of access to the prison has been identified to be minor within the TAP DWP. The SIBD DWP has been amended to set out the full extent of engagement between September and November 2019, which is


Social Impact and Business Disruption Delivery Work Plan Apartments and Normanby Mews) have not been engaged in the preparation of this SIBD DWP. Potential impacts or effects have been based only on comments via liaising with the body corporate/ residential managers. On the one hand, the residents of the 48 Normanby Mews Apartments (a complex comprising of four x four story buildings) have been disenabled from participating by decisions of the body corp representative. On the other hand, 94 households within the Miro Apartments, Enfield Road (who are largely owners, rather than renters) have not yet been engaged. To have not engaged and provided the opportunity for some estimated 140 households to understand the project and identify their particular concerns or issues about the social impacts of the works is a significant failing of the SIBD DWP, which raises a number of concerns about the adequacy of this SIBD DWP to meet the objectives and requirements of the CRL designation conditions, namely, 61.3. It is my expert opinion that the CLG and CCP and the expertise of the persons employed by the Alliance to consult and engage throughout the implementation of the Normanby works should not replace the SIBD in its purpose under Designation Conditions 61.1, 61.2 and 61.3. Whilst I understand that CRLL/ Link Alliance are endeavouring to meet tight time-frames, I strongly suggest that an engagement process with residents is necessary to inform this SIBD DWP before it is implemented.

considered to be appropriate for the nature and scale of the works.

14) The above concern is related to issues I have with the quality of the engagement process and methodology for the preparation of this SIBD DWP, which appears to have been limited by the fact that it was undertaken over seven days (10-17 October 2019) – a time-frame too short to enable full engagement and follow-up door knocking, face-to face meetings and best use of the infohub engagement method. It would appear as if the CCP for Normanby Road will become a proxy for this lack of engagement with potentially affected parties not yet engaged at the expense of the SIBD DWP understanding, identifying, assessing, mitigating and monitoring the concerns and potential impacts of these parties from the outset. SIBD DWP - Roles and Responsibilities 15) The SIBD DWP does not yet identify who is responsible for developing, delivering and monitoring the DRP for Mt Eden. As I have mentioned before this is a crucial mitigation and management measure. The person responsible would best be a local or someone with knowledge, connections and relationships in the Mt Eden area (as we have learnt from what

The SIBD DWP has been amended to set out the full extent of engagement between September and November 2019, which is considered to be appropriate for the nature and scale of the works, and to understand that issues and concerns of the affected community.

Page 68

| Normanby Road Early Works

SIBD SMEs attempted to engage with the property owners/occupiers or a building representative directly during the door knocking exercise. However, the SIBD SMEs also provided additional opportunities for the affected community to provide feedback, via four information sessions. These sessions were aimed at the community as a whole and were attended by local residents. On the basis of the feedback received from door knocking and the information sessions it is considered that the level of engagement is sufficient to understand the issues and concerns of the affected community.

Each SIBD DWP has been informed by a robust engagement exercise which is detailed separately in each DWP. The same approach will be adopted on future SIBD DWPs. Appendix F presents the roles and responsibilities of the DRP Manager and the Mt Eden Station Manager.


Social Impact and Business Disruption Delivery Work Plan is working in K Rd). It is also essential that this person works closely with the SIBD DWP team and CCP team so that DRP measures and ways of monitoring these activities are tailored to the effects outlined in the SIBD DWP. Until that role is filled, it would also be beneficial if the SIBD DWP lists the interim contact details for a contact in the project team who will be available to talk to interested stakeholders about developing the DRP. 16) It is good to note that the SIBD technical lead is listed as being responsible for SIBD monitoring. However, as I have consistently noted in previous peer reviews the monitoring roles and responsibilities need to be clarified and presented in this SIBD DWP as an implementation measure. Identification and management of impacts (Sections 6-8) 17) Given my concerns raised above regarding both the inadequate profiling of and engagement with the affected community it is difficult to clarify whether or not all potential impacts have been adequately identified and mitigated in this SIBD DWP. There is significant (and justifiable) risk that resident’s, in particular, could challenge the adequacy of the SIBD DWP and CEMP and their failure to meet the objectives of the Designation Conditions. Again, I strongly recommend that engagement with residents to identify and address their concerns and issues (particularly around works and cumulative effects of the project, including the proposed night works) is necessary before this SIBD DWP is implemented. Development Response Plan 18) I repeat earlier comments made that the Development Response Plan (DRP) remains a list of potential activities in the appendix – a cut and paste from other SIBD DWPs for works in Aotea and K Road station areas. As an essential mitigation strategy this DRP should be more advanced and should be a reflection of the needs and issues particular to the Mt Eden community. Whilst I note that the Uptown Business Association is wishing to help develop this Mt Eden DRP, the SIBD DWP does not yet identify who is responsible and what resources will be required for moving this work along. 19) I am of the opinion that the preparation of the DRP requires immediate attention and should be developed in conjunction with the SIBD DWP team, communications and engagement team, CLG and interested parties such as the Uptown Business Association. Again, the DRP as a mitigation strategy needs to be specific to the context of the project Page 69

| Normanby Road Early Works

Monitoring roles and responsibilities are presented in Appendix F.

Refer to 14) above.

Refer to Appendix F for details of the DRP and Appendix G for the responsibilities of the Development Response Manager.


Social Impact and Business Disruption Delivery Work Plan site, the Mt Eden community and the local needs and interests of the businesses, as well as the residents, local workforce and visitors who utilise these businesses and amenities. Monitoring and Reporting 20) It is acknowledged that the CCP provides a comprehensive complaints and reporting process, as well as processes of ongoing engagement which will likely pick up on any unaddressed or emergent impacts and issues arising from the Normanby Road Early Works. However, it should not be assumed that this replaces the need for an adequate SIBD DWP and monitoring plan in the first place.

Section 10 outlines the approach to reporting. A SIBD Monitoring Plan, consistent with the other SIBD DWP’s, has been included in Appendix G.

21) I continue to repeat the importance of SIBD monitoring (and opportunity to adapt and improve) the effectiveness of all the mitigation measures outlined by the SIBD, CCP and other DWPs. Section 10 does not go far enough to explain the processes and mechanisms for monitoring – what will be monitored, by whom, when and what will be done with the data gathered, and how it will inform ongoing community engagement and the next stages of the Mt Eden station project works. 22) I repeat that Section 8.5 of the SIBD DWP states “consumer spending and footfall data will be used to inform the development and ongoing implementation of the DRP”. Whilst welcome, this requires clarity on how and when this data gathering will occur, who is responsible (see comment above regarding roles and responsibilities) and what process or methodology will be used. Please remedy as part of the immediate work needed to develop, implement and monitor the DRP measures, with particular attention to how this is done in collaboration with the SIBD team. Role of the CLG 23) It would be beneficial if the membership of the CLG, their stakeholder interests (invited and those who attend) are included in the SIBD DWP and CCP. From a peer review perspective this group is established by the Designation Conditions to perform and important role in the preparation and implementation and monitoring of this and other plans. Page 70

| Normanby Road Early Works

Reference to this data collection is included in Appendix G rather than Appendix E.

Section 6.7 provides an overview of the CLG including the range of members. No additional details are required for SIBD purposes.


Social Impact and Business Disruption Delivery Work Plan It is still unclear whether the CLG is appropriately attended and resourced and tasked to undertake its various responsibilities (set out in Condition 7), in particular to be an active conduit - to be the eyes and ears of the community - for communications between other parties in their area and the Project Team. There is no evidence to clarify who is represented on the CLG (particularly residents who are absent from this SIBD DWP), how many reps attend the CLG meetings, and whether these members have a broad outreach to people in the local area. These contacts should be listed in the SIBD DWP and CCP in ways that protect people’s privacy but should be held on the CLM database. 24) It is my opinion, repeated on numerous occasions that a review of the role and functions of the CLG (including that in K Rd and Aotea station areas) should be undertaken as a matter of ongoing improvement to ensure its relevance and performance as a deliberative forum now and through the implementation and monitoring stage.

Page 71

| Normanby Road Early Works

The opinion of the IPR is noted. No change to SIBD DWP.


Social Impact and Business Disruption Delivery Work Plan

D3. Auckland Council Comments Auckland Council Feedback P 6, identify Normandy road on figure 1-1.

P15, Table 3-1 Stage 1- Establishment of alternative car park at 14-22 Boston Road for premises at 32 Normanby Road Does the alternative have the same capacity? P18 states: The NoR SIA identified social infrastructure within the Mt Eden area. On review it was confirmed that none of the social infrastructure identified lies within the area that will be affected by the Normanby Road early works.

Response Figure 1.1 provides a broad location of the CRL Route and is a figure that has been used consistently in all the DWP’s. There are a number of figures contained in the SIBD that show the location of Normanby Road, including Figure 4.1. The alternative car park for 32 Normanby Road will have the same capacity

Confirmation has been provided on P18 that access to social infrastructure will not be compromised during the early works.

Social infrastructure needs to be accessible, so although not directly impacted, will access to the social infrastructure be compromised for any of the surrounding areas, if so which, how much and what mitigation is in place? P20 Figure 4-1 mark up road names referred to in table 41 on map P24 “where time permitted the blue areas” I’m a bit troubled by this statement, time to engage should have been made available for everyone in both the blue and yellow shaded areas. How many affected parties were missed due to time constraints? P27, P33, P39 refer to Appendix C. This should have been added to the draft as it is finalised and needs to be included so that it can be reviewed. P29 “Further feedback was obtained from residents, members of the public and local businesses via the Information Hub, and CLG meetings”. Indicate where the record of this feedback is in the report. P29 a map indicating where the other works areas are in relation to the Normandy road works, and which parties are affected by both would be helpful to understand cumulative effects. P30 “Engagement to date has occurred with a property representative, typically the building managers or body corporate chairperson, and not with individual apartment residents” what was the reason for this? Have tenants from Miro apartments been given the option to engage? Page 72

| Normanby Road Early Works

Figure 4.1 has been amended to reflect the road names referred to in Table 4.1. Section 5.3 has been revised to provide clarity, and sets out the methods and range of engagement which was undertaken between September and November 2019. Appendix C has been included.

Section 6.7 provides additional information on feedback received from Information Hub. Appendix D1 provides a record of the CLG Comments. No concerns were raised at Information Hub or CLG meeting. There has been co-ordination between the SIBD teams working on the Mt Eden early works and the Normanby Road early works. There are no common affected parties across these works. The SIBD DWP has been amended to set out the full extent of engagement between September and November 2019, which is considered to be appropriate for the nature and scale of the works.


Social Impact and Business Disruption Delivery Work Plan If not, they need to be allowed to do that. If tenants have deferred to the property manager to represent them that needs to be stated explicitly in the SIBD DWP.

SIBD SMEs attempted to engage with the property owners/occupiers or a building representative directly during the door knocking exercise. In addition, the SIBD SMEs also provided additional opportunities for the affected community to provide feedback, via four information sessions. These sessions were aimed at the community as a whole and were attended by local residents.

Re the noise impacts on 22-24 Normandy Road, there seems to be considerable risk of exposure to noise exceeding levels that will be disruptive to residents. It is noted on p 47 that efforts to engage directly with the tenants are happening, this needs to be done prior to lodgment of the DWPs to take on board any specific feedback in the (SSCNVMP).

On the basis of the feedback received from door knocking and the information sessions it is considered that the level of engagement is sufficient to understand the issues and concerns of the affected community. This feedback has been forwarded to the acoustic SME and the Mt Eden Community Station Manager in regard to further consultation in relation to noise. Further consultation feedback will inform the SIBD review and Monitoring Plan. The SSCNMP for 22-24 Normanby Road states that the anticipated construction noise effects are predicted to be typically acceptable, but with the potential for short term disturbance. It is considered that sufficient engagement with the affected community and the acoustic SME has allowed the SIBD SMEs sufficient understanding of the potential noise impacts and concerns. It is recognised that management of noise via the CNV DWP / SSCNVMP alongside proactive communication is key to managing SIBD effects resulting from construction noise. The Link Alliance will carry out the construction works in accordance with these documents and the relevant noise conditions.

P31 how well attended were the the information sessions? Page 73

| Normanby Road Early Works

The local community were made aware of the information sessions via numerous methods. During the SIBD engagement for


Social Impact and Business Disruption Delivery Work Plan

P31 Community and Business Liaison Group, a detailed list of members is needed. Is anyone who should be, not represented by this group? P35 is Rachel Blundell the contact for all Mt Eden works or just the Normandy road one? P42 & P43 Wellbeing only discussed in relation to businesses “The Link Alliance will support businesses by providing pro-active communication on construction timing and scope of work to minimise risk of anxiety and stress around uncertainty”. What about residents? Particularly as the property manager at 22-24 Normandy Road has disengaged. P45 “Any claims received by the Link Alliance will be forwarded to CRLL. Financial compensation is outside the scope of this SIBD DWP”. As monitoring of the effectiveness of the mitigation plan is not being collected for this stage, it will be difficult for affected parties to prove a claim. Monitoring of this stage is also required and shouldn’t defer to the main works as that excludes impacts caused during this phase. Proactive engagement to inform the monitoring rather than relying on complaints would be a better approach. P50 will the business owners that weren’t available be contacted again? It is likely that the business disruption will be considerable for the vets, reliant on easy customer access with live animals.

Page 74

| Normanby Road Early Works

the Normanby early works a number of community members attended the information sessions. Section 6.7 provides an overview of the CLG, including the range of members. No additional details are required for SIBD purposes. Refer to 8.2 for the list of relevant personnel for the Normandy Road. This omission has been corrected.

An SIBD Monitoring Plan is included in the SIBD DWP. The purpose of this monitoring is set out in 10.1. Proactive engagement is proposed throughout the Normanby Road early works. This will be led by the Mt Eden Station Community Manager.

All business and residents identified as affected parties will be engaged with prior to the commencement of the early works. This will be led by the Mt Eden Community Manager Team.


Social Impact and Business Disruption Delivery Work Plan

Appendix E: Development Response Measures The Link Alliance will implement the following measures in conjunction with the affected community and as far as they are practicable. The DRP is a live document and opportunities for additional mitigation will be sought from the affected community from future engagement and in response to SIBD monitoring. Business Support package A free of charge business support package which includes: • 12 months with a Business Mentor from Business Mentors NZ, • a 12-month membership with the Auckland Business Chamber, and • free social media training. Trader Directory An online directory promoting businesses to the 1600+ CRL workers expected at peak construction, encouraging them to shop local and to use local services and facilities. Also accessible by Auckland’s wider community. The Trader Directory will be printed and available at all construction sites, handed out to cruise ship passengers and will be promoted using established social media channels. It is free to list local businesses and Link Alliance has received strong interest in the Trader Directory already. Business may register by emailing the City Rail Link at traders@cityraillink.govt.nz. Meet the Neighbours Series CRL Ltd has started a ‘meet the neighbours’ series which profiles local businesses providing insights into business owners and the challenges and opportunities that exist neighbouring the CRL project. The series is included in the project newsletter ‘CRL Connection’ which is disseminated to more than 4000 people. The profiles are also promoted on CRL’s social media channels and disseminated to the local community through Link Alliance’s regular email newsletters. Street cleaning and maintenance Link Alliance will work closely with council contractor cleaning services to prioritise construction areas with regular cleaning, that is often more regular and thorough than the businesses have normally. Business advertising Link Alliance will work with businesses to include their advertising where possible on hoarding structures. Additional Wayfinding Signage Link Alliance will display wayfinding signage at key points to help pedestrians navigate their way through diversions. Activations and events Link Alliance will work with the Uptown Business Association to leverage key events and festivals and promotional opportunities. Affected Community Involvement The Link Alliance will identify opportunities for Uptown Business Association and the affected community to be consulted on and to make decisions with regards to the DRP, and it will continue to support community information sessions.

Page 75

| Normanby Road Early Works


Social Impact and Business Disruption Delivery Work Plan

Appendix F: Project Roles and Responsibilities Role

Name

Contact details

Responsibilities

Mt Eden Community Manager

Sonya Leahy

sonya.leahy@linkalliance.co.nz

• •

Page 76

| Normanby Road Early Works

Manages a communications and engagement team that is the primary contact for project related enquiries and complaints Having ongoing conversations with the community to keep them informed of key construction activity, milestones, programme and progress Utilising a range of communications tools including face-to-face engagement, works notifications, drop-in sessions, station email addresses, digital channels including the CRLL website and social media and the CRL freephone number, to have ongoing conversations with the business and residential communities about best ways to manage effects and impacts Managing stakeholder risks and immediately reporting any high-risk stakeholder / communication issues to the Mt Eden Station Project Manager and Communications and Engagement Manager. Assisting the CRLL Communications team with key stakeholder engagement including the Mana Whenua Forum, Local Board engagement and media. Providing advice to the Mt Eden Station Project Manager / Construction Manager on critical stakeholder engagement, communications and relationship building. Co-ordination of Mt Eden CLG meetings. Assisting the Mt Eden Station Construction Manager in briefing site personnel on: - The mandatory site inductions regarding the standards and requirements for community relations; - Procedures to follow if staff are approached by a member of the public or the media; and - Behavioural procedures in and around the construction site boundaries.


Social Impact and Business Disruption Delivery Work Plan

Role

Name

Contact details

Responsibilities

Link Alliance Development Response Manager

Natalie Donzé (Interim)

mteden@linkalliance.co.nz

• • • • •

Social Impact and Business Disruption Monitoring

Kim Hardy / John Daly

john.daly@linkalliance.co.nz

Page 77

| Normanby Road Early Works

Manages planning, delivery and evaluation of the overall Development Response Plan for the Mt Eden precinct. Manages street response measures including street cleaning, graffiti removal. Co-ordinates business promotion events. Co-ordinates business support programme. Proactively identifying opportunities to mitigate impact on businesses. Regular audits of the construction sites, including the DRP, and address issues with the construction manager. Monitoring of SIBD Effects and mitigation measures, via: o Attendance or review of minutes from CLG, Business Forum and / or consultation events to monitor SIBD impacts. o Undertake SIBD engagement to inform the annual report or updates of the SIBD DWP. o Review of feedback, public enquiries and complaints raised by affected parties for annual report. Share feedback with the project team, and co-ordination and facilitation of responses. Prepare, review and update SIBD DWP (if required), including identifying additional affected parties and mitigation measures. Preparation of the annual SIBD monitoring report and reporting to CLG (As required by Condition 61.8).


Social Impact and Business Disruption Delivery Work Plan

Appendix G: SIBD Monitoring Plan

Monitoring of the Affected Communities Experience and Perception of SIBD Impacts

Monitoring of Mitigation Implementation Plan

Data Source CLG Feedback Business Forum Weekly Information Sessions DRP and Station Community Manager Direct Engagement Engagement Exercise or interviews with CLG/Stakeholders for Annual Report

Data Source Site Audits by Development Response Plan, including accessibility.

Pedestrian Street Counts on Victoria St Albert St and Wellesley Street - Albert St.

Timeframe Audits Weekly (subject to operational need)

Quarterly

Area based spending data

Quarterly

CPTED Audit

Following changes to construction layout Ongoing

| Normanby Road Early Works

Comment on Data Collected The views and experience of the impacts of the CRL works and the effectiveness of the mitigation measures will be sought from the affected community. Monitor for changes in the community profile.

Comment on Data Collected Visual inspection of the construction area and ease of navigating within the affected area.

Quarterly reports for SIBD monitoring Annual A measure of on-street activity on (timeframes to be key streets within the affected agreed with AT) community.

Street Frontage Vacancy Rate Count

Events and festival data and discussion with providers on requirements e.g. Auckland Book Festival Associated Monitoring of DWPs outlined in Table 7-1

Page 78

Timeframe Quarterly 2 – 3 monthly Quarterly reports for SIBD monitoring Quarterly reports for SIBD monitoring Annual

Ongoing / Quarterly

Economic data to monitor the impacts of construction works on the vibrancy and vitality of the area. Economic data to monitor the impacts of construction works on the vibrancy and vitality of the area A measure of the effectiveness of the CPTED measures. Data to inform whether bespoke updates are required to the Development Response Plan.

SMEs and the project team will undertake monitoring in line with their CRL Designation condition / DWP.


Social Impact and Business Disruption Delivery Work Plan An overview of issues will be sought of SIBD related issues to monitor associated SIBD impacts.

Additional Monitoring for Annual Report

Monitor for changes in the community profile

Page 79

Data Source Number and type of complaints received

Timeframe Annual

Complaints resolved rate

Annual

Council feedback from monthly reporting

Monthly / Annual

Council feedback and the response to SIBD issues will be detailed within the annual report.

Data Source Census Data and Local Board Data Additional data collected as per Table 13

Timeframe Annually

Comment on Data Collected Socio-economic data to ensure the community profile is correct. A range of primary and secondary data to inform the community profile/

| Normanby Road Early Works

As stated above and collated annually for the Annual Report.

Comment on Data Collected Complaints will be handled in line with the complaint’s process set out in the CCP. This data will be collected to monitor the response to SIBD related as part of the Annual Report.