Odour Management Plan Revision 06

Page 1

Auckland City Rail Link In association with:

ODOUR MANAGEMENT PLAN Connectus Document Ref: 025-Y023-2719 Revision: 06 28th June 2017

COMMERCIAL IN CONFIDENCE


This page intentionally left blank.

CONNECTUS PROJECT NO. 2665 CITY RAIL LINK LIMITED

PAGE 2 OF 20


DOCUMENT INFORMATION Organisation:

Connectus

Document Title:

Odour Management Plan

Connectus Document Number

025-Y023-2719

Client:

City Rail Link Limited

Project:

CRL Enabling Works Contract 2

Location:

Auckland CBD

Project No:

2719

REVISION HISTORY Rev

Date

Details

Author Reviewer

1ST Draft for Connectus Review

A. Curtis

C. Hind

2nd Draft – AT Review sent as Rev 01 to AT

A. Curtis

C. Hind

/

Approver

1

29/07/15

01

4/08/15

02

11/09/15

3rd Draft – AT Review (#2) Sent as Rev 02 to AT

A. Curtis

C. Hind

03

25/09/16

Final for AT Submission to AC (#1)

A. Curtis

C. Hind

04

09/10/15

Final for AT Submission to AC (#2)

A. Curtis

C Hind

05

24/11/15

Addressed Council Comment – additional line added at the end of the contingency measures table in section 6

A. Mawdsley

C Hind

J.Surphlis

C. Powell

ISSUED FOR CONSTRUCTION – Certified by Auckland Council 06

28/06/17

Revise odour monitoring

This document remains the property of Connectus. Its contents are confidential and shall not be reproduced, destroyed or given away without the express, written permission of Connects. The electronic version of this document in iTWOcx Database on designated server(s) is the Master Copy and is a controlled document. Unless specifically noted thereon, other copies of this document are uncontrolled.

CONNECTUS PROJECT NO. 2665 CITY RAIL LINK LIMITED

PAGE 3 OF 20


This page intentionally left blank

CONNECTUS PROJECT NO. 2665 CITY RAIL LINK LIMITED

PAGE 4 OF 20


GLOSSARY Term

Definition

AC

Auckland Council

AECOM

AECOM New Zealand Limited

AT

Auckland Transport

CEMP

Construction Environmental Management Plan

CRL

City Rail Link

GRP

Glass-reinforced plastic

H2S

Hydrogen Sulphide

ISCA

Infrastructure Sustainability Council of Australia

Km/h

Kilometres per hour

LEL

Lower Explosive Limit

m/s

Metres per second

O2

Oxygen

OMP

Odour Management Plan

OMS

Orakei Main Sewer

ppb

Parts per billion

Pipe Jack

Trenchless pipe installation method where pipes are driven horizontally between two vertical shafts using a tunnel boring machine

TBM

Tunnel Boring Machine

VOC

Volatile Organic Compound

CONNECTUS PROJECT NO. 2665 CITY RAIL LINK LIMITED

PAGE 5 OF 20


This page intentionally left blank.

CONNECTUS PROJECT NO. 2665 CITY RAIL LINK LIMITED

PAGE 6 OF 20


ODOUR MANAGEMENT PLAN Doc No: 025-Y023-2719 REVISION: 06 DATE: 26-June-2017

Table of Contents 1.

INTRODUCTION ........................................................................................................................ 8 1.1

Purpose of Odour Management Plan ................................................................................... 8

1.2

Consent Requirements ........................................................................................................ 8

1.2.1 1.3 2.

Sustainability ................................................................................................................. 9

OMP Author....................................................................................................................... 10

PROJECT DESCRIPTION........................................................................................................ 10 1.4

Summary of Methodology .................................................................................................. 10

1.4.1

Pipe Jacking ................................................................................................................ 10

1.4.2

Shaft Construction ....................................................................................................... 12

1.4.3

OMS Strengthening ..................................................................................................... 12

1.4.4

Utilities Relocation ....................................................................................................... 12

3.

AIR DISCHARGES ................................................................................................................... 12

4.

CONTROL MEASURES ........................................................................................................... 13 1.5

Odour Control Measures.................................................................................................... 13

1.6

Dust Control Measures ...................................................................................................... 14

5.

MONITORING .......................................................................................................................... 15 1.7

Odour Monitoring ............................................................................................................... 15

1.7.1 1.8

Monitoring for Fugitive Odour ....................................................................................... 15

Dust Monitoring ................................................................................................................. 15

1.8.1

Visual Inspection and Monitoring Methods ................................................................... 15

6.

CONTINGENCY MEASURES................................................................................................... 16

7.

COMPLAINT PROCEDURES ................................................................................................... 16

8.

APPENDIX A: ISCA REQUIREMENTS ..................................................................................... 17

9.

APPENDIX B: BEAUFORT CHART .......................................................................................... 18

10.

APPENDIX C: ODOUR MONITORING .................................................................................. 19

CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

PAGE 7 OF 20


ODOUR MANAGEMENT PLAN Doc No: 025-Y023-2719 REVISION: 06 DATE: 26-June-2017

1.

INTRODUCTION

Auckland Transport (AT) has been granted resource consents (R/LUC/2014/4792, R/REG/2014/4793, R/REG/2014/4794, R/REG/2014/4795 and R/REG/2014/4796) for the realignment of a stormwater main along Albert Street, Auckland City, as part of the enabling works for the proposed City Rail Link (CRL). The Albert Street Stormwater Main Realignment (the Project) involves the construction of a replacement stormwater main along the eastern side of the Albert Street road reserve between Wellesley Street and Swanson Street. In its current location, the existing stormwater main conflicts with the proposed alignment for the CRL rail tunnels and needs to be relocated to enable construction of the tunnels. The Project also involves strengthening of the Orakei Main Sewer (OMS), running west to east along Victoria Street. The strengthening is necessary to reduce the risk of damage to the OMS during subsequent construction of the CRL, including the proposed Aotea Station which will sit directly above the OMS. This Odour Management Plan (OMP) has been prepared by AECOM New Zealand Limited (AECOM) and forms part of the Construction Environmental Management Plan (CEMP) for the Project. The OMP specifically relates to Conditions 68-73 of the discharge permit R/REG/2014/4796. The OMP is generally consistent with the draft OMP dated February 2015 which was provided in support of the resource consent application.

1.1

PURPOSE OF ODOUR MANAGEMENT PLAN

The purpose of this OMP is to identify specific measures for the control of potential air discharges from the OMS strengthening works that could be deemed as noxious, offensive or objectionable. As explained in Section 2.1.3 of this OMP, there is a requirement to strengthen a section of the OMS in order to allow for subsequent construction works associated with CRL. There is the potential that these strengthening works could result in odour for a period of time if not appropriately mitigated, and the resource consents therefore require odour control measures to be implemented. While the primary purpose of the OMP is to manage potential odour effects associated with the OMS strengthening works, there is also potential for dust emissions from Project construction activities as a whole if appropriate mitigation measures are not implemented. The OMP therefore includes a section relating to dust mitigation.

1.2

CONSENT REQUIREMENTS

Table 1 outlines the relevant consent conditions from discharge permit R/REG/2014/4796 and how these are addressed within the OMP.

CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

PAGE 8 OF 20


ODOUR MANAGEMENT PLAN Doc No: 025-Y023-2719 REVISION: 06 DATE: 26-June-2017

Table 1 OMP conditions from discharge permit R/REG/2014/4796 and the relevant sections of this document

Condition Number

68

69

70

Specific conditions – discharge permit R/REG/2014/4796

71

72

73

1.2.1

Condition All processes on site shall be implemented, operated, maintained, supervised, monitored and controlled so that any emissions authorised by this consent are maintained at the minimum practicable level. Unless provided for by Condition 70, there shall be no odour beyond the boundary of the worksite caused by discharges from the aspects of the Project related to the Orakei Main Sewer which, in the opinion of an enforcement officer, is noxious, offensive or objectionable. All offensive or objectionable odours beyond the boundary of the worksite caused inadvertently as a result of processes on site shall be mitigated as soon as practicable in accordance with the requirements of the Odour Management Plan submitted in accordance with Condition 72. Beyond the boundary of the worksite, there shall be no hazardous air pollutant, caused by discharges from the aspects of the Project related to the Orakei Main Sewer that causes, or is likely to cause, adverse effects on human health, environment or property. An Odour Management Plan (OMP) shall be prepared by a suitably qualified person and provided to the Council (Team Leader Central Monitoring) for certification at least 20 working days prior to the commencement of works. Auckland Council shall provide the determination to the Consent Holder, in writing, of whether the OMP can be certified as per the requirements of the relevant consent conditions within 10 working days of receipt of the OMP. The purpose of the OMP is to provide specific details related to the control of potential air discharges that could be deemed as noxious, offensive or objectionable, associated with the construction of the aspects of the Project related to the Orakei Main Sewer. The OMP shall be generally consistent with the draft OMP dated February 2015 and provided in support of the application material. All works shall be undertaken in accordance with the certified OMP.

Section Addressed in

Document in full

4.1, 5.1

1, 4.1, 5.1

4.1, 5.1

Document in full

1, 4.1

Sustainability

AT is seeking an Infrastructure Sustainability Council of Australia (ISCA) Infrastructure Sustainability (IS) rating for the CRL enabling works, including the stormwater main realignment and OMS strengthening works. Full details are included in the Project’s Sustainability Management Plan. Project sustainability requirements that relate directly to the OMP are included in the ISCA appendix (Appendix A).

CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

PAGE 9 OF 20


ODOUR MANAGEMENT PLAN Doc No: 025-Y023-2719 REVISION: 06 DATE: 26-June-2017

1.3

OMP AUTHOR

This OMP has been prepared by Andrew Curtis, an Associate Director and leader of the air quality team for AECOM. Andrew has more than 28 years engineering experience and almost 19 years’ experience as an air quality consultant, in which time he has been responsible for leading some of New Zealand’s largest air quality projects.

2.

PROJECT DESCRIPTION

This section presents a summary of the Project works in relation to the matters addressed by the OMP. A detailed description of the construction methodology is provided in the CEMP.

1.4

SUMMARY OF METHODOLOGY

The Project will commence and be partially completed prior to CRL construction commencing. The duration of the works associated with the stormwater main realignment and OMS strengthening is approximately 18 months. Figure 1 indicates the Project extent between Wellesley Street and Swanson Street, including the location of the OMS works. In summary, the construction works will consist of the following: 1.4.1

Pipe Jacking

The realigned stormwater main will be installed by pipe jacking, a trenchless installation method where pipes are driven horizontally between two vertical shafts using a tunnel boring machine (TBM). The first stage of the pipe jacking will run from Victoria Shaft One to the Swanson Street Shaft. Upon reaching the receiving shaft, the TBM will be lifted out and transported above ground to Victoria Shaft One, whereby the second stage of pipe jacking will occur between this shaft and the Wellesley Street Shaft. Pipe jacking has a number of environmental benefits (e.g. less soil disturbance, reduced dust) over open cut construction, due to the reduced surface interaction required for this method.

CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

PAGE 10 OF 20


ODOUR MANAGEMENT PLAN Doc No: 025-Y023-2719 REVISION: 06 DATE: 26-June-2017

Figure 1 Pipe jack Construction Works: Shaft locations and Pipe jack sequencing

CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

PAGE 11 OF 20


QUALITY MANAGEMENT PLAN Doc. No. Y017-Y003-2719 REVISION 2 DATE 18-July-2017

1.4.2

Shaft Construction

A total of four shafts will be constructed for the Project as shown in Figure 1. Three construction shafts will be required at the following locations along Albert Street in order to install the new stormwater main: •

Victoria Street (Victoria Shaft One): Main shaft / TBM Launch shaft (12 m x 12 m plan by 18.8 m deep).

•

Swanson Street: TBM Stage 1 Reception Shaft (3.5 m diameter excavation, 16 m deep)

•

Wellesley Street: TBM Stage 2 Reception Shaft (4.5 m diameter excavation, 15.5 m deep)

The fourth shaft is required for the OMS strengthening works (refer Section 2.1.3 below): •

1.4.3

Victoria Street West (Victoria Shaft Two): OMS access shaft (upstream access to sewer; 9.5 x 7.6 m plan by 22 m deep)

OMS Strengthening

A glass-reinforced plastic (GRP) liner will be installed into the profile of the OMS which will then be grouted in place. This will reduce the risk of damage to the sewer during subsequent construction of the CRL works. To install this liner, and to comply with health and safety regulations for working in confined spaces, it will be necessary to use two access shafts, one upstream and one downstream of the strengthening works. 1.4.4

Utilities Relocation

In addition to relocating the stormwater main, other utilities also need to be relocated to make room for installation of the pipe jack shafts. Further detail on Utilities relocation can be found in the CEMP for the Project.

3.

AIR DISCHARGES

The main potential discharge associated with the proposed OMS strengthening works is odour, generated by the decomposition of sewage. Exactly how much odour will be present is difficult to assess as there are a range of factors that will influence it. However, in the worst-case conditions it is likely that there will be significant concentrations of hydrogen sulphide and other reduced sulphur compounds which could be considered odorous. There is also potential for there to be other gases such as methane and carbon dioxide which while they are odourless do have the potential to result in other effects, such as asphyxia or in the case of methane explosions. The monitoring and mitigation of compounds relating to these effects are addressed in the Contaminated Soils Management Plan (Appendix F to the CEMP for this Project). There is also some potential for dust emissions associated with the earthworks. Given the relatively small area of exposed earthwork surfaces for the Project, however, these effects should be minimal with the use of standard construction dust control measures.

CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

PAGE 12 OF 20


QUALITY MANAGEMENT PLAN Doc. No. Y017-Y003-2719 REVISION 2 DATE 18-July-2017

4. 1.5

CONTROL MEASURES ODOUR CONTROL MEASURES

The two access shafts that will be required to reach the level of the OMS will remain open to street level for the duration of the strengthening works, to allow for worker and equipment access. As a result, there is the potential for odour to be released. At the western (i.e. upstream) end of the section of OMS to be strengthened, a bulkhead will be installed which will divert air and liquid wastewater flow into a wet well. From the wet well, both air and liquid will be pumped through two separate pipes in a diversion line to Victoria Shaft One and then back into the OMS through another bulkhead at that location. This allows the OMS to operate as a closed system while the strengthening works are being undertaken. The diversion line will be at roughly the same level as the OMS and does not rise to the surface. The diversion line will be installed using pipe jacking. Figure 2 illustrates this method. Figure 2 Odour Control Measures

An odour control system will be required in order to control odour emissions expected to occur when the OMS is broken into to install the bulkheads. Two alternative methodologies are proposed for odour suppression, with a final choice depending on equipment availability and conditions at the time. The first method is in line with that proposed in the resource consent application and will involve: •

Installing a ventilation system to capture any odours that might be released around the work areas. The system will be required when the diversion bulkheads are being installed, and may be required while the strengthening works are occurring, depending on how well the bulkheads seal.

•

A forcing ventilation system and biox odour treatment system within the shaft to provide fresh air and neutralising agent. This system will be designed to minimise the potential for adverse odours from the work site affecting the local receiving environment beyond the site boundary

CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

PAGE 13 OF 20


QUALITY MANAGEMENT PLAN Doc. No. Y017-Y003-2719 REVISION 2 DATE 18-July-2017

The second method makes use of a Biox fogging air curtain. This suppresses odours and harmful gasses by misting a suppression agent across the exposed sections of the sewer main within the shaft. This system has proven effective during other works to strengthen the OMS at Stanley Street. Fixed gas monitoring will be completed on a continuous basis during the works and will monitor Methane, Carbon Monoxide, Oxygen and Hydrogen Sulphide. Once the excavation has reached the OMS, and when personnel are working within the OMS, hand held gas detection will also be employed by a suitably trained individual for Hydrogen Sulphide, Methane, Carbon Monoxide, Oxygen, Nitrogen Dioxide and Carbon Dioxide. Levels wil be recorded each shift on the Shift Operations Report Form. Table 2 outlines recommended personal monitoring alarm levels relating to contamination. In the event that any of the alarm levels are exceeded, works will cease and all workers will vacate the area until such time as atmospheric conditions have returned to normal (background), or appropriate control measures are adopted to prevent potential exposure to contaminants. Table 2 Personal Monitoring Alarm Levels

Compound

Alarm Level

Lower Explosive Limit (LEL)

2%

Oxygen (O2)

Below 19.5 % and above 22 %

Hydrogen Sulphide (H2S)

5 ppm

1.6

DUST CONTROL MEASURES

Given the relatively small volumes of material being excavated, and the likely wet nature of much of the material, it is not considered that there is a significant potential for dust emissions. However the following mitigation measures will be implemented to ensure that there is no potential for dust nuisance effects to occur. Set out in Table 3 are the dust mitigation measures that will be used, as applicable, to control any dust effects associated with shaft excavation and the disposal of spoil from the pipe jacking process. These mitigation measures are standard practice, are extensively used and have been proven to be effective for this purpose. However, the list is not exhaustive, and if additional methods are identified which may be more effective these will be implemented. Table 3 Dust Management Measures

Source of Dust Stockpiles

Sealed surfaces Vehicles

Miscellaneous CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

Control •

Limit the height and slope of stockpiles to reduce wind entrainment;

•

Where practical orientate stockpiles to maximise wind sheltering as much as possible;

•

Keep active stockpiles damp at all times or bunker or cover stockpiles of fine materials;

•

Dampen inactive stockpiles if they are producing visible dust emissions;

•

Limit the volume of material in the stockpiles to a maximum of 40m3.

•

Regular removal of dust through washing or vacuum sweeping;

•

Clear all spillages on sealed surfaces as soon as practicable.

•

Limit load sizes to avoid spillages;

•

Cover loads of fine materials;

•

Minimise mud and dust track out by using wheel cleaning facilities if required at site exits to sealed roads.

•

Ensure sufficient water is available on site; PAGE 14 OF 20


QUALITY MANAGEMENT PLAN Doc. No. Y017-Y003-2719 REVISION 2 DATE 18-July-2017

Excavation

5. 1.7 1.7.1

•

Take account of daily weather forecast wind speed, wind direction and soil conditions before commencing an operation that has a high wind potential;

•

Limit drop heights when moving spoil or loading trucks.

MONITORING ODOUR MONITORING Monitoring for Fugitive Odour

Site Personnel will undertake daily fugitive odour monitoring during the working week and ensure that appropriate action is undertaken in the event that objectionable or offensive odours persist. Odour Monitoring Form 025-Y020-2719 will be used as attached at Appendix C.

1.8

DUST MONITORING

The overall approach to dust control is primarily based on visual monitoring in combination with good management of the construction areas and a rapid response to any complaints received. Good practice focusing on pre-emptive measures will aid in the avoidance of significant dust emissions, or if dust emissions occur, the subsequent mitigation or remediation of any adverse effects. Proactive monitoring for dust will involve a weekly inspection item, documented on the project’s weekly environmental inspection checklist, to inspect pavements and building facades for dust build up. Reactive monitoring will include response to complaints and / or obvious dust discharges from site. 1.8.1

Visual Inspection and Monitoring Methods

General visual monitoring of all construction areas will be undertaken on a daily basis or potentially more frequently, if weather or project conditions change. This type of monitoring relates to the control measures described in Section 4 and will include pre-emptive measures to avoid dust emissions. Table 4 below describes the monitoring programme. The Site Engineer will be responsible for undertaking dust monitoring. Table 4 Visual Dust Monitoring Programme

Monitoring Activity

Frequency

Check weather forecasts for strong winds and rainfall to plan appropriate work schedule and dust management response.

Daily

Inspect land adjacent to the site, construction exits and adjoining roads for the presence of dust deposition.

Twice daily

Observe weather conditions including wind and rain via observations and data outputs from weather stations.

Daily and as conditions change

Inspect all exposed surfaces for dampness and to ensure that the exposed un-stabilised area is minimised.

Daily and as conditions change

Inspect watering systems (sprays and water carts) to ensure equipment is maintained and functioning to effectively dampen exposed areas.

Weekly

CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

PAGE 15 OF 20


QUALITY MANAGEMENT PLAN Doc. No. Y017-Y003-2719 REVISION 2 DATE 18-July-2017

Monitor dust generating activities and water application rate.

In winds, over 11 knots of Beaufort Scale 3 (see Appendix B)

Check for dust on local roads being used to access the site.

Daily

Inspect any wheel wash equipment that may be required to ensure effective operation.

Weekly

6.

CONTINGENCY MEASURES

Table 5 describes the key risks associated with the OMS odour mitigation system and the contingency measures to address them. Table 5: Risk events and contingency measures for OMS odour mitigation system.

Risk event

Contingency measure

Failure of air extraction systems resulting in fugitive odour release.

• Back up electricity generators will be available and able to be connected to the air extraction system to ensure its continued operation.

Fugitive odour exceeds the threshold of 0.35ppb for H2S despite the use of a carbon filter or Odour neutralising spray

• Cover and compartmentalise the works area using work tents, tarps or more rigid structures to reduce air flow

7.

• Spare parts for critical components of the extraction system will be available at short notice from the suppliers for repairing the system.

• Provide additional odour neutralising spray • Where odour neutralising spray is used as a primary treatment method, and threshold exceedances cannot be prevented, employ a carbon filtration system as a fall-back position.

COMPLAINT PROCEDURES

In the event that odour or dust related (including external/community) complaints are received, the procedures detailed in Section 4.4.5 of the Project CEMP will be followed. All complaints will be recorded in the Enquiry and Complaints Register.

CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

PAGE 16 OF 20


QUALITY MANAGEMENT PLAN Doc. No. Y017-Y003-2719 REVISION 2 DATE 18-July-2017

8.

APPENDIX A: ISCA REQUIREMENTS

AT and Connectus are seeking an Infrastructure Sustainability Council of Australia (ISCA) Infrastructure Sustainability (IS) Rating for the CRL Enabling Works – including the stormwater main realignment and OMS strengthening works. This appendix details IS requirements that are different, or additional to the Project’s Consent Requirements. It is essential that these requirements are met to achieve the Project’s sustainability goals; however, they are not consent requirements to be certified by Auckland Council. These IS rating requirements are included as an appendix because they are not yet fixed. They remain subject to change as the Project’s sustainability program evolves. Applicable ISCA requirements that relate to this OMP are listed below along with their associated target Levels. ISCA Category DIS – 4 Air Discharge

Target Level 2

Construction Requirements

How we aim to achieve this

Measures to minimise adverse impacts to local air quality during construction have been identified and implemented.

Section 4

AND Monitoring of air emission and / or air quality is undertaken at appropriate intervals and in response to complaints during construction. AND Monitoring and modelling demonstrates no recurring or major exceedances of air emission or air quality goals.

Section 5 Note: Section 7.11.1 of the Assessment of Environmental Effects identifies the potential for a dust nuisance as limited. This is consitant with a signifigance assessment of 1 or 2 within the ISCA TC DIS-4.01 21/11/2013. Therefore, visual monitoring has been deemed appropriate. The weekly site inspection checklist will be amended to require inspection staff to proactively inspect surfaces (window sills etc.) adjacent to the work sites for evidence of dust build up. Section 5 for monitoring

CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

PAGE 17 OF 20


QUALITY MANAGEMENT PLAN Doc. No. Y017-Y003-2719 REVISION 2 DATE 18-July-2017

9.

APPENDIX B: BEAUFORT CHART

Beaufort Description Force

Speed Specification on land Knots

km/h

m/s

Less than Less than Less than 1 1 1

0

Calm

Smoke rises vertically.

1

Very Light

Direction of wind shown by smoke drift but not by wind vanes.

1-3

1-5

0.3 – 1.4

2

Light breeze

Wind felt on face, leaves rustle, ordinary wind vane moved by wind.

4-6

6 - 11

1.67 - 3

3

Gentle breeze

Leaves and small twigs in constant motion, wind extends light flag.

7 - 10

12 - 19

3.3 – 5.3

4

Moderate breeze

Wind raises dust and loose paper, small branches move.

11 - 16

20 -29

5.6 - 8

5

Fresh breeze

Small trees in leaf start to sway, crested wavelets on inland waters.

17 - 21

30 - 39

8.3 – 10.8

6

Strong breeze

Large branches in motion, whistling in telegraph wires, umbrellas used with difficulty.

22 - 27

40 - 50

11.1 – 13.9

7

Near gale

Whole trees in motion, inconvenient to walk against wind.

28 - 33

51 - 61

14.2 – 16.9

8

Gale

Twigs break from trees, difficult to walk.

34 - 40

62 - 74

17.2 – 20.6

9

Strong gale

Slight structural damage occurs, chimney pots and slates removed.

41 - 47

75 - 87

20.8 – 24.2

10

Storm

Trees uprooted, considerable structural damage occurs.

48 - 55

88 - 101

24.4 - 28

11

Violent storm

Widespread damage.

56 - 63

102 - 117 28.3 – 32.5

12

Hurricane

Widespread damage.

>64

CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

>119

>33

PAGE 18 OF 20


QUALITY MANAGEMENT PLAN Doc. No. Y017-Y003-2719 REVISION 2 DATE 18-July-2017

10. APPENDIX C: ODOUR MONITORING Auckland City Rail Link Project

Project No:

2719

Complete this form for odour monitoring – Required by the AQMP (CRL-PAT-ENV-CON-PLN-000899) Monitoring Details: Date:

/

/

Wind Speed:

Time:

Wind Direction:

Location:

Nearest sensitive receiver:

Likely Source:

Distance to nearest receptor:

Odour Type: (What does the odour smell like?) ☐ Fragrant

☐ Bark-like, birch bark

☐ Like blood, raw meat

☐ Like Gasoline, solvent

☐ Perfumy

☐ Woody, resinous

☐ Rubbish

☐ Fishy

☐ Sweet

☐ Medicinal

☐ Compost

☐ Putrid, foul, decayed

☐ Fruity

☐ Burnt, smoky

☐ Silage

☐ Paint-like

☐ Bakery (fresh bread)

☐ Soapy

☐ Sickening

☐ Rancid

☐ Coffee-like

☐ Garlic, onion

☐ Musty, earthy, moldy

☐ Sulphidic

☐ Spicy

☐ Cooked vegetables

☐ Sharp, pungent, acid

☐ Dead animal

☐ Meaty (cooked, good)

☐ Chemical

☐ Metallic

☐ Fecal (like manure)

☐ Sea/marine

☐ Etherish, anaesthetic

☐ Tar-like

☐ Sewer odour

☐ Herbal, green, cut grass

☐ Sour, acrid, vinegar

☐ NO ODOUR

☐ Oily, fatty

Odour Intensity: 0 - 5 (Taken at 1 minute intervals for a period of ten minutes) Odour Intensity Description

Reading No.

Intensity Level

Reading No.

0 Not perceptive

1

6

1 Very weak

2

7

2 Weak

3

8

3 Distinct, nuisance only if continuous

4

9

4 Moderately strong, nuisance with frequent occurrences

5

10

Intensity Level

5 Extremely strong No.

Remedial Actions:

Date Due:

Responsibility:

Monitoring signoff: Monitoring Name:

Person

Project Environmental Representative Name: CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

Signature:

Date:

Signature:

Date:

PAGE 19 OF 20


QUALITY MANAGEMENT PLAN Doc. No. Y017-Y003-2719 REVISION 2 DATE 18-July-2017

CONNECTUS PROJECT NO. 2719 CITY RAIL LINK LIMITED

PAGE 20 OF 20