Local Board Chairs Update| 13 March 2017
City Growth
Progress • • • •
Land designation and consents Surface property bought and subterranean negotiations started Regional consents in appeal Designation alterations underway
C1- Britomart works •
New Britomart accommodation opened in January and CPO entrances closed. CPO interior now being removed.
C2- Albert St works • •
Albert St piling halfway Pipejack from Victoria to Swanson St completed and now heading to Wellesley St
Other •
First contract documents out to market
New Britomart entrance
Mana Whenua • • • •
Engaged with the project since 2012 Building a relationship of trust Monthly forum Workshops Influence: •
Maramatanga
Cultural appreciation Design Consents Sustainability Induction Monitoring
Delivering the CRL Sustainably Setting the benchmark for designing, building and operating sustainable infrastructure •
Early construction contracts
•
Leading rating for C2
•
World first for integrating Mana Whenua values
•
Targeting zero waste to landfill
•
Measuring and reducing carbon footprint
•
Social value through procurement
•
Reporting performance
CRL Ltd Structure
Contracts
Development Potential •
Britomart Station
•
Aotea Station - above and beside
•
Karangahape Station - above
•
Mt Eden - 2.4ha