Karangahape Community Liaison Group Meeting 9 July 2019


Agenda • Introduction to the Link Alliance • Upcoming utility investigation and relocation works • Preparation of draft management plans for those utility works • Link Alliance works in other locations • Wider project update

2


Introductions •

Dale Burtenshaw, Deputy Alliance Director

•

Hugh Leersnyder, Environment, Sustainability & Planning Manager

•

Rachel Blundell, Senior Communications & Stakeholder Manager

•

Sonya Leahy, Stakeholder Communications Manager

•

Aidan Kirkby-McLeod, Senior Planner

•

Mark Anderson, Utilities Manager

•

Jonathan Hill, Karangahape Station Construction Manager

3


Introducing the Link Alliance • Alliance model often used to deliver complex and challenging projects • Promotes innovation and flexibility and helps drive value for money, as companies equally share the gains and the pains involved in delivery

• Link Alliance partners: • Construction: Vinci Construction Grands Projets, Soletanche Bachy International NZ and Downer NZ • Design: AECOM, Tonkin+Taylor, WSP Opus • CRL Limited

• International team with local experience - spanning rail projects in

Hong Kong, Singapore, Qatar, Egypt and Auckland’s own Waterview Tunnel

• Knowledge transfer – staff with C1/C2 experience teaming with embedded CRL staff

4


The Link Alliance - delivering Auckland’s first underground

5


Overview programme (all dates approximate) Key Milestones

2019

2020

2021

Enabling works, including utilities, demolition

Q3

•

Q3

Mt Eden Station

Q4

•

Karangahape Station

Aotea Station

Testing and commissioning

2022

2023

2024

•

•

•

Q1

Q1

•

•

•

Q1

Q1

•

•

•

Q1

Q2

Q4

6


What’s happening right now? • Alliance mobilisation at a temporary office in Ellerslie • Negotiating PAA with CRL Ltd • Preparing material for communication and engagement about enabling works

• Planning and preparation for early works • Recruitment and staffing • Preparation of management plans for consenting • Establishing interfaces with K Road Enhancements Project, C2 contract, C5 & C7 contracts

Karangahape Station’s Mercury Lane entrance

7


8


What’s happening first in the Karangahape area? • Utility investigations – Beresford Square and corner of Mercury Lane & Cross St – Aug 2019

• Utility relocations – Beresford Sq/Pitt St & Mercury Ln/Cross St – late 2019

• Closure of Beresford Square – late 2019 onwards • Asbestos testing in Mercury Lane & East St buildings to be demolished – July to Sept 2019

• Asbestos removal and soft-strip/salvage – Sept to Dec 2019

• Site establishment in Beresford Square (former Wilson’s carpark) – Oct 2019

• Demolition of buildings (in red zone) – approx. Dec 2019 to Q1 2020

9


Location of utility investigations in Beresford Square & Mercury Lane – August 2019

10


Tree and toilet demolition – planned for September 2019

11


Utility relocations in Pitt Street area – planned October to December 2019

Road closed to traffic

12


Utility relocations – Beresford Square & Pitt Street – December 2019 to January 2020

Road closed to traffic

13


Potential utility relocation – subject to station design confirmation – Feb to Mar 2020

Road closed to traffic

14


Potential utility relocation – subject to station design confirmation – Feb to Mar 2020

Road closed to traffic

15


Utility relocations – Mercury Lane – October to December 2019

16


Utility relocations – other side of Mercury Lane – December 2019 to February 2020

17


Managing utility relocations • We appreciate that utility diversions will be noisy and disruptive and will work to manage negative impacts as much as practicably possible.

• Beresford Square will need to be closed to traffic

to enable us to undertake the relocations quickly and safely. It will then remain closed, as this is the site of the Beresford Square entrance of the future Karangahape Station.

Beresford exit

• Property access will be maintained. However,

there may be times when we need to liaise with you about the timing of works directly outside your premises to minimise disruption, i.e. weekends or evenings.

View to station entrance from Cross St 18


Managing utility diversions

View towards Beresford Square from Pitt St

• Pedestrians may need to be re-routed around works on the footpath.

• We will use water-filled barriers and temporary fencing wherever possible to maintain visibility for businesses.

• A development response plan is being developed

to help mitigate the impacts of construction works on the local community. It will complement the DR plan currently in place for the K Road area to support businesses as much as practicably possible.

• This CLG will be an important avenue for receiving and giving feedback on the project and its management of construction impacts.

View down Mercury Lane to station entrance 19


Developing management plans for utility relocation works • A suite of management plans are required by

• We are aiming to provide summaries of the draft management plans to CLG members in mid-August and will then meet to discuss these with you.

• The management plans are developed by

• The subject matter experts who have drafted the plans will attend this CLG meeting so you can provide your feedback directly and ask any questions.

the CRL designation and the regional resource consent to manage the effects of construction. subject matter experts, covering such areas as: • Traffic, access and parking • Noise and vibration • Social impact and business disruption • Air quality • Contamination

• The plans will then be finalised before undergoing an independent peer review and lodgement with Auckland Council for final approval.

• Trees and vegetation

20


Consultation to inform draft management plans • The plans outline how we will manage effects during the utility diversions – noise, dust, potential access and parking disruption, etc. • We need to understand how people could be affected so that the management plans we prepare are effective. • The preparation of the Social Impact & Business Disruption Delivery Work Plan and Site-Specific Construction Noise & Vibration Management Plans will involve direct engagement with those in close proximity to the works.

View up Mercury Lane to station entrance

• The CLG also provides valuable input and feedback. 21


Communications & Engagement – managing impacts with care & consideration • Interface with connected projects - C1/C2 contract on Albert St & K Road enhancements project • Development Response – business packs and support • Community Liaison Groups • Working with Mana Whenua, Local Boards, Business Associations and Auckland Council • Campaigns for significant traffic switches for buses, cyclists and drivers • Activations/events • Hoardings • Construction updates • Meet the Alliance events

22


What works are starting elsewhere on the CRL project this year? Albert Street (Wyndham St to Mayoral Drive)

• Utility investigations starting week of mid-late August – taking about a month to complete

• Utility diversions starting at Wyndham St end of

Albert St – completed in stages from end of August 2019 until mid 2020

• Seven canopy removals (various locations along Albert St and cnrs of Victoria & Wellesley) – December 2019 to Q2 2020

• Site establishment at Bledisloe carpark – Q4 2019 • Piling and D-wall construction for Aotea Station ground support – starts Q2 2020

23


What works are starting elsewhere on the CRL project this year? Mt Eden

• Soft-strip & salvage work within the Mt Eden

demolition area – aiming for mid-July 2019 start (will take about 3 months)

• Temporary site office established July/Aug at 97 Mt Eden Rd (next to existing station ramp)

• Erection of hoardings around the demolition site – Aug 2019

• Asbestos removal – Aug to Oct 2019 • Demolitions – Sept 2019 to Q1 2020 (approx.) • Portal works – piling and ground retention for tunnel entrance – starts Dec 2019.

24


C1 Britomart & Lower Queen St • Construction of tunnel base slabs underneath the CPO is

complete for both tunnels and onstruction of tunnel walls has commenced

• Construction of tunnel base slabs in Lower Queen St is

complete and construction of tunnel walls has commenced

• Preparatory works within station underway to allow

installation of an additional – fourth – escalator and replace the existing ones with metro grade escalators

• Half a million man hours on C1 with no lost time injuries • Minimal movement of CPO building and minimal effect on adjacent buildings

Lower Queen Street

The north tunnel – breaking through to Britomart Station

25


Lower Queen St plaza – new design renders

26


C2 Albert Street works update • Wyndham St has reopened after three years • Above-ground works have started, including

installation of new utility services, tree pit construction and new finished footpath and road carriageway

• Tunnel floors and walls are largely complete with only one more section of roof to be poured

• Tunnel box construction expected to be completed by July

• Canopy removals are underway

The north tunnel – breaking through to Britomart Station

27