Recommendation on an outline plan of works under s176A of the Resource Management Act 1991 Application number(s):
OPW60339200
Requiring authority's name:
City Rail Link Limited (CRLL)
Site address:
Project Area bounded by Canada Street (south), East Street (west), and Mercury Lane (east).
Legal description:
Pt Allotment 8 SBRS OF Auckland SECT 7, Lot 4 DP 51945, Lot 3 DP 51945, Lot 1 DP 71575, Pt Lot 1 DP 82089, Lot 1 Deeds Plan 1082, Allotment 62 SBRS OF Auckland SECT 7, Pt Lot 1 DP 45190, Pt Allotment 9 SBRS OF Auckland SECT 7.
Records of Title:
NA103D/292, NA92B/899, NA103D/291, NA129A/195, NA92B/900, NA75C/630, NA92B/903, NA67C/819, NA43B/35, NA38D/205, NA541/140, NA140/278.
Proposed work / project: The demolition of buildings in the Project Area including foundations, and the removal and disposal of all demolished material and disturbed ground to enable construction of the proposed City Rail Link (CRL) underground station at Karangahape Road, including the Mercury Lane entrance.
Recommendation I have read the outline plan of works (OPW), supporting documents, and the report and recommendations on the OPW. I am satisfied that I have sufficient information to consider the matters required by the Resource Management Act 1991 (RMA) and make a recommendation under delegated authority. The OPW does show that: 1.
The project and the proposed works are within the scope of CRL Designation 25004 (and associated conditions); and
2.
The OPW has sufficient detail to describe the proposed works and measures to manage adverse effects under s176A(3).
Acting under delegated authority, the following change to the OPW is recommended to be requested under section 176A to better manage adverse effects from the proposed works: 1.
Prior to the demolition works commencing, the C3 Alliance Contractor shall provide to the Auckland Council Compliance Monitoring Officer the final version of the SiteSpecific Construction Noise Management Plans for 16D and 16E East Street and the final version of the Site-Specific Construction Vibration Management Plan for 14 East Street.
Advice notes This recommendation on the outline plan of works recognises the scope of works enabled under the CRL designation. This covers only any activity that would otherwise infringe a rule in a district plan under the RMA. The requiring authority is responsible for identifying and obtaining all other necessary consents and permits. These may include: •
• • •
Any relevant resource consents both under any relevant national environmental standard (e.g. NES for assessing and managing contaminants in soil to protect human health), and any relevant regional rules under the operative and proposed regional plan(s) and regional coastal plan(s) the Building Act 2004 any relevant Auckland Council bylaws Heritage New Zealand Pouhere Taonga Act 2014.
Recommendation approved by:
Barry Kaye Duty Commissioner
21 June 2019
Schedule 1 1.
The proposed works / project has been confirmed as falling within the scope of the City Rail Link designation (Auckland Unitary Plan ref. 2500-4) and satisfying s176A RMA on the basis of the recommended change to manage demolition effects and being undertaken in accordance with the plans and all information submitted with the outline plan of works, detailed below, and all referenced by the council as OPW60339200. •
Outline Plan of Works and assessment prepared by Aurecon, dated 16 May 2019
Report title and reference
Author
Rev
Dated
CRL-KRD-RME-000-RPT-0129 Karangahape Road Demolition Works Outline Plan
Aurecon
1.0
16 May 2019
CRL-KRD-RME-000-RPT-0130 Construction Environmental Management Plan
Aurecon
1.0
16 May 2019
CRL-KRD-RME-000-RPT-0134 Erosion and Sediment Control Plan
Aurecon
3.0
11 April 2019
CRL-KRD-RME-000-RPT-0138 Transport Access and Parking Delivery Work Plan
Flow Transportation Consultants
5.0
16 May 2019
CRL-KRD-RME-000-RPT-0137 Construction Noise and Vibration Delivery Work Plan
Marshall Day Acoustics
3.0
15 April 2019
CRL-KRD-RME-000-RPT-0136 Historic Character Delivery Work Plan Archaeology Section
Clough and Associates Ltd
4.0
7 May 2019
CRL-KRD-RME-000-RPT-0135 Contamination Delivery Work Plan
Golder Associates (NZ) Ltd
Rev1
13 May 2019
CRL-KRD-RME-000-RPT-0133 Air Quality Delivery Work Plan
Golder Associates (NZ) Ltd
Rev0
7 May 2019
CRL-KRD-RME-000-RPT-0131 Social Impact and Business Disruption Delivery Work Plan
Aurecon
1.0
9 May 2019
CRL-KRD-RME-000-RPT-0132 Communication and Consultation Plan
Aurecon
3.0
17 May 2019
•
Communication and technical memos provided during application processing
Email correspondence and reference
Author
Dated
Email request for technical comments
Warwick Pascoe
22 May 2019
Email with technical memo CDWP
Marija Jukic
28 May 2019
Email with technical memo TAP DWP
Flynn Roser
28 May 2019
Email with initial technical memo Social Impacts and Business Disruption DWP
Dr Jennifer Joynt
28 May 2019
Email with technical memo CEMP and ESCP
Tim O'Grady
29 May 2019
Email with technical memo HC DWP
Myfanwy Eaves
29 May 2019
Email with technical memo AQDWP
Paul Crimmins
29 May 2019
Email with matters of clarification on TAP DWP to CRLL
Emily Allan
10 June 2019
Email with clarification from CRLL on the TAP DWP
Aidan KirkbyMcLeod
12 June 2019
Email with technical memo CNV DWP
Daniel Winter
13 June 2019
Email with final technical memo Social Impacts and Business Disruption DWP
Dr Jennifer Joynt
17 June 2019
Email with matters of clarification on CNV DWP to CRLL
Blair Masefield
17 June 2019
Email with clarification from CRLL on the CNV DWP
Aidan KirkbyMcLeod
18 June 2019