Statement of Performance Expectations for Financial Year 2021-2022
Table of Contents Statement of Responsibility Project overview
3 4-5
Objectives of the City Rail Link project
7
Performance targets
8
Statement of Forecast Comprehensive Revenue and Expenses
10
Statement of Forecast Financial Position
11
Statement of Forecast Changes in Equity
12
Statement of Forecast Cash Flow
13
Notes to the Forecast Financial Statements
14 - 17
Appendix 18
2
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
Statement of Responsibility CRL Ltd is responsible for the statements contained in this document, including the appropriateness of the business assumptions underlying them. CRL Ltd is also responsible for internal control systems that provide reasonable assurance as to the integrity of its financial reporting.
Sir Brian Roche
Anne Urlwin
Chair
Director
30 June 2021
This Statement of Performance Expectations (SPE) sets out the performance expected of City Rail Link Limited (CRL Ltd) for the period 1 July 2021 to 30 June 2022.
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
3
Karangahape Rd SKY TOWER
Symonds St Connection with Western Line
Central Motorway Junction
Vincent St Pitt St Mayoral Dr
Connects to existing rail network
Albert St
d Bore
Connects to existing rail network
l
e Tunn
Redeveloped Mt Eden Station
l
nne er Tu d Cov
New Karangahape Station
n Cut a
New Aotea Station
CRL Underground Track Cut and Cover Tunnel Bored Tunnel Existing Western Line
Redeveloped Britomart Station
City Rail Link (CRL or the Project) will contribute to a vibrant Auckland by transforming how people travel, live in, work in and enjoy their city.
The Project's scope includes:
It is New Zealand's largest transport infrastructure project ever and a gamechanger for Auckland, delivering a much better rail system for our growing international city.
• Streetscape enhancement around stations and along the entirety of
*Scale is accentuated
BRITOMART STATION
AOTEA CENTRE
• Building 3.45 kilometre twin track underground tunnels connecting Britomart to Mt Eden, with tunnel depths of up to 42 metres underground • Building two new stations; one under Albert Street with entrances at Wellesley and Victoria Streets provisionally named Aotea, and the other under Karangahape Road with entrances at Beresford Square and Mercury Plaza provisionally named Karangahape • Major redevelopment of Britomart Station transforming it into a two-way through station, and major redevelopment of Mt Eden Station Albert Street • Preparing stations and key urban surrounds to enable work by Kāinga Ora and Panuku Development Auckland for the construction of new homes, community spaces and workplaces • Wider network improvements at The Strand, Ōtāhuhu and Newmarket • Capacity for nine-car electric trains on the CRL line and operation of 48 trains per hour in the peak • 100-year asset life The Crown and Auckland Council (CRL's Sponsors) have agreed to co-fund and partner to deliver the Project, and collaborate on other initiatives, seeking to achieve a number of overarching objectives. These include creating significant travel time savings and better connections for Auckland. Once it's built, CRL will double the number of people living within 30 minutes travel of Auckland's city centre and allow for a train at least every 10 minutes during peak.
4
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
Up to 54,000 rail passengers per hour at peak
will also enable a huge building programme of new
times will be able to travel in and out of the inner-
homes, shops and workplaces which are either
city during rush hour after CRL is constructed. To
underway or planned along the new rail corridor. The
move the same number by bus or car would require
station areas will become bustling urban destinations,
another 16 motorway lanes or three more Auckland
opening up the surrounding streets to more foot
Harbour Bridges. Better travel choices will also help
traffic, creating ideal places to live, work and socialise.
ease pressure on Auckland's roads and reduce bus congestion in the city centre.
Functions and Operations
Each CRL station and key urban surrounds will enable
The CRL Ltd Board provides governance and
future development by other agencies. The greatest
assurance that management is delivering to the
opportunity to create new homes, community spaces
objectives. The Chief Executive has appointed a
and workplaces is within the 107,000sqm available
leadership team to provide direction and oversight
around the Mt Eden Station, where Sponsors have
to the activities of CRL Ltd. CRL is managed via
indicated their support for a new development
a series of workstreams, and team structure is
Blueprint. The civil, urban realm and infrastructure
adapted progressively in keeping with the evolving
works necessary to enable Sponsor approved designs
requirements of the Project through its lifecycle.
will be delivered by CRL Ltd with Kāinga Ora and Panuku Development Auckland leading the overall
Establishment and Ownership
development.
CRL Ltd commenced its first year as an operating
CRL Ltd's partnership with Mana Whenua ensures the
company on 1 July 2017. CRL Ltd reports regularly to
Project is embedded with cultural and kaitiaki values,
its Sponsors (the Crown and Auckland Council), as set
and that it benefits from Māori mātauranga across all
out in the Project Delivery Agreement (PDA), and to
relevant project stages. World class stations, designed
the Sponsors (the Crown as 51 per cent shareholder
together with Mana Whenua, will be unique to New
through the Minister of Transport and Minister of
Zealand; recognising the cultural and historic ties of
Finance, and 49 per cent shareholder Auckland
Iwi to Tāmaki Makaurau.
Council) as required by the Companies Act, Crown
CRL will help shape New Zealand's economic growth, job creation and the upskilling of its workforce will
Entities Act and the Crown Companies Owners' Expectations Manual.
benefit. New Zealand for years to come. The Project
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
5
6
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
What CRLL intends to achieve in 2021/2022 In conjunction with the Statement of Intent, this Statement of Performance Expectations describes key focus areas in 2021/2022 to help us achieve key performance targets. These targets support the objectives of the Project and CRL Ltd. CRL Ltd will report on its performance in implementing these activities in its 2021/2022 Annual Report. CONTRACT
CONTRACTOR
SCOPE
C1
Downer Soletanche Bachy Joint Venture (awarded July 2016)
Creation of temporary Britomart Station passenger facility, construction of tunnels from below Britomart to former Downtown Shopping Centre (DSC) site and streetscape enhancement on Lower Queen Street and around Britomart Station
C3
Link Alliance (Vinci, Downer, Soletanche Bachy, WSP Opus, Aecom, Tonkin+Taylor, CRL Ltd)
Tunnels from just south of Wyndham Street to the North Auckland Line (NAL) at Mt Eden, building two new stations at Aotea and Karangahape and redeveloping Mt Eden Station
C5*
Link Alliance (awarded as part of expanded C3 contract)
Connection of tunnels into existing North Auckland Line live rail corridor environment
C7*
Link Alliance (awarded as part of expanded C3 contract)
Rail systems, integration testing and commissioning from Britomart to Mt Eden Station
C8
Newmarket Junction (KiwiRail)
New crossover and associated signaling equipment at Newmarket
C9
Britomart East
Remodelling of Britomart East junction to increase trains per hour capacity including structural alterations to achieve this
*The C5 and C7 contracts were included per Variation Agreement to the Project Alliance Agreement, dated 20 October 2020. CRL Ltd is working with the Ministry of Transport to build a focus on national security risks and interests into its procurement framework and processes.
CRL Ltd's Reportable Outputs This section describes CRL Ltd's outputs for the period 1 July 2021 to 30 June 2022 which are reportable under section 149E(1)(a) of the Crown Entities Act 2004. Per the appropriation CRL Ltd's reportable output is to "Deliver the Auckland City Rail Link project by 2024". Per section 149E(1)(c) of the Crown Entities Act 2004, CRL Ltd does not propose to supply any class of outputs in the 2022 financial year that is a non-reportable class of outputs.
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
7
The expected revenue and expense for each reportable output for the financial year 2022 is as follows: DELIVER THE CITY RAIL LINK PROJECT
REVENUE ($'000)
EXPENDITURE ($'000)
Deliver the Auckland City Rail Link project by 2024*
398
204,683
*Subject to determination of COVID-19 impact
The performance of the output will be measured through the Output Measures noted below. CRL Ltd’s Output Classes for the fiscal year 2022 relate to Health and Safety, Project Delivery, Funding Envelope, Sustainability and Social Outcomes, Community and Stakeholder Engagement. STRATEGIC AREA OUTCOME
PERFORMANCE TARGETS AND MEASURES
Health and Safety
Build an • An externally validated maturity assessment of the CRL HSE Management System using the Risk Management Maturity Model (RM3) will achieve Level 3 underground rail (Standardised), and Level 4 (Predictable) in two or more areas by 30 June 2022 link that is safe for constructors, • Total Recordable Injury Frequency Rate (TRIFR) at or below seven injuries per operators, million hours worked maintainers • Annual staff wellbeing survey completed and action plan in place and users • Publish an annual safety assurance summary report by 30 June 2022 reporting on safety for operations, maintenance, and users
Project Delivery
Deliver a safe, operable, quality underground rail link in a timely manner
• Complete C1 by December 2021 • Complete first tunnel boring machine (TBM) drive by February 2022 • L aunch second TBM drive by May 2022 • Aotea Station – complete pilings and foundations works by March 2022 • Complete NAL Down Main line works by April 2022 • Complete award of C9 Britomart East works by December 2021
Funding envelope
Achieve fiscal efficiency
• Meet delivery targets of approved Appropriation ($490m)** • Per the PDA, timely financial reporting of project costs on a cost to complete basis • Operate CRL Ltd’s corporate functions within the approved budget
Sustainability and Social Outcomes
Achieve sustainability excellence including social outcomes
• C1 to achieve “Excellent” Infrastructure Sustainability (IS) “as built” rating • C3 to achieve ‘’Excellent’ Infrastructure Sustainability (IS) ‘’design” rating • 95 per cent of construction demolition waste (including spoil) diverted from landfill • C3 to achieve 15 per cent reduction (versus design base-case) in embodied carbon of materials • Deliver social outcomes pilot "Progressive Employment Programme" with six rangatahi (young people) • Six Link Alliance construction contracts to be awarded to Māori and/or Pasifika small and medium sized enterprises by 30 June 2022
Community and Stakeholder Engagement
Deliver a high level of communications and engagement
• Increased public participation through events (target 8) and site tours (target 25) • Build positive profile of the Project with videos (target 10), social media (target at least 5 posts a week), proactive media releases (target 25) and community newsletter (target 12) • Responsiveness (target 2 working days response to public enquiries)
*Oversite Development: whilst there is no specific target for 2021/22, development work continues, led by Kāinga Ora and Panuku Development Auckland (and supported by CRLL) on this important value creation and capture opportunity for Auckland and as a financial contributor to CRLL. The above is explained in detail in the Outcomes, Target Areas and Measures section of the Statement of Intent. With the upcoming completion of CRLL’s early works contracts (including C1) and expected award of the C9 contract we intend to update the Statement of Intent within FY2022. ** Appropriation reflects the Crown's 50% contribution to FY2022 project funding.
8
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
Forecast Financial Statements The forecast financial statements (on pages 10-13) include a Statement of Forecast Comprehensive Revenue and Expenses, Statement of Forecast Financial Position, Statement of Forecast Changes in Equity and Statement of Forecast Cash Flows for the 2022 financial year. CRL Ltd is funded to deliver the Project. Under the terms set out in the PDA, funding is recognised as share capital. Other funding received by CRL Ltd is by way of rental income from properties purchased to enable construction but not yet decommissioned, and interest on surplus cash balances. These items will be recorded as revenue in the Statement of Forecast Comprehensive Revenue and Expenses. CRL Ltd incurs expenditure as part of its activities. Operating expenditure (i.e., the day-to-day running of CRL Ltd) and project expenditure (i.e., unable to be capitalised) is recorded in the Statement of Forecast Comprehensive Revenue and Expenses. This expenditure is funded by the Sponsors. Project expenditure that is capital in nature is recorded on the Statement of Forecast Financial Position as Capital Work in Progress. Assets are transferred to the shareholders as construction is completed for each asset.
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
9
Statement of Forecast Comprehensive Revenue and Expenses For the year ending 30 June
FORECAST 2020/21
BUDGET 2021/22
$000
$000
Rental revenue
126
117
Interest revenue
466
281
Other revenue
2,503
0
Total Revenue
3,095
398
3,057
3,508
Professional services
864
684
IT expenses
479
559
General expenses
2,515
3,047
Insurance expenses
8,649
8,206
3
0
254
147
14,514
11,192
484
0
218,368
177,034
Depreciation and amortisation expenses
5,405
306
Impairment expenses
2,181
0
256,773
204,683
(253,678)
(204,285)
Revenue
Expenditure Employment expenses
Bad and doubtful debts Lease payments Third party works Capital expenditure write-offs Vested asset expense
Total Expenditure Net Surplus (deficit)
10
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
Statement of Forecast Financial Position For the year ending 30 June
FORECAST 2020/21
BUDGET 2021/22
$000
$000
15,831
19,196
Prepayments
8,331
6,850
Trade and other receivables
7,050
7,437
31,212
33,483
1,519,345
2,291,598
Prepayments
24,566
18,002
Subterranean land
13,064
24,064
117,681
117,610
189
23
Total Non-Current Assets
1,674,845
2,451,297
Total Assets
1,706,057
2,484,780
71,484
74,491
1,555
1,556
-
-
Total Current Liabilities
73,039
76,047
Total Liabilities
73,039
76,047
1,633,018
2,408,733
2,058,280
3,038,280
(425,262)
(629,547)
1,633,018
2,408,733
Assets Current Assets Cash and cash equivalents
Total Current Assets
Non-Current Assets Capital work in progress
Property, plant and equipment Intangibles
Liabilities Current Liabilities Accounts payable and accruals Current employee entitlements Related party payables
Net Assets
Equity Contributed Capital Retained earnings Total Equity
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
11
Statement of Forecast Changes in Equity
BUDGET BUDGET CAPITAL ACCUMULATED LOSSES
For the year ending 30 June Opening balance as at 1 July 2021
BUDGET TOTAL 2021/22
$000
$000
$000
2,058,280
(425,262)
1,633,018
(204,285)
(204,285)
-
-
(204,285)
(204,285)
980,000
-
980,000
3,038,280
(629,547)
2,408,733
Total Comprehensive Revenue and Expenses for the year Deficit for the year Other comprehensive income and expenses
-
Total Comprehensive income and expenses
Owner Transactions Share capital issues Closing balance as of 30 June 2022
12
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
Statement of Forecast Cash Flow For the year ending 30 June
FORECAST 2020/21
BUDGET 2021/22
$000
$000
2,666
122
(41,597)
(28,430)
466
281
(38,465)
(28,027)
(775,292)
(937,540)
(2,271)
(10,971)
(103)
(97)
(777,666)
(948,608)
Proceeds from issue of share capital
790,000
980,000
Net Cash Flows from Financing Activities
790,000
980,000
Net Increase/(Decrease) in cash and cash equivalents
(26,131)
3,365
Cash and cash equivalent at beginning of period
41,962
15,831
Cash and cash equivalent at end of period
15,831
19,196
Cash Flows for Operating Activities Cash received from customers Cash paid to suppliers & employees Interest received Net Cash Flow from Operating Activities
Cash Flows from Investing Activities Acquisition of capital work in progress Acquisition of property, plant & equipment Acquisition of intangibles Net Cash Flow from Investing Activities
Cash Flows from Financing Activities
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
13
NOTES TO THE FORECAST FINANCIAL STATEMENTS For the year ending 30 June 2022
Reporting Entity
Basis of Preparation
City Rail Link Limited (‘CRL Ltd’ or the ‘Company’) is
These prospective financial statements have been
a Crown Entity, registered under schedule 4A of the
prepared for the purpose of providing information on
Public Finance Act, and is domiciled in New Zealand.
CRL Ltd’s future operating intentions and financial
The Company was incorporated on 13th April 2017.
position, against which it must report and be formally
CRLL is jointly owned by the Crown, and Auckland
audited at the end of the financial year.
Council.
These prospective financial statements have been
The Company’s purpose is to govern and manage the
prepared:
delivery of the Project.
• In accordance with the Crown Entities Act 2004,
City Rail Link Limited commenced operations with
which include the requirement to comply with New
effect from 1 July 2017.
Zealand generally accepted accounting practice (NZGAAP) and the Companies Act 1993 • In accordance with PBE FRS42 and NZGAAP as it relates to prospective financial statements • The Company reports under Tier 1 Public Benefit Entity (PBE) standards and as such the prospective financial statements have been prepared on that basis • In New Zealand ‘000 Dollars ($), which is the Company’s functional currency, unless separately identified • The information in these financial statements may not be suitable for another purpose.
Statement of Significant Underlying Assumptions Funding from
Funding from the Sponsors is based on the expenditure programme for the Project,
the Sponsors
assuming sufficient funding is available for the Project. Funding requirement is assessed monthly and the funding application to the Sponsors and approval by the Sponsors is completed before the beginning of every quarter. For successful funding applications, the majority of funds are received at the beginning of the new quarter.
Personnel costs
Forecast costs assume the current organisational structure will be in place throughout the period. A proportion of personnel cost which is directly attributable to the Project is capitalised and recognised as Capital Work in Progress in the Statement of Forecast Financial Position.
Capital
CRL Ltd is undertaking a programme of capital spending aimed at delivering the CRL project. Projected costs and timing of expenditure are based on plans and quotations that were current when these forecasts were prepared.
Opening equity
Estimated opening equity assumes 2020/21 net deficit of $253.7 million. This impacts on estimated amounts of cash in hand and net assets.
14
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
NOTES TO THE FORECAST FINANCIAL STATEMENTS For the year ending 30 June 2022
Significant Accounting Policies
Foreign Currency Transactions
The financial statements contained in this document
Foreign currency transactions are translated into NZ$
are prospective and, by their nature, contain
(the functional currency) using the spot exchange
assumptions which may lead to material differences
rates at the date of the transactions. Foreign exchange
between the prospective financial statements and the
gains and losses resulting from the settlement of
actual financial results prepared in future reporting
such transactions and from the translation at year-
periods. CRL Ltd has undertaken a review of its
end exchange rates of monetary assets and liabilities
financial models, and believes they remain fit for
denominated in foreign currency are recognised in the
purpose in assisting CRL Ltd in preparing prospective
surplus or deficit.
financial statements. The prospective statements for CRL Ltd is subject to significant management
Goods and Service Tax
judgement relating to the timing and quantum of the
Items in the financial statements are presented
investments, and the prospective information reflects
exclusive of GST, except for receivables and payables,
the best information available to management.
which are presented on a GST inclusive basis. Where
Project Funding
GST is not recoverable as input tax, it is recognised as
Project costs, which are capital in nature, create an asset for CRL Ltd as well as operating costs for its day to day running and management and are funded by a share issue to the Crown and Auckland Council. This funding is not recognised as revenue in the forecast financial statements.
part of the related asset or expense.
Income Tax CRL Ltd is a Public Authority in accordance with the Income Tax Act 2007 and consequently is exempt from the payment of income tax. Accordingly, no provision has been made for income tax.
Rental Revenue Other revenue generated by CRL Ltd is from rental
Property, Plant & Equipment
income from properties required to enable the build
Property, plant and equipment consists of land,
but not yet decommissioned and will be recorded as
building, subterranean land, furniture and fittings,
revenue.
computer hardware, software and office equipment.
Interest Income
Recognition and measurement
Interest revenue is calculated on a proportion basis
Property, plant and equipment is measured initially
for the surplus cash balances throughout the forecast.
at cost. Cost includes expenditure that is directly
General Expenses
attributable to the acquisition of the items. The
General expenses includes costs such as operating leases, rates, directors fees, telecommunications and other office operating costs.
cost of an item of property plant and equipment is recognised only when it is probable that future economic benefit or service potential associated with the item will flow to CRL Ltd, and if the item’s cost can be measured reliably. The majority of capital expenditure will remain as ‘Capital Work in Progress’ for the duration of the Project. Work in progress is recognised at cost less impairment and is not depreciated.
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
15
NOTES TO THE FORECAST FINANCIAL STATEMENTS For the year ending 30 June 2022
Depreciation
Estimates and assumptions are continually evaluated
Land, Buildings and Subterranean Land are held for
and are based on expectations of future events
the development of rail tunnels and stations and are
that are believed to be reasonable under the
not depreciated. All other assets are depreciated on
circumstances.
a straight- line basis over the useful life of the asset.
The estimates and assumptions that have significant
Depreciation is charged at rates calculated to allocate
risk of causing material adjustment to the carrying
the cost or valuation of the asset less any estimated
amount of the assets and liabilities within the forecast
residual value over its remaining useful life:
financial statements are as follows:
The estimated useful lives of property, plant and
• Third Party Works: CRL Ltd fund work undertaken
equipment are as follows:
by KiwiRail Holdings Ltd on the KiwiRail Holdings
Land and buildings Temporary Not depreciated
Ltd network. As part of the overall project CRL
Buildings - other
4 years
Subterranean land
Not depreciated
Furniture and fittings
5 years
Office equipment
5 years
Computer hardware
5 years
The assets’ residual values, useful lives and amortisation methods are reviewed, and adjusted if
Ltd undertakes or funds construction work across the wider Auckland rail network. The nature of the work completed, and the ownership of the assets constructed, means they do not form part of the CRL Ltd assets, in accordance with NZ GAAP. • Asset Transfers: as CRL Ltd completes certain contracts it may transfer separable assets relating to
appropriate, at each financial year end.
enabling works (including assets related to a number
Derecognition
their subsidiaries as those assets are commissioned
of utility services) for the CRL to the Sponsors or
An item of property, plant and equipment is
for use. However, the ownership of the majority
derecognised upon disposal or when no further future
of CRL Ltd’s key assets will stay with CRL Ltd until
economic benefits or service potential are expected
the completion of the Project. Therefore, they
from its use or disposal.
will remain as CRL Ltd work in progress until that
Gains and losses on disposals are determined by
time. Per PBE IPSAS 37 Joint Arrangements, CRL
comparing proceeds with the carrying amount. These
Ltd continues to be classified as a joint venture
are included in surplus or deficit.
(as opposed to joint operation) by the Sponsors as
Share Capital and Equity
be determined. Any separable assets transferred
All B class shares issued are fully paid and have a face value of $1 each. The Shareholder’s investment in CRL Ltd is made up of 2,058,280 shares as of 1 July 2021 and is expected to be 3,038,280 shares as of 30 June 2022.
Critical Accounting Estimates and Assumptions In preparing these prospective financial statements, CRL Ltd has made estimates and assumptions concerning the future. These estimates and assumptions may differ from the subsequent actual results.
16
the ultimate ownership of the CRL assets is yet to prior to project completion will transfer without compensation and hence will be treated as a vested asset in the period in which the asset transfer occurs. CRL Ltd will recognise a vested asset expense on transfer of the asset. • COVID-19: the cost impact of COVID-19 is yet to be determined across CRL Ltd’s construction contracts, but the expectation is that such costs will be able to be accommodated within the existing project budget. The impact (if any) to the target project completion date is yet to be fully quantified. • The Business Hardship Programme was launched in December 2019. The programme was set up to
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
NOTES TO THE FORECAST FINANCIAL STATEMENTS For the year ending 30 June 2022
provide assistance in the form of rental payment contributions to small retail businesses that have been directly impacted by the delay to completion of the C2 contract works within the Albert Street Impact zone between Victoria and Customs Street intersections.
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022
17
Appendix: Directory Shareholders The Minister of Finance The Minister of Transport Auckland Council
Board Sir Brian Roche (Chairman) Russell Black Brian Harrison Karen Jordan Anne Urlwin
Senior Management Sean Sweeney (Chief Executive) Caroline Beaumont Patrick Brockie Steve Brunell Elgan Davies Sumi Eratne Gerry Goodwin Victoria Jessop Rob Mair Kirsten Mayne Russell McMullan Sandip Ranchhod
Bankers Bank of New Zealand ANZ Bank New Zealand Limited
Auditor Audit New Zealand on behalf of the Auditor-General
Registered Office Level 2, 25 Teed Street Newmarket Auckland 1149 Email: info@cityraillink.govt.nz Web: www.cityraillink.co.nz Phone: 0800 275 8255
18
CITY RAIL LINK LIMITED | Statement of Performance Expectations 2021-2022