Notification of upcoming utility work in K Rd area October 2018

Page 1

1 OCTOBER 2018

CityRailLink

NOTIFICATION OF UPCOMING UTILITY WORK IN YOUR AREA

Dear neighbour, City Rail Link (CRL) would like to advise you of upcoming utility works planned in your area. These works are required to take place ahead of the construction of CRL’s Karangahape Station which is expected to begin in the second half of next year. The utility works will be undertaken by two contractors in two phases; 1)

Investigation Work I. Manhole investigation Beresford Sq, Pitt St, Karangahape Rd, Mercury Ln Tuesday 2nd - Friday 6th October, 7am – 5pm

II. Trench investigation Beresford Sq (one location only) Expected to begin mid-late October and be completed over one weekend

2)

Main Diversion Work I. Trench work Mercury Ln and Cross St Expected to begin in January 2019 and completed in stages over 6 months

II. Trench work Beresford Sq and Pitt St Expected to begin in January – April 2019 and completed in stages over 6 months

Once we have contractors on board and have confirmed methodology and timing, we will be back in touch to provide more information. We understand construction can be disruptive and we would like to work with you to ensure this disruption is kept to a minimum. Thank you in advance for your understanding. For any further enquiries, please contact City Rail Link: Contact: Phone: Email:

Holly Claeys, Stakeholder and Street Response Manager 021 832 616 Holly.Claeys@CityRailLink.govt.nz

Did you know When the CRL is up and running, up to 54,000 passengers will be able to travel through the city in peak. That’s equivalent of 16 lanes of traffic or three of Auckland’s Harbour Bridge. To find out more about the City Rail Link project, please visit www.CityRailLink.govt.nz

Follow the progress

CityRailLink.co.nz

CityRailLink


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Notification of upcoming utility work in K Rd area October 2018 by City Rail Link Ltd - Issuu