
5 minute read
C13 6 Porters Ave + 3 Ngahuru St (Eden North Apartments) SSCNVMP
C13 6 Porters Ave + 3 Ngahuru St (Eden North Apartments) SSCNVMP
C13.1 Introduction
This Site Specific Construction Noise and Vibration Management Plan (SSCNVMP) is for the residential building located at 6 Porters Ave. A SSCNVMP is required because construction is predicted to exceed the standards in CRL designation conditions 31 and 33. This SSCNVMP has been prepared in accordance with CRL designation condition 37 and 38 and is Appendix C13 of the Mt Eden Main Works Construction Noise and Vibration Delivery Work Plan (CNV DWP). It is a supplementary document that builds on the CNV DWP, and therefore directly references relevant sections of the CNV DWP to avoid repetition. The objective of this SSCNVMP is to detail the best practicable option(s) (BPO) to avoid, remedy or mitigate the identified adverse effects from noise and vibration exceedances at 6 Porters Ave.
This SSCNVMP has been prepared for the Link Alliance and forms part of the Construction Environmental Management Plan (CEMP) for the Mt Eden Station Main Works. It builds on the SSCNVMP previously prepared and implemented for the Mt Eden Enabling Works.
C13.2 Engagement
Mt Eden Enabling Works (for information)
Link Alliance representatives Sonya Leahy, Hilary Konigkramer, Aidan Kirby-McLeod, Phil Young and Craig Fitzgerald (Marshall Day Acoustics) met with building representative Diane Gribben (Body Corporate Chair of North Eden Apartments) and Daniel (Building manager) on 18 September 2019. The matters discussed included:
An overview of the project
General programme, demolition, blasting, rock breaking and utilities relocation activities
Overview of the CNV DWP and this SSCNVMP, communications triggers and protocol and for monitoring and pre-construction building condition surveys The modern multi-level terraced apartment building features basement car parking beneath 48 apartments across two buildings, some with balconies on the south side overlooking the rail corridor and worksite. There are approximately 2-3 families with young children. Rock breaking activities are required in close proximity to this building for short periods. Figures B.7 and B.8 in Appendix B of the Mt Eden Enabling Works CNV DWP predict rock breaking noise levels of up to 75 –80 dB L Aeq on the south façade and 80 –90 dB L Aeq on the west façade. While this significantly exceeds the 75 dB L Aeq noise limit on the west façade, levels will reduce rapidly as works migrate away. Other utilities works will generally be compliant. Activity specific mitigation and management measures are included in Section 9 of the CNV DWP and not repeated here (e.g. Section 9.7 concrete and rock breaking). The modern concrete building has well sealed openable glazing. The estimated sound level difference across the façade with the windows and doors closed is 25 –30 decibels. The predicted construction noise effects from Table 12.1 in Section 12.1 are predicted to result in short-term noise disturbance. Physical receiver mitigation, such as temporary relocation of affected receivers, alternative ventilation and façade sound insulation improvements, have been considered, but are not required as part of the BPO for the C3 enabling works.
Page 46 Mt Eden Main Works CNV DWP –Appendix C SSCNVMPs
Preliminary excavator mounted rock breaker vibration level predictions (Section 6.2 of the Enabling Works CNV DWP) identify that there is potential to exceed the commercial cosmetic building damage thresholds. Cosmetic building damage effects are deemed ‘minor damage’ in the DIN Standard (Section 5.2), such as cracking in paint or plasterwork, and can generally be easily repaired. A pre construction building condition survey in accordance with CRL designation condition 46 will ensure any damage is identified for remediation. Ms Gribben agreed that prior communication of timeframes for works with the potential to exceed the relevant noise limits was an acceptable means of managing effects. No further activity specific consultation is necessary over and above regular communication (Section 10).
Mt Eden Main Works
Link Alliance representatives XXX met with building representative XXX on XXX date. The matters discussed included:
An overview of the next project phases
General programme, rock removal, excavation, piling, and utilities relocation activities
General review of CNV DWP and this SSCNVMP, communications triggers and monitoring CNV DWP Section 7 identifies summarise the potential scale of noise and/or vibration exceedances using the modelling outputs in insert hyperlink to the GIS maps here. The relevant stages are summarised below. Activity specific mitigation and management measures are included in Section 9 of the CNV DWP, and referenced in brackets, rather than repeated.
Noise
Retaining walls (refer piling in Section 9.8)
Excavation (refer concrete and rock breaking in Section 9.7) Utilities and drainage (refer concrete cutting and breaking in Sections 9.6 and 9.7)
Fenton and Porters Ave (refer rock breaking and piling in Sections 9.7 and 9.8)
Night Works (refer cranage night works in Section 9.2) The predicted construction noise effects from Table 12.1 in Section 12.1 are predicted to result in XXX noise effects. Physical receiver mitigation, such as temporary relocation of affected receivers, alternative ventilation and façade sound insulation improvements, have been considered, but are not required as part of the BPO for the Mt Eden Station Main Works.
Vibration
Excavation and piling (refer breaking, piling and compaction in Sections 9.7, 9.8 and 9.10) Fenton Bridge (refer rock breaking in Section 9.7)
Porters Bridge (refer rock breaking in Section 9.7)
Utilities and drainage (refer breaking, piling and compaction in Sections 9.7, 9.8 and 9.10) The above activities are predicted to have the potential to exceed the commercial cosmetic building damage thresholds. Cosmetic building damage effects are deemed ‘minor damage’ in the DIN Standard (Section 5.2), such as cracking in paint or plasterwork, and can generally
Page 47 Mt Eden Main Works CNV DWP –Appendix C SSCNVMPs
be easily repaired. A pre construction building condition survey in accordance with CRL designation condition 46 will ensure any damage is identified for remediation. XXX agreed that prior communication of timeframes for works with the potential to exceed the relevant noise and vibration limits was an acceptable means of managing effects. No further activity specific consultation is necessary over and above regular communication (Section 10).
C13.3 Review Process
If Ms Gribben or affected site representatives request consultation in the future, this SSCNVMP will be updated in accordance with CRL designation conditions 37.5 and 38.5, with consideration given to the following:
The extent to which noise may exceed the designation standards
The timing and duration of any exceedance
The type of activity causing any exceedance
A summary of the communication and consultation with the receiver
The methods and measures to mitigate effects
A statement of why they reflect best practicable option Communications records are contained in the communication and consultation plan (CCP). This SSCNVMP will be updated to summarise engagement and any agreed site-specific measures.
Page 48 Mt Eden Main Works CNV DWP –Appendix C SSCNVMPs