City Rail Link – C1-C2 Community Liaison Group Meeting MINUTES AND ACTION POINTS Rā: Wā: Wāhi:
27 May 2020 5pm – 6:30pm Online, via Microsoft Teams CRL CRL staff & contractors
ATTENDEES CLG Members
Maria HernandezCurry (MHC)
Stakeholder Communications Manager – CRL Ltd
Lucas Nikkel (LN)
C2 Project Manager – CRL Ltd
Nicole Lawton (NL)
Communications Coordinator – CRL Ltd
C Williamson
Andrew Swan (AS)
C1 Construction Manager – CRL Ltd
J Mantell
Jhon Aragon (JA)
C1 Delivery Manager – CRL Ltd
Brandy Smith (BS)
Downer Stakeholder Engagement Manager
P McLuckie T Loveridge – Heart of the City V Morrison-Shaw N Quigley J Smith N Playle
R Beckett – Auckland Transport Terry Sugrue – Auckland Transport
ITEM
UPDATE/ACTIONS
1
Welcome and introductions
• MHC welcomed everyone and thanked them for their patience and cooperation in attending the meeting via online format. She then introduced the meeting agenda. • CLG members, CRL and Auckland Transport staff in attendance introduced themselves.
2
C1 Britomart/Lower Queen Street update – Andrew Swan and Jhon Aragon
• Covid-19 distancing and health and safety measures have been put in place on the C1 construction site in accordance with government requirements. These Covid-19 restrictions mean that C1 construction is not working at 100 per cent capacity and productivity is reduced. This, grouped with the effects of Alert Level 4 lockdown, means C1 is expecting some “programme slippage” – although we are still assessing what this means in the long run and continue investigating opportunities to make up time. • Britomart Station was due to be reopened by Christmas 2020, however this is likely to now be delayed. • The tunnels underneath the Chief Post Office (CPO) building and Lower Queen Street have been constructed, and within the CPO, the ground floor is currently being reinstated. • Working on mechanical electrical and plumbing requirements for the CPO’s basement area are underway. • Reinstatement work will start soon on the ground floor of the CPO. • New metro grade escalators have already been installed with two more to be installed in June.
Page | 1
CRLL – CLG