Aotea Utility Works Stages 1-3 CLG meeting 05 August 2019


What’s happening first in Albert Street?

• Utility investigations and diversions starting at

Wyndham St end of Albert St – completed in stages from September 2019 until mid 2020

• Seven canopy removals (various locations along Albert St and cnrs of Victoria & Wellesley) – December 2019 to Q2 2020

• Site establishment at Bledisloe carpark – Q4 2019 • Piling and D-wall construction for Aotea Station ground support – starts April 2020

2


Developing management plans for stages 1 to 3 of Aotea utility relocation works • A suite of management plans are required by

the CRL designation and the regional resource consent to manage the effects of construction.

• The management plans are developed by

subject matter experts, covering such areas as:

• Traffic, access and parking • Noise and vibration • Social impact and business disruption • Air quality • Contamination

• The subject matter experts who have drafted the plans are available so that you can provide your feedback directly and ask any questions. • The plans will then be finalised before undergoing an independent peer review and lodgement with Auckland Council. • We’re hoping to gain council approval prior to the end of September to enable us to start utility relocation works.

• Ecology, Trees and vegetation • Archaeology • Ground water and settlement

3


Subject Matter Experts (SMEs) here this evening •

Jarrod Snowsill, Principal Planner

•

Mark Anderson, Utilities Manager

•

Kim Hardy, Social Impact & Business Disruption Specialist

•

Andrew Curtis, Air Quality

•

Caroline Secretin, Environmental Management and Erosion and Sediment Control

•

Joe Grimes, Acoustics and Vibration

•

Matthew Brown, Environmental Contamination

•

Angela Chaffe, Ecology

•

Werner Pretorius, Transportation

•

Sarah Macready, Archaeology

•

George Brink, Groundwater and Settlement

•

Rachel Blundell, Communications & Engagement Manager

4


Utility diversion works – Stage 1

Sept 2019 – Oct 2019

5


Utility diversion works – Stage 2

Oct – Dec 2019

6


Utility diversion works – Stage 3

Jan 2020 – Mar 2020