Aotea Station CLG meeting 28 May 2020 4pm-5pm


Agenda & welcome from our Community Manager - Shaun Sutton


• Welcome to our virtual CLG • Construction update • Development response update • Planning and consents update

• Environmental update • Questions and feedback Artist impression of main station entrance on Wellesley Street West


• Return to site following Alert Level 4 Lockdown

4


February 2020

March 2020

April 2020

May 2020

5


• New normal working hours for the Link Alliance

• Catch-up opportunities following lockdown • Business forum update • Remember, we’re available to our neighbours anytime Contact the Aotea Station team:

aotea@linkalliance.co.nz OR

Link Alliance normal working hours: Monday to Friday, 7am-10pm Saturday, 7am-7pm Work outside of these hours is possible, but noise limits are much lower

0800 CRL TALK and select option 3 6


• Ongoing call for artwork for Aotea Station

• Tunnel boring machine name selected!

7


Construction Update Station Manager - Matt Sinclair


Key Milestones Achieved

Utility diversions from Victoria St to Wyndham St to enable Piling start.


Key Milestones Achieved • Utilities trench and installation from Victoria St to Wellesley St are 50% complete • Utility installation across Victoria St are complete • Fire Service access trials

10


Key Milestones Achieved

• Utilities cleared from Wellesley St to start Station Wall construction – Diaphragm wall • Gas Diversion complete to Crowne Plaza

11


Key Milestones Achieved

Bentonite Silo & Plant Setup

Ablutions Block Team Briefing Area First Aid Room Kitchen Facility

Building Perimeter Walls – Below Ground

12


Upcoming Milestones • Diaphragm Wall Rig used to construction perimeter station wall Arrives at Aotea mid June.

13


Upcoming Milestones

• Piling Rig arriving this week to Kingston St

14


Covid 19 Lockdown Site shut down commenced 23rd March Site re-establishment 28th April under Level 3 Working in team bubbles; temperature checks; daily staff tracking and health questionnaire.

15


Station Overview

16


Station Overview - Traffic Sequence Slip Lane closed for Utility Diversions

Utility Diversions

Indicative Major Traffic Sequence

Station Wall & Roof Construction

Wellesley St

Utility Diversions

Victoria St

Piling & Roof Construction

May 2020 – Sept / Oct 2020 17


Station Overview - Traffic Sequence Removal of Bluestone Wall

Piling & Roof Construction

Entrance Building Construction

Station Wall Construction

Station Roof Construction

Indicative Major Traffic Sequence

Wellesley St

Victoria St

Commence Station Excavation

Sept / Oct 2020 – Mid 2021 18


Station Overview - Traffic Sequence

Entrance Building Construction

Roof Construction Station Excavation

Station Excavation

Indicative Major Traffic Sequence

Station Below Ground Construction

Wellesley St

Victoria St

Station Wall & Roof Construction

TBM Arrival Tunnel 1

Mid 2021 – Early 2022 19


Station Overview - Traffic Sequence

Entrance Building Construction

Victoria St Entrance Buildings

TBM Arrival Tunnel 2

Station Excavation Station Excavation Station Below Ground Construction

Indicative Major Traffic Sequence

Wellesley St

Victoria St

Station Below Ground Construction

Early 2022 – Late 2022 20


Station Overview - Traffic Sequence Street Scape / Urban Design

Station Mechanical / Electrical & System Installations

Indicative Major Traffic Sequence

Wellesley St

Victoria St

Architectural Finishes

Late 2022 – 2024 21


Top Down Construction Method & Sequence

Station Wall & Roof Construction

Station Excavation & Concourse (mid) slab construction 22


Top Down Construction Method & Sequence

Station Wall & Roof Construction Station Excavation & Concourse (mid) slab construction

23


Top Down Construction Method & Sequence

Roof Construction Excavation to Base of Station & Base Slab Construction

24


Top Down Construction Method & Sequence

Concourse Construction Base Slab Construction & Internal Structure

25


Top Down Construction Method & Sequence

Concourse Construction

Base Slab Construction & Internal Structure

26


Top Down Construction Method & Sequence

Internal Architectural Finishes / Mechanical & Electrical Installations

27


Development Response Development Response Manager - Holly Claeys


Development Response

Identify Development Response is the coordinated planning and implementation of tools to mitigate the impacts of large scale development and cumulative impact of construction activity on people.

Manage

Mitigate

29


Making things more convenient for you • • • •

Onsite staff helping pedestrians Boot cleaning brushes Bridges over trench to ensure access to local business Ramps to ensure everyone is able to use the footpath

30


Local Business signage Implementation examples • Blocking existing signage • Changing road layout • Cutting back canopies

31


Hoardings • Local artists • Innovative ideas • Window into the work site • Giving space back

• Schools campaign • Wayfinding • Businesses Open

32


Activation space • Space no longer used

• Give back to the community • Colourful • Greenery/life • Drop in Centre • Space where community can have lunch and learn more about the project

33


Planning and consents Senior Planner - Alisdair Simpson


Consenting and approvals - Update Aotea Main Works

What was approved as part of the Outline Plan:

• Outline Plan approval issued on Friday 8 May

Construction Environmental Management Plan

• Allows for Aotea Station construction works to commence

Communication and Consultation Plan

Transport, Access and Parking DWP

• The approved Management Plans provide an environmental frameworks for the construction of Aotea Station

Construction Noise and Vibration DWP

Social Impact and Business Disruption DWP

• Approved Management Plans prepared to address CRL conditions

Trees and Vegetation DWP

Historic Character DWP

Air Quality DWP

Contamination DWP

• All approved management plans will be provided on the CRL website

35


Consenting and approvals - Review, monitoring and update • All management plans will be subject to an annual review • Aim is to ensure the plans are ‘fit for purpose’ and support the construction activates as required • Management plans will be updated if required during the construction works • Monitoring of construction works will identify any areas that are inconsistent with the approved management plans

36


Environmental Update Environmental Advisor - Maria Aguiar


Environmental Monitoring Update Attended/on-site monitoring and inspections: • Noise & Vibration • Dust • ESCP and discharge water quality • Contamination • Archaeology & Heritage • Trees – inventory and protection of retained trees

Unattended/automatic monitoring: • Noise & Vibration • Dust • Groundwater (boreholes) and settlement (prisms) 38


39


Environmental Monitoring Update

40


Questions & Answers Contact the Aotea Station team anytime on aotea@linkalliance.co.nz OR 0800 CRL TALK and select option 3