2 minute read

2. Aotea Main Works

2.1 Overview of Works

The Aotea main works will involve three main phases of work. Each phase of work involves multiple construction activities which will be undertaken throughout the Aotea project site. The phases associated with the Aotea main works involve:

Foundation works to form the perimeter walls of the station box and underground running tunnels. This involves diaphragm wall construction, roof construction, piling and jet grouting; Construction of the Aotea Station platforms, Wellesley Street entrance structure, concourse, Victoria Street entrance structures and Kingston Street Plenum, and; Structural fitout of the Aotea Station including MEFH installation, and internal and architectural finishings.

The works require the operation of a Construction Support Area (CSA) within the Bledisloe House car park site and a portion of Mayoral Drive. Equipment used to undertake these works will be

predominantly situated in the CSA. Upon completion of the Aotea main works, the area will be repurposed in preparation for public realm reinstatement works 2 .

The methodology for the construction of the Aotea Station is predominantly based on a ‘top down’ and ‘bottom up’ approach. The ‘top down’ approach relates to the southern end of Albert Street (south of Durham Street) and involves the installation of the ‘roof structure’ early on, which enables a limited number of traffic lanes to operate concurrently with the construction of the station, which occurs beneath. This approach reduces the construction effects on traffic flow within the city centre. The tunnel alignment on the northern end of Albert Street (north of Durham Street) will be constructed using a ‘bottom up’ methodology.

A detailed description of the Aotea main works is included in the CEMP and includes;

an overview of the works including indicative timeframes in Table 2-1. the construction sequencing including equipment and earthworks volumes for the works in Table 2-2. further detail of the CSA in Section 2.6.2 of the CEMP. Drawings indicating the staging of the construction activities and proposed layout of the CSA is provided as Appendix B.

It is noted that public realm reinstatement works and details of architectural finishing’s for the Aotea Station (Condition 47 –54 of Designation 2500-1), will form part of separate Outline Plan packages to be prepared in the future prior to the commencement of the respective works 2 .

2.2 Programme

The Aotea main works are anticipated to take approximately 45 months to complete, occurring from April 2020 to December 2023 (approximately) as detailed in Table 2-1 in Section 2.2 of the CEMP. Some construction activities outlined in each phase of the Aotea main works will occur in parallel.

2.3 Construction Methodology

The Aotea main works will be divided into stages as described in the CEMP.

Page 12

Aotea Station Main Works

This article is from: