Contracts 1 and 2 – CPO Building/Lower Queen Street and Albert Street Works - Construction Update Community Liaison Group Meeting Tuesday, 25 September 2018


Agenda 1

Introduction – Sonya Leahy

2

Construction Update

3

•

Contract 1, CPO Building and Lower Queen Street – Nick Adams

•

Contract 2, Albert Street – Lucas Nikkel

Sustainability Annual Review

• 4

5

Contracts 1 and 2 – Ghida Sinawi and Nick Braxton

Albert Street Public Realm (Streetscape) Reinstatement •

Overview of reinstatement design – John Fellows

•

Programme and sequencing of reinstatement works – Lucas Nikkel

•

Auckland Council approvals – Richard Jenkins

Improving the Community Liaison Group process – Sonya Leahy

2


Contract 1 – Britomart and Lower Queen Street Construction Update

Nick Adams 25 September 2018


Secant Piling and Capping Beams Installation of secant piles on northern side of Lower Queen St

Installation of struts between the capping beams. Struts support the secant piles as the excavation progresses deeper

Excavation on the capping beam exposing the secant piles take from southern end of Lower Queen St

4


Underpinning and load transfer - Chief Post Office (CPO) Plan view showing layout of the unpinning frames ground floor CPO

Installed underpinning frames on the northern side of CPO. Views looking west to LQS

Red structural steel

Grey – Post tensioned reinforced concrete

5


Underpinning in the CPO • Underpinning frames with a collar around each • Photo of restricted working area within the CPO building

• 12m long, 12 ton beams into position

column.

• Hydraulic flatjacks installed beneath each corner of each collar. When pressurised the jacks lift the collar and therefore the column – ‘ Load transfer’

6


Underpinning and Load Transfer Complexity of the reinforcing steel in the concrete underpinning beams

7


Underpinning and Load Transfer of the Completed concrete underpinning beam with steel collars on top

8


Excavation in Contract 1 Excavation within the CPO beneath the underpinning frames

Original foundation piles exposed during excavation

9


Excavation in the Chief Post Office (CPO) CPO is being held by the underpinning frames The pile cap and piles will be demolished

Daylight beneath the building looking west towards Lower Queen Street

10


Excavation on Lower Queen Street Remaining parts of the pedestrian underpass

Progress of excavation on Lower Queen Street

11


Completion Timeline • Complete excavation: early 2019; • Construct rail tunnels: late 2018 to mid-2019; • Reinstate CPO building: mid-2019 to late-2020;

• Remove plaza temporary accommodation: mid to late 2020 • Urban realm: mid-2019 to late 2020

12


Contract 2 – Albert Street

Recent Milestones

Lucas Nikkel 25 September 2018


Completed tunnel box • Looking south through the completed tunnel box sections. • Temporary cut off wall (removed as part of C3) visible at end of tunnel box.

14


Excavation progress • Photo showing general progress of excavation, waterproofing and tunnel box activities.

• Image taken from outside Quay West looking south

15


Underneath Customs St

16


Backfilling • Backfilling commencing at the very southern end of the tunnel box.

17


Removal of struts

• Struts are being removed before the backfill begins.

18


Sustainability Annual Review

Update

Nick Braxton 25 September 2018


Why Sustainability

.

One of CRL’s primary objectives, acknowledged in CRLL’s Statement of Intent, is to “Provide a sustainable transport solution that minimises environmental impact”.

20


2017/18 Review Overview

1. Targets 2. Activities

3. Results 4. Successes 5. Challenges

21


Targets

A quadruple bottom line sustainability approach is being taken that encompasses environmental, social, cultural and economic objectives and outcomes across the whole lifecycle of the project 22


Activities: Contract 1&2 • Contract 1 & 2 progressing ISCA “As Built” rating

• Resource use and waste tracked • Driver training programme implemented • Grid switching implemented • Monitoring/audits: waste, energy, site, management, stakeholders • Knowledge shared

23


Results: Driver training • All bulk excavation drivers trained • 5.6% reduction: 5,300L and 15 tCO2e • Sub-contractor implementing it on wider fleet

24


Results: Grid switching •

3 transformers installed

•

198,000 litres saved

•

450 tCO2e GHG not emitted

25


Results: Construction optioneering

26


Materials and Waste

27


Results: Tracking against targets

28


Successes • Sustainability embedded across the project

• Energy and materials use tracking well

• Multiple initiatives: Transformers, recycling, driver training, innovations…

• Cost savings

29


Achievements:

Deloitte Energy Efficiency Award

Finalist at the Sustainable Business Network Awards

30


Challenges •

Continuing performance for materials and energy

•

Reducing water use

•

Replicating on remainder of CRL

31


Feedback / questions?

32


Albert Street Public Realm (Streetscape) Reinstatement Update

John Fellows, Lucas Nikkel, Richard Jenkins 25 September 2018


Albert Street Reinstatement CRL works

Contract 2 Works

Contract 3 Works

34


35


36


Auckland Council Approvals – Outline Plan • Outline Plan for the reinstatement works is submitted to Council (required by CRL designation conditions) • Outline Plan identifies the reinstatement works and how construction effects will be managed • Council can request changes to the Outline Plan Outline Plan

Construction Environmental Management Plan (CEMP)

Transport, Access and Parking

Construction Noise and Vibration

Social Impact and Business Disruption

Historic Character

Delivery Work Plans (DWPs)

Urban Design

Communication and Consultation Plan

Trees and Vegetation

Contamination

Air Quality

Public Art

SSCNVMPs

37


Auckland Council Approvals – Management Plans • Management Plans for the reinstatement works are submitted to Council (required by CRL resource consent conditions) • Management Plans identify how particular construction effects will be managed • Council certifies the Management Plans

38


Reviewing the effectiveness of the Community Liaison Group

Sonya Leahy 25 September 2018


Why a review? To ensure:

• CLGs are effective as they can be

• Both CRL and its CLG members are getting the most out of the meetings.

• CLG membership is reflective of the surrounding community

• CLG members can review and input into plans easily and effectively, as required under CRL’s consent conditions.

40


What do we want to review? • Is membership reflective of the community?

• Options for wider representation and improved attendance

• Are meetings meaningful for members?

• Member’s thoughts • Can CLGs be utilised more? • Options to improve the documentation review process

• Frequency of the meetings

41


What ideas do we have? • Establish Terms of Reference • Review membership

• Tailor CLG meeting content • Explore better ways of providing information and receiving feedback on project plans

• Meet more often • Make CLG members more visible to others in the community

• Creating visible online access to CLG presentations and minutes.

42


What next? • Develop a new CLG strategy • Canvas members to understand what does and doesn’t work for them

• Invite a Local Board representative to meetings

• Discuss all the proposed changes with members

43


Any Questions?