C1-C2 CLG minutes - ACTION POINTS / MINUTES Date: Time: Venue:
19 June 2018 5:30pm – 6pm AMP – Level 17, Mairangi Room
Attendees CLG: Paul Mcluckie Ross Baxter David Brown Kathy Ross Chris – Stamford Residences
Page | 1
Roger – Prince Albert Apartments Lauren – Precinct Lexie – Precinct Richard Hansen – Aotea Gifts Donald Hansen Julian – Aotea Gifts
CRL Carol Greensmith Aidan Kirkby-McLeod Makere Carroll
Connectus Alan Howard-Smith Stan Schwalger
AECOM Craig Hind Ngan Truong Matthew Kerr-Ridge
Item
Topic
1
Welcome
1.1
Carol opened the meeting and everyone introduced themselves
2
C2 Public Realm Reinstatement Addendums: Transport, Access and Parking Delivery Work Plan – Lower Albert St
2.1
Matthew presented an overview of C2 Public Realm Reinstatement
2.2
Ngan presented on the Transport, Access and Parking Delivery Work Plan
2.3
Richard asked if there was a fourth stage to the traffic layout staging on Lower Albert Street according to the DWP - Ngan answered that there wasn’t
2.4
Richard asked when the traffic would switch - Ngan answered that it would be by late 2019 until early 2020 at this stage - Richard asked if there was currently a solid date for the switch as they needed to let their tourist companies in Japan know so that they could alter their travel route past Aotea Gifts