Aotea CLG presentation 19 February 2020

Page 1

Aotea Station CLG meeting 19 November 2019


Agenda • Introductions • Construction update - early works • Albert Street service lane • Station main works • Delivery Work Plans and management plans • Subject matter experts • Round table discussion: Main station works Delivery Work Plans

2


Introductions – who is in the room?

3


Construction update – early works

4


Looking ahead – December and January

5


Albert Street service lane

• What do we need to do? • Challenges • Solutions

6


Remove parking along service lane

Allow for turning room at the far end of the lane

Southern end of Service Lane closed to install new services

7


Station main works

8


Station Victoria Street West entrances

9


Station concourse level

10


Station overview

m 380

g– lon

12

ide w 8m 1 o t

eep d 8m –1

11


Main Works Programme 1

12


Main Works Programme 2

13


Main Works Programme 3

14


Main Works Programme 4

15


Main Works Programme 5

16


Main Works Programme 6

17


Construction staging

18


Key construction interface – bluestone wall and Auckland District Court

19


Key construction interface – bluestone wall and Auckland District Court

20


Key construction interface – bluestone wall and Auckland District Court

21


Key construction interface – bluestone wall and Auckland District Court

22


Delivery Work Plans and Management Plans • • • • •

CRL Designation Conditions

A2N Regional Consent Conditions

Transport, Access and Parking Construction Noise and Vibration Social Impact and Business Disruption Historic Character Trees and Vegetation

• • • •

Construction Environmental Management Plan Communication and Consultation Plan Air Quality Contamination

• • •

Erosion and Sediment Control Plan Flocculent Treatment Management Plan Groundwater and Settlement Contingency Plan Industrial Trade Activity Management Plan

•

23


Who approves the plans and how?

Construction Environment Management Plan

• • • • DRAFT

• • • • • • •

Communication and Consultation Plan Noise and Vibration Transport, Access and Parking Social Impact and Business Disruption Historic Character Air Quality Contamination Groundwater and Settlement Management Trees and Vegetation Erosion and Sediment Controls Industrial Trade Activity Management Plan

24


Who approves the plans and how?

DRAFT

Construction Environment Management Plan Delivery Work Plan/ Management Plans

Community Liaison Group

Council draft review Update

Update Submit to Auckland Council for approval

peer review panel • Transport, Access and Parking • Noise and Vibration • Social Impact and Business Disruption • Historic Character • Trees and Vegetation • Contamination • Air Quality

OPW approval (Designation)

Certification (A2N)

Consultation and Engagement – on going during process 25


What happens after the plans are approved ? Construction Environment Management Plan

Annually reviewed

Delivery Work Plan/ Management Plans

Material Change or unforeseen effects

Material Change?

IF YES: Compliance with conditions Construction method changes Results of monitoring Comments from Auckland Council

Affected parties will be notified of review and material change CEMP/DWPs to document inputs received Subject to peer review Submitted to Auckland Council for approval

26


Caroline Secretin Principal Environmental Scientist

Construction Environmental Management Plan

27


John Daly Principal Planner/ Social Impact Specialist

Social Impact and Business Disruption DWP

28


Aaron Hutching Aotea Community Manager

Communication and Consultation Plan

29


Ellen Chang Civil Engineer

Erosion and Sediment Control Plan

30


Jason Pene Air Quality Specialist

Air Quality DWP

31


Lyndsey Smith Principal Environmental Scientist (Ecologist)

Trees and Vegetation DWP

32


Dan Marsh Lead Transport Specialist

Transport, Access and Parking DWP

33


Joe Grimes Noise and Vibration Specialist

Construction Noise and Vibration DWP (Site Specific Noise and Vibration Management Plans)

34


Jane Matthews Project Historical Architect

Historic Character DWP – Built Heritage

35


Sarah Macready Project Archaeologist

Historic Character DWP – Archaeology

36


Emma Trembath Land Contamination Specialist

Contamination DWP

37


George Brink Groundwater and Settlement Specialist

Groundwater and Settlement Monitoring and Contingency Plan

38


Rose Turnwald / Rob Van de Munckhof Environmental Engineers

Industrial and Trade Activities Environmental Management Plan

39


Delivery Work Plans round table DWPs

SME for Roundtable

Air Quality

Peter Stacey/Jarrod Snowsill

Consultation and Communications

Rachel Blundell, Aaron Hutching

Contamination

Emma Trembath/Naomi Macorison

Construction Environmental Management

Caitlin Smith

Construction Noise and Vibration

Claire Drewery/Joe Grimes

Erosion and Sediment Control

Ellen Chang

Groundwater and settlement

George Brink

Historic Character

Jane Matthews/Jarrod Snowsill

Social Impact and Business Disruption

Kim Hardy, John Daly/Holly Claeys

Traffic, Access and Parking

Dan Marsh

Trees and Vegetation

Lyndsey Smith

40


Aotea Station CLG

• Next Steps • Thank You

41