SHELDON ROAD & BRADSHAW ROAD
INTERSECTION IMPROVEMENT PROJECT
JANUARY 14, 2016 6—8 PM
Pleasant Grove High School 9531 Bond Road Elk Grove, CA 95624
WHAT IS THE PURPOSE OF THIS MEETING? This Open House meeting is being held to provide the public an opportunity to review the proposed project, view project designs (currently 35% complete), obtain the latest information about the project, ask questions, and offer input to the project team.
WHAT IS THE PLAN FOR THE EVENING? 6—8 PM
OPEN HOUSE Sign in, review displays, provide input, ask questions, and enjoy refreshments
6:30—7 PM
PRESENTATION Learn more about the project details.
WHAT IS BEING PROPOSED? Improvements to the intersection of Sheldon Road and Bradshaw Road are planned because threshold values for increased traffic have been met, per the process outlined in the Rural Road Improvement Policy and Standards. Based on community input and City Council direction, two options are being considered for the intersection: a signal or a roundabout. All proposed designs, currently 35% complete, take into consideration design preferences expressed in the Rural Road Improvement Policy and Standards. Tonight we would like to get your input on these designs and understand your design preferences.
WHAT IS THE PROJECT SCHEDULE? DATE
MILESTONE
November 30, 2011
First Open House with the entire Rural Roads area invited to provide input on intersection alternatives to be considered
June 13, 2012
City Council directed to proceed with a signal and a roundabout design
November, 2015
• Design advanced to the 35% level • Environmental field studies completed • Environmental technical reports approved by Caltrans (federal funding requirement)
December, 2015
City environmental document (IS/MND) completed and circulated for public review/comment
January 14, 2016
Community Open House
January 27, 2016
City Council Meeting
Summer 2016
Federal environmental documents approved by Caltrans and FHWA
Early 2017
Community Open House
Summer 2017
Right-of-way acquisition completed
Summer 2017
Final design completed
Fall 2017
Advertise for construction
Late 2017—2018
Construction
WHAT WILL THIS PROJECT COST? SIGNAL PROJECT COST = $6.1M $5.2M in federal funds $900K in City funds ROUNDABOUT PROJECT COST = $7.9M $5.2M in federal funds $2.7M in City funds
Here we are today!
ROUNDABOUT INTERSECTION OPTION LEGEND: Proposed Roadway Proposed Paths
Bradshaw Road
Sheldon Road
ROUNDABOUT INTERSECTION
SIGNAL INTERSECTION OPTION LEGEND: Proposed Roadway Proposed Paths
Bradshaw Road
Sheldon Road
CONTACT US Tom Metcalf (916) 478-2281 TMetcalf@elkgrovecity.org
City of Elk Grove Public Works Department 8401 Laguna Palms Way Elk Grove, CA 95758