WINTER ’17 vol. 1 Aquatics 14 Calendar of Events 15 Community Main St. 11 Hearst Center 6–7 Historical Society 11 Library 8–9 Mayor’s Corner 3 Public Meetings back Rec Center 12–13
UNIVERSITY AVENUE UPDATE Construction work on University Avenue is drawing to a close for the winter. Much has been accomplished since the project kicked off on March 1, 2016. New water main, storm sewer, and sanitary sewer are mostly completed
May 2016
June 2016
IMAGES OF BOULDER/UNIVERSITY AVENUE INTERSECTION November 2016
(Phase 1 of the project). Following this underground work, new pavement was installed. Two new intersections are fully completed: Boulder Drive and Holiday Road. New access points are provided at Royal Drive and Melrose Drive. Lighting and landscaping are installed, with more to come. University Avenue will be open with two lanes of traffic in both directions over the winter. The City would like to thank everyone for their patience during construction. Work will continue next year, to complete Phase 1 and move into Phase 2
UAS imagery courtesy of Foth Infrastructure and Environment LLC, Cedar Rapids office
between Grove Street and McClain Drive
(McClain Drive to Midway Boulevard). More information on Phase 2 will be
By the numbers:
available in the Spring and future articles.
57,500 square yards of pavement
Please continue supporting the businesses
9,700 square yards of trails & sidewalks
along University Avenue. Construction
12,000 feet of storm sewer pipe
update maps and other information
140 storm sewer structures
are available on the project website at
8,000 feet of water main
www.cedarfalls.com/universityave.