GOAL 2: Island Reclamation Plant Relocation
GOAL 2: Island Reclamation Plant Relocation: Design
Key Issues
Target Date: 12/25 Grants and Outside Funding Sources Debt Restructure Rate Structure Use of Property Plant Design 1. Complete 30% design
Complete 2. Prepare report with recommendations Complete 3. DECISION: Debt Restructure and Rate
Approval Complete 4. Complete 60% design 8/22 5. Complete 90-100% design 12/22 6. Begin construction 2023
Responsibility: FPUA
July 2022 Update
60% wastewater plant design has been scheduled for the August 2, 2022 FPUA Board meeting. This includes early material ordering and work packages to address supply chain delays. Additionally, the request will include direct owner purchases provision to reduce tax cost and reducing the total project cost.
FPUA DOU and City Manager will continue to propose a solution for the disposition of property for the benefit of both entities.