GOAL 2: Island Reclamation Plant Relocation

GOAL 2: Island Reclamation Plant Relocation: Design

Key Issues

 Target Date: 12/25  Grants and Outside Funding Sources  Debt Restructure  Rate Structure  Use of Property  Plant Design 1. Complete 30% design

Complete 2. Prepare report with recommendations Complete 3. DECISION: Debt Restructure and Rate

Approval Complete 4. Complete 60% design 8/22 5. Complete 90-100% design 12/22 6. Begin construction 2023

Responsibility: FPUA

July 2022 Update

60% wastewater plant design has been scheduled for the August 2, 2022 FPUA Board meeting. This includes early material ordering and work packages to address supply chain delays. Additionally, the request will include direct owner purchases provision to reduce tax cost and reducing the total project cost.

FPUA DOU and City Manager will continue to propose a solution for the disposition of property for the benefit of both entities.