GOAL 3: Downtown Development Master Plan

GOAL 3: Downtown Development Master Plan: Development

Key Issues

 Vision  Boundary  Projects  Land Uses  Development Standards 1. Finalize scope of project Complete

2. DECISION: Funding Direction 3. Task 1: Kick-off, Data Collection, and

Project Management 4. Task 2: Public Engagement Complete Complete

Complete

5. Task 3: Market Study, Frameworks

Overlays Complete

6. Task 4: Design Charette Complete 7. Task 5: Final Master Plan Presentation 9/22

Responsibility: City Manager

July 2022 Update

The design charette workshops were held June 27-30, 2022. During the week, a team of design experts met with stakeholders like local citizens, businesses, community groups, and property owners to develop a shared vision for the future of Downtown Fort Pierce and adopt an implementation strategy to guide development. S&ME is now preparing the final master plan that will be presented to the CRA Advisory Committee and FPRA Board in Fall 2022.