GOAL 4: Greenway Trail
GOAL 4: Greenway Trail: Development
Key Issues
Link to Sun Trail Goals Options Funding Route through Downtown FEC Land Acquisition (Small Parcel 1. Complete Highwaymen Trail Gap
Design 2. Solidify Historic Downtown route 3. CONFERENCE AGENDA: Presentation and
Direction 8/22
10/22 11/22
4. DECISION: Historic Downtown Route 12/22 Responsibility: City Engineer
July 2022 Update Highwaymen Trail Segment
• Design plans to be completed by end of August 2022. • No response received from FEC Railroad in regard to purchase or lease of corner parcel for trail connectivity.
Historic Downtown Segment
• Consultant has submitted 30% plans for review. • Alternative routes being explored (ongoing). • Proposed route shared with consultant working on Downtown Master Plan.