GOAL 3: Seaplane/Shuffleboard Area: Directions and Actions

GOAL 3: Seaplane/Shuffleboard Area: Directions and Actions

Key Issues

 Design  Construction  Funding 1. Prepare report 2. CONFERENCE AGENDA: Report

Presentation and Direction 8/21 10/21

3. DECISION: Design Contract

12/21 4. Complete design 3/22 5. DECISION: Award construction contract 5/22 6. Construction 2022

Responsibility: City Engineer

September 1, 2021 Update

Executed Letter of Agreement between City and Lawnwood Medical Center submitted to FDOT. Awaiting finally permit approval for Seaplane Base.