Avenue B (13th Street to 8th Street)

Construction continues with improvements moving east of 10th Street. Drainage work at 9th Street has been completed, curb, gutter and sidewalk are being formed. Underground utility conduit installation is nearing completion, with pedestals and junction boxes to remain.

Avenue D (Indian River Drive to 29th Street)

The most recent submittal for the resurfacing of Avenue D from 29th Street to US 1 is currently in review. The project is anticipated to be out for bid in July.

Ohio Avenue

(US Highway 1 to 11th Street)

A pre-construction meeting has been scheduled for July 12, 2023, and construction commencement is anticipated for September 2023.

2023 Annual Resurfacing Contract

The Annual Resurfacing Contract Request for Proposals has been advertised and bids are due July 27, 2023. The term of this contract is three years with options to renew for two additional one-year periods.

2023 Annual Pavement Marking Contract

The contractor proposal for the restriping of Delaware Avenue is scheduled for approval at the July 17 Commission meeting.

The Oaks at Moore’s Creek Phase II (Means Court Extension)

The project includes the extension of Means Court roadway between Avenue B and Moore’s Creek to support a 15lot single-family affordable housing subdivision. Improvements include water, sewer, gas, and storm drainage facilities, along with sidewalks, curb & gutter, street lighting, landscaping, and underground electric.

Current work activities include the installation of the conduits for fiber, street lighting, and underground electric, along with sidewalk and driveway apron construction.