JANUARY 31, 2025

UPCOMING EVENTS

February 4: EDC Board Meeting (12:00 PM, Council Chambers)

February 11: City Council Meeting (5:00 PM, Council Chambers)

February 12: Public Meeting for Sunset Boulevard Project (6:00 PM, Council Chambers)

February 20: Planning & Zoning Meeting (5:00 PM, Council Chambers)

February 26: Coffee with the Contractors (9:00 AM, 112 N. Arizona Dr)

CITY UPDATES

DOWNTOWN PARKING GARAGE: WORK UPDATE FOR FEBRUARY 3 - 7

With the crane now in place, significant progress continues on the Parking Garage project. Next week, construction efforts will focus on pouring perimeter and ramp walls, with columns continuing their vertical expansion. Additionally, work will commence on underground utilities, including stormwater drainage, sanitary sewer installation, electrical and power conduits, and domestic water infrastructure. These critical advancements will support the long-term functionality and efficiency of the facility.

UPDATE ON PRESTON ROAD GREEN RIBBON PROJECT

The Preston Road Green Ribbon Project continues to make significant progress, with flower bed preparation now complete from Preston Road/FM 455 to north of Celina High School. This phase included the strategic installation of new mulch and gravel, setting the foundation for a vibrant and sustainable landscape. Planting begins in late March or early April once temperatures are optimal for growth. The selected plant species - Blue Grama Grass, Blue Chip Juniper, Chapel Hill Yellow Lantana, Lilyturf, Pink Skullcap, and Asian Star Jasmine - will enhance the corridor with natural beauty while supporting long-term sustainability.

TEMPORARY LANE CLOSURE FOR W. FRONTIER PARKWAY

Beginning Monday, February 3, the westbound lane of W. Frontier Parkway between the Dallas North Tollway and Doe Branch Boulevard will be closed daily from 9:00 AM to 3:00 PM to accommodate utility installation and turn lane construction for the Creeks Retail development. Traffic signals will be in place to manage the flow of vehicles through the area. This temporary lane closure is expected to last approximately one month, weather permitting. We appreciate the community’s patience and cooperation as we work to enhance infrastructure and improve traffic flow in this corridor.

ANNUAL “CHOUP” COOK-OFF BRINGS CITY STAFF TOGETHER

Last week, City staff came together for our annual “Choup” Cook-Off, where team members showcased their favorite chili and soup recipes for everyone to enjoy. Chief John Cullison, Shannon Gartner, and Amy Alexander had the honor of serving as judges for this friendly competition. Events like these play a vital role in fostering camaraderie among our staff, especially as our team is spread across various locations. They provide an opportunity for connection, inclusion, and shared moments of enjoyment. We extend our appreciation to our Human Resources team for their dedication to organizing these meaningful activities, which strengthen our workplace culture and bring us together as one team.

WELCOMING NEW TEAM MEMBERS AND CELEBRATING STAFF PROMOTIONS

The City of Celina is pleased to welcome five exceptional individuals to our growing team and to celebrate the well-earned promotion of one of our own. Their contributions will play a vital role in advancing our mission, and we are confident in the positive impact they will make. As we continue to build a strong and dedicated team, we look forward to the leadership and innovation they will bring in shaping the future of Celina.

ANNUAL STREET MAINTENANCE UPDATE: HILLSIDE STREET

The Public Works Department, in partnership with Apple Pavement Services, will be conducting essential road maintenance as part of the Annual Street Maintenance (ASM) Program. This project will take place on Hillside St., from Maryland St. to the dead end, beginning on Monday, February 3, and concluding on Monday, February 17. During this time, two-way traffic may be limited in construction areas, and the contractor will direct traffic through the affected zones as needed. Residents in the affected area have already been notified of the upcoming work. We appreciate your patience and cooperation as we work to improve our roadways.

DALLAS NORTH TOLLWAY PHASE 4A PROJECT: LANE CLOSURE NOTIFICATION

As part of the ongoing work on the DNT Phase 4A project, please be advised that crews will be implementing the upcoming lane closures. These closures are necessary for transporting topsoil, performing a mass haul of materials, and completing clean-up work in the affected areas. Please note that the entire left lanes will not be closed,

Angela Aguirre Rojas Site Coordinator
Michael Cook Construction Inspector
Gavin Dennis Part-Time Parks & Recreation Maintenance Worker
Alycea Hooten Wastewater Camera Technician
Joseph Westbrook Firefighter/Paramedic
Michael Graff Promoted to Senior Plans Examiner

and we will ensure there are no conflicts between lane closures within the same areas. Additional closures will occur at construction exits as needed to maintain safety and efficient traffic flow.

February 3, through Saturday, February 8, from 6:30 AM to 6:30 PM

• The daily northbound and southbound left lane of Dallas Pkwy. from First St. to FM 428

Monday, February 3, through Friday, February 7, from 9:00 AM to 4:00 PM

• The daily northbound and southbound U-turn lane at First St.

ROAD CLOSURES RESIDENT MAP

The City ‘s Road Closures Resident Map serves as a crucial tool for residents to remain informed about ongoing projects and associated road closures within the city. This comprehensive resource empowers individuals to plan their travel routes effectively, minimizing disruptions caused by construction activities. By clicking on the map or accessing the link above, residents gain access to the full interactive map, ensuring easy navigation and timely updates on the evolving infrastructure projects throughout Celina.

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
City Manager's Weekly Report (January 31, 2025) by Celina, Texas - Life Connected. - Issuu