F 3 COAT STUCCO EXTERIOR FINISH; SCRATCH, BORWN AND FINISH, APPLY TO FACE OF APEX BLOCK
C
5" CONC. TOP SLAB OF INSUL-DECK FLOOR SYSTEM - SEE STRUCT.
WATER AND ICE GUARD
L
ST STUCCO REGLET OR DRIP SCREED, EQUIV.
PITCH STUCCO FINISH TOWARD ROOF - (TYP.)
RADIANT HEATING COILS
RADIANT HEATING COILS
Main Roof/Stairwell 60' - 0"
ROOFING MEMBRANE
12" INSUL-DECK FLOOR SYSTEM
PITCH STUCCO FINISH TOWARD ROOF -(TYP.)
10" APEX BLOCK WALL
10" 5"
BUILT-UP CANT STRIP
CABLE RAIL POST; EPOXY AND SET INTO CONC. PARAPET.
FILL CORES/CONC. GROUT. -SEE STRUCT. FOR REINFORCING
10"
J
ROOF SOIL (GROWING MEDIUM) GREEN ROOF SYSTEM. SKY GARDEN GR-SP; GR FILM SEAMS TAPED W/ ROOT GUARD
7" DIAM. METAL FLUE
REBAR @ BOTTOM OF CONC. BEAM - SEE STRUCT. W 14X STEEL BEAM (TYP); EXPOSED - SEE STRUCT.
10" DIAM. FLUE COVER 2" AIR SPACE
INSULATION POLYSTYRENE FOAM 3' - 8 1/2"
5/8" GYP. CEILING
4" MEATL STUD FRAMING
5/8" GYP. CEILING
ROOT BARRIER; ROOT GUARD 5/8" PLYWOOD SHEATHING
WATERPROOF MEMBRANE
ICE AND WATER GUARD
10" APEX BLOCK
TOP SLAB OF INSUL-DECK FLOOR; SLOPE 1/8"/FT ROOFING MEMBRANE
HORIZONTAL CABLE RAIL RAILING BY CABLE RAIL OR EQUIV.
ROOFING MEMBRANE OVER CONC. SLAB.
Second Floor 12' - 0"
CABLE RAIL RAILING; BY CABLE RAIL OR EQUIVALENT
CABLE RAIL POST; EPOXY AND SET INTO CONC. PARAPET.
ROOFING MEMBRANE
RAILLING POST; DOWEL INTO AOEX BLOCK PARAPET, GROUT AND EPOXY
1' - 4"
WESTILE PAVER ROOFING SYSTEM SEE DETAIL 7/A4.7
WESTILE PAVER ROOFING SYSTEM - SEE DEATIL 7/A4.7
3 COAT STUCCO EXTERIOR FINISH; SCRATCH, BROWN AND FINISH; WRAP OVER WALL; CONTINUOUS.
REBAR @ UNDERSIDE OF INSUL DECK CONC. BEAM -SEE STRUCT.
MODIFIED APEX BLOCK
12" INSUL-DECK FLOOR SYSTEM W/ 4-1/2" TOP CONC. SLAB; SLOPE TO DRAIN 1/8"/FT (TYP.) RAIDANT HEATING COILS
5/8" GYP. CEILING MODIFIED APEX BLOCK; THIS LOCATION
REBAR @ UNDERSIDE OF CONC. BEAM -SEE STRUCT.
5/8" GYP. CEILLING
FILL CORES W/ CONC. GROUT. -SEE STRUCT.
12 1/2" INSUL-DECK FLOOR SYSTEM - SEE STRUCT.
REBAR @ BOTOTM OF CONC. BEAM
5/8" GYP. CEILING
P.T. 2X10 FRAMING @ DOOR OPENING
REBAR @ BOTTOM OF CONC. BEAM - SEE STRUCT. W 14X STEEL BEAM (TYP); EXPOSED - SEE STRUCT.
5/8" GYP. CEILING
8 Wall @ Parapet and Cable Rail 1" = 1'-0"
REINFORCED CONC. LINTEL - SEE STRUCT.
Fifth Floor 48' - 0"
P.T. 4X12 CURB; WRAP W/ ROOFING MEMBRANE & WATERPROOF MEMBRANE BY G-SKY.
10" APEX BLOCK WALL
12 1/2" INSUL-DECK FLOOR SYSTEM
5" CONC. TOP SLAB OF INSUL-DECK FLOOR SYSTEM - SEE STRUCT.
RADIANT HEATING COILS
Second Floor 12' - 0"
REBAR @ UNDERSIDE OF INSUL-DECK CONC. BEAMS
F
Third Floor 24' - 0"
PITCH STUCCO FINISH TOWARD ROOF - (TYP.)
TOP CONC. SLAB OF INSUL-DECK FLOOR; SLOPE 1/8"/FT
Detail @ Steel Beam and Roof 1/2" = 1'-0"
2X10 BLOCKING
L
BUILT-UP CONC. CANT STRIP
4
3 COAT STUCCO EXTERIOR FINISH OVER METAL LATH; SCRATCH, BROWN AND FINISH
11 3/4"
K
WATER AND ICE GUARD
RADIANT HEATING COILS
WESITLE PAVER ROOFING SYSTEM - SEE DETAIL 7/A4.7
1' - 4"
Roof Parapet Detail 1/2" = 1'-0"
1' - 4"
10
I
6 Planter Detail @ Deck 1/2" = 1'-0"
3 Insul-Deck @ Steel Beam 1/2" = 1'-0"
ROOFING MEMBRANE O/ CONC. SLAB @ EXTERIOR DECK
J
TOP CONC. SLAB OF INSUL-DECK FLOOR; -SEE ROOF PLAN FOR SLOPES & DRAINAGE
6" 12" 4"
4" POURED CONC. APRON @ DRIVEWAY - SLOP TO RAIN TO STORM DRAINAGE @ STREET
#3 REBAR @ 16" O.C. E.W.
RADIANT HEATING COILS
ROOT BARRIER; ROOT GUARD WATER PROOF MEMBRANE
REBAR @ UNDERSIDE OF INSUL DECK CONC. BEAM - SEE STRUCT.
Fifth Floor 48' - 0"
DRIP SCREEN - ST STUCCO REGLET OR DRIP SCREEN EQUV.
APEX WALL SYSTEM 5/8" GYP. CEILING
5 1/2" MTL C CHANNEL SILL PLATE: THRU BOLT INTO CONC. SLAB (TYP.)
2 Fifth Floor Planter @ Ext. Wall 1/2" = 1'-0"
1' - 8"
4" METAL STUD FRAMING
VOLCLAY WATER PROOFING PANELS, SEE SHEET A4.14 FOR DETAILS; INSTALL PER MANUFACTURERS REQUIREMENTS
INSULATION POLYSTYRENE FOAM
3 COAT STUCCO EXTERIOR FINSIH; SCRATCH, BROWN AND FINISH
FILL CORES W/ CONC. GROUT -SEE STRUCT. FOR REINFORCING
10" APEX BLOCK WALL
STL REINFORCING -SEE STRUCT.
5/8" GYP. CEILING
2' - 6 3/4"
4" WASHED AND CLEANED GRAVEL
GREEN ROOF SYSTEM SKY GARDEN GR-SP; GR FILM SEAMS TAPED W/ ROOT GUARD
DRIP EDGE
WATER AND ICE GUARD; MOISTURE BARRIER (3) COAT STUCCO EXTERIOR FINISH OVER METAL LATH; SCRATCH, BROWN, FINISH
2X6 WD NAILER
5 1/2" MTL 'C' CHANNEL (TYP.)
Stairwell Roof 72' - 8"
5/8" PLYWOOD SHEATHING.
First Floor 0' - 0"
BUILT-UP CONC CANT. STRIP
FLASHING
Fourth Floor 36' - 0"
FLASHING
5/8" PLYWD SHEATHING
D
CLAY FLUE CAP.
1/2" EXPANSION JOINT
P.T. 4X12 ROOF SOIL (GROWING MEDIUM)
METAL FLUE CAP. CLAY FLUE TO EXTEND PAST CHIMNEY (CAP @ 12" DIM.)
12" INSUL-DECK FLOOR SYSTEM - SEE STRUCT.
REBAR @ UNDERSIDE OF INSUL-DECK CONC. BEAMS - SEE STRUCT.
Notes
G
GARAGE DOOR
5/8" GYP. CEILING
7" DIAM. FLUE; W/ 10" FLUE COVER
L
4" MEATL STUD BRACING @ 24" O.C.
5 1/2" METAL STUD WALL
EXISTING FILL
3 COAT STUCCO EXTERIOR FINISH; SCRATCH, BROWN AND FINISH
5" POURED CONC. -SEE STRUCT. FOR STL REINFORCING
1' - 4"
STL REINFORCING -SEE STRUCT. CONT. POURED CONC. FOOTING -SEE STRUCT.
Third Floor 24' - 0"
6"
1' - 0"
Basement Floor -12' - 0"
1' - 8"
FILTER BARRIER PER MANUFACTURER SPECIFICATIONS - TYP. MIN. 4" DIAM. FOUNDATION DRAIN
9 Wall Section @ South Wall 1/2" = 1'-0"
REBAR @ UNDERSIDE OF INSUL DECK CONC. BEAM - SEE STRUCT.
12" INSULDECK FLOOR SYSTEM 7" FLUE TO EXTEND THRU INSULDECK FLOOR; EXTEND TO WOOD BURNING STOVE UNIT. W/ 10" FLUE COVER
7 Detail @ Chimney Flue (Typ.) 1/2" = 1'-0"
6 7/8"
INSUL BLANKET W/ VAPOR BARRIER ONE SIDE - TYP. @ CONC. SLAB LOCATIONS
VOLCLAY WATER PROOFING PANELS, SEE SHEET A4.14 FOR DETAILS; INSTALL PER MANUFACTURERS REQUIREMENTS
5' POURD CONC. SLAB W/ STL REINFORCING -SEE STRUCT.
ROOFING MEMBRANE O/ CONC. SLAB @ EXTERIOR DECK
RADIANT HEATING COILS
TOP CONC. SLAB OF INSUL-DECK FLOOR; -SEE ROOF PLAN FOR SLOPES & DRAINAGE
4" WASHED & CLEANED GRAVEL
Main Roof/Stairwell 60' - 0"
APEX BLOCK WALL BEYOND
5 1/2" METAL STUD WALL
1/2" EXPANSION JOINT WESTILE PAVER ROOFING SYSTEM -SEE DETAIL 7/A4.7
2X10 NAILER
10" POURED IN PLACE CONC. WALL
INSUL BLANKET W/ VAPOR BARRIER ONE SIDE -TYP. @ CONC. SLAB LOCATIONS
STL REINFORCING -SEE STRUCT.
Date
05/07/20
Drawn by Checked by
BB PHJ
CONT. POURED CONC. FOOTING -SEE STRUCT.
6"
Basement Floor -12' - 0"
RADIANT HEATING COILS
12"
5 1/2" METAL STUD WALL
8' - 11"
Clerestory Roof 65' - 6"
RADIANT HEATING COILS
BRIAN BECHTOLD
HALL RESIDENCES
TOP CONC. SLAB OF INSUL-DECK TO SLOPE 1/8"/FT
5/8" GYP. CEILING REBAR @ UNDERSIDE OF INSUL DECK CONC. BEAM -SEE STRUCT.
20"
FILTER BARRIER PER MANUFACTURESERS SPECIFICATIONS -TYP.
Details
MIN. 4" DIA FOUNDATION DRAIN; DRAIN TO CISTERNS; EXCESS WATER TO DRAIN TO DAYLIGHT
-STL REINFORCING -SEE STRUCT.
5 Stairwell Roof Detail 1/2" = 1'-0"
1 Foundation Wall @ Footing 1/2" = 1'-0"
A 4.8