BIM EXECUTION

M E T C A L F E E L E M E N T A R Y S C H O O L RRESB DEVELOPMENT

MEET OUR TEAM

RESB DEVELOPMENT
Sarah Montgomery Project Manager Brandon Lopez BIM Manager Elham Ghahari Discipline Lead Ravi Kiran Mane BIM Support
Zoom Miro Autodesk Construction Cloud
OF COMMUNICATION Weekly Meetings Email Whatsapp RESB DEVELOPMENT
METHODS
Industries BEP AND MEETING LEVEL 400
RESB

SITE LOCATION

About the School:

Originally opened in 1969

Ranked among the top 20% of public schools in all of the State of Florida

1250 NE, 18 th Ave, Gainesville, Fl 32609

About the Site:

Sits on 13.56 acres

Overall (rough) SF: 76,500 ft²

Fifteen buildings to be modeled

Buildings connected by covered walkways

All single story buildings located on the same ground level

RESB DEVELOPMENT
RESB
14 15 1/2 1 1/2 4 Brandon Lopez: 01. Architectural 02. Structural 10 11 1/2 1 1/2 4 Sarah Montgomery: 5 3 7 2 8 Elham Ghahari: 6 9 12 13 Ravi Kiran Mane: 14 15 1/2 1 1/2 4 Brandon Lopez: 10 11 1/2 1 1/2 4 Sarah Montgomery: 5 3 7 2 8 Elham Ghahari: 6 9 12 13 Ravi Kiran Mane: 03. MEP Plumbing Electrical Brandon Lopez: HVAC Electrical Sarah Montgomery: 03. Technical Information Lumion Brandon Lopez: Synchro Pro Sarah Montgomery: Navisworks Ravi Kiran Mane:
DEVELOPMENT PROJECT RESPONSIBILITIES
RESB DEVELOPMENT SITE PLAN WORK BREAKDOWN 14 15 3 2 11 13 1 12 4 5 6 10 9 8 7
SARAH MONTGOMERY RAVI MANE ELHAM GHAHARI BRANDON LOPEZ

ARCHITECTURAL

Building 11 Existing Plan
RESB DEVELOPMENT
Building 11 RESB's Plan

Building 14 Existing Plan

ARCHITECTURAL

Building 14 RESB's Plan

RESB DEVELOPMENT

Building 12 & 13 Plan

STRUCTURAL

Building 12 & 13 Isometric View

RESB DEVELOPMENT

STRUCTURAL COMPONENTS

RESB DEVELOPMENT

ELECTRICAL SYSTEM

RESB DEVELOPMENT

MECHANICAL

RESB DEVELOPMENT

PLUMBING

RESB DEVELOPMENT

LUMION/GOOGLE EARTH PLAN COMPARISON

RESB Industries

LUMION RENDER

RESB Industries
RESB Industries

RESB Industries

CLASH DETECTION

List of clash results we encountered after the clash detection test:

Windows with columns

Columns with floor

Columns with walls

Columns with ceiling

Columns with roof

Joists with walls(Exterior & Interior)

Joists with ceiling

Joists with Roof

External walls with beams

Partition walls with beams

RESB Industries

ACCEPTABLE

Columns clashing with floor Columns clashing with wall Columns clashing with ceiling
RESB Industries

RESB Industries

CLASH DETECTION

ACTIVE

Windows with columns

Clash of Walls with Joists and beams Clash of Roof with joists and beams
RESB Industries PROJECT DIFFICULTIES 01 02 03 Drawings missing/difficult to interpret Lumion crashing in the middle of renders Time Management 04 Video quality upload Issues 05 Computer processor issues for structure model

THANK YOU