Skip to main content

WorkSamples_Blake_Minster

Page 1

01.\

DENVER INTERNATIONAL AIRPORT | Stantec & RNN Architects Construction Administration - Construction documentation Project Lead: Carl Hole CA Lead: Nathan Martin, Rusty Lamb Softwares: Revit, Trimble ProjectSight, Bluebeam Program: Aviation Terminal interior renovation Location: Denver, Colorado

PROJECT OVERVIEW

E1

E2

E3

E4

E5

• Aided Stantec with the Construction Administration process. • Managed ‘As-Built’ Drawing set in BIM. • Formulated sketches in response to RFI’s • Conducted frequent observation walks with contractors. • Aided with Punch walks for approval of construction. • Submittal reviews. • Attended coordination meetings between MEP and structural. • Reviewed Shop Drawings • Construction Document production for Phase 2

E6

E7

E8

E9

CITY & COUNTY of DENVER

E10

DENVER INTERNATIONAL AIRPORT D

COUNTY DENVE OF

E.J.

N22

CITY AN

EW

Personal Duties:

R

Work includes moving all TSA Security Lines from Level 5 to Level 6 while reconfiguring ticketing and baggage check-in at Level 6. Vertical circulation to / from the Level 4 train departure platform is being expanded and MEP / COM / Security systems are being reconfigured from Level 3 through Level 7 roof to accommodate alternations to the terminal. Baggage Handling Systems from Level 6 to Level 4 are undergoing major renovations / changes. Retail spaces are also undergoing relocation and reallocation where possible. The Terminal is identified by three modules: MOD 1, 2 and 3 and the project consists of three phases. The first two Design/Construction Phases are scheduled to be completed within the original $770 million budget and involve the middle third (Mod 2) in its entirety and the west half of the north third (Mod 1) of the existing terminal building. The initial 2 phases focus strictly on installing new ticketing / check-in space on Level 6 for selected airlines in Mod 2, reconditioning all of Level 5 in Mod 2 as well as a new TSA security checkpoint in the west half of Mod 1, level 6 of the north area of the main terminal. Modifications to Level 4 AGTS (train) platform and new MEP systems are included in this initial work.

SE A L DESIGNER OF RECORD SC-T 6

ACM-8 8' - 6"

S ELEVATOR LOBBY

TML_05_11E_011

3

11'-4"

A5.3209

E-GYP 11' - 6"

RFI 2509

E-GYP 11' - 6"

2'-9"

2'-9" 2'-8 1/2"

A

39

5

S

GYP-1 11' - 6"

A

ACT-2 11' - 6"

S

20'-11 1/4"

7'-8"

S

S

Z1 8' - 6"

1'-4"

S

2'-10 3/4"

RFI 2673

1 OPP __________________ A5.1821

E-GYP 9' - 0"

1'-4 1/2" S

S

ACT-2 11' - 6"

S

RFI 2509

RFI 2509 ACT-2 4'-0" 11' - 6"

GYP-1 8' - 6" S

ENTRANCE

S

A5.3209

4 Z1 10' - 0"

TR-12.1 A

S

Z1 8' - 6"

OTS -

S

N20

S

TML_05_11E_MS38

Z1 8' - 6"

RFI 2441

A

TML_05_11E_122

MECH. SHAFT

OPH 1

GYP-1 8' - 6"

S

E-GYP 11' - 6"

A

S

__________________

(E)TE-90

GYP-1 11' - 6"

S

S

Z1 8' - 6"

(E)TE-91

(E)TE-92

1'-4"

SC-3

S

1'-4"

1'-6"

3 A5.3311

__________________

10'-6 3/4"

6'-8"

OPP

RFI 2276

6'-8 1/4"

GYP-1 12' - 3"

S

S

S

S

S

ACM-8 8' - 7"

ACM-8 8' - 7"

VESTIBULE TML_05_11E_CR03

7

ACT-1 12' - 6" GYP-1 13' - 11"

S

1050 17TH ST., #A200, DENVER, CO 80265

S 5

RFI 2276

RFI 2952

STANTEC

N21

A

__________________

GREAT HALL COMPLETION PHASE 1

2 A5.1821

__________________

OPP

1'-4"

1 / A5.1561

4

ACT-2 14' - 0"

1 A5.4101

OTS -

__________________

S

ELECTRICAL

OTS -

E-ACT 9' - 0"

RFI 3015 5

S

S

TML_05_11E_080

1 A5.1881

__________________ OPH

S RFI 2509

S

4

S

S

A

N19

ACL 14' - 0"

A WHITE BOX S EQ

WHITE BOX

TYP EQ

S

S S

TML_05_11E_005 OTS -

TML_05_11E_115

S

S

S

A

S

LIFT SYSTEM

4

TML_05_11E_097 S

OTS -

A

1 A5.1893

__________________

10 S

2'-0"

4

37

S 35

S 10

A5.1764

TML_05_11E_086

A5.1764

JANITOR CLOSET

S

EQ

TML_05_11E_126

5

2'-1"

S

2'-0"

2'-0" 2'-0"

GYP-1 9' - 5"

GYP-1 8' - 0"

°

6" 6" 6"

83

83

°

RFI 2772 5

S

2'-0"

S

A5.3311

S

S

S

S

S

TML_05_11E_121

A5.5306

2 OPP __________________ A5.1782 S (E) BAGGAGE BOH

(E) BAGGAGE SHAFT

TML_05_11E_048

TML_05_11E_MS36

OTS -

S

A

MECH SHAFT

BIM 360://03-SP-TML GHP Completion-201735867/TML_STN-A_GHCP-5-6_Central-2021.rvt

CEILING HATCH LEGEND RADIO ANTENNA WIFI AP CEILING

WIFI AP OMNI S S

ALL DEVICES LOCATED IN CEILING OTHER THAN ACL TO HAVE A WHITE FINISH. RE: CEILING MATERIAL LEGEND.

SQUARE 2' LAY-IN AIR RETURN RETURN AIR GRILLE

WORKPOINT LEGEND

EXIT SIGN A

FIRE ALARM SPRINKLER (FIRE EXTINGUISING)

SPEAKER COLUMN

ALL DEVICES LOCATED IN ACL CEILING TO HAVE A BLACK FINISH.

SQUARE 2' LAY-IN AIR DIFFUSER

DAYLIGHT SENSOR

SPEAKER

AMBIENT NOISE SENSOR

LINEAR DIFFUSER 4" WIDE MAX.

WP

ARROW INDICATES STARTING WORKPOINT FOR CEILING LAYOUT

GYPSUM BOARD

OPEN GAPS FOR AIR RETURN

5

BATT INSULATION ABOVE CEILING, 3" MIN.

ACM-8 PERFORATED METAL LAY-IN TEGULAR PANELS AND GRID ACL PERFORATED LINEAR METAL PANEL

REFER TO A5.5312 FOR ACCESS PANEL DETAILS.

SA-1 INSULATED METAL PANEL. RE:A5.7056 EXT ASSEMBLY SCHEDULE

PHASE LEGEND:

GYP-1 GYPSUM BOARD CEILING

OUT OF PHASE SCOPE

Z1, Y1, X1, W1 HORIZONTAL ASEMBLIES. RE. TO A5.7020 SCHEDULE 2HR FIRE RATED

OUT OF SCOPE EXISTING TO REMAIN 4

SHEET KEYNOTES RCP

CEILING MATERIAL LEGEND

ACT-3 ACOUSTIC CEILING TILE 2'X2' LAY-IN

ACOUSTICAL BATT INSULATION ABOVE

CAMERAS

SUSPENDED LINEAR LIGHTING FIXTURE SQUARE 2' LAY-IN LIGHTING FIXTURE

OCCUPANCY SENSOR

5

ACM-8 8' - 7"

AIR SHAFT TML_05_11E_095 MEN'S RESTROOM TML_05_11E_004

2 A5.1881

__________________

4

OTS -

OTS OPEN TO STRUCTURE RFI 2998R1 OTE OPEN TO EXTERIOR GYP-S ACOUSTICALLY INSULATED CEILING. RE. TO A5.5701. CAC=35 SC-1 / SC-2 / SC-3 SMOKE CURTAIN SC-T TEMPORARY SMOKE CURTAIN TO BE CONSTRUCTED IN CONFORMANCE WITH NFPA 204. REFER TO 8/A5.5304 FOR SIM DETAIL. FINISH TO MATCH ADJACENT CEILING.

5

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

SLOPED CEILING. REFER TO A5.3100 SERIES FOR POSITION, SLOPE AND DIMENSIONS. PROVIDE SMOKE SEAL AT GYPSUM BOARD CEILING EXISTING BAGGAGE CONVEYOR. OPEN TO ABOVE. SMOKE CURTAIN. REFER TO A5.5305 FOR DETAILS. NEW SMOKE CURTAIN TO TIE INTO EXISTING AT PHASE DEMARCATION. LOCATION OF NEW FIRE SUPPRESSION, FIRE ALARM, SECURITY, AND COMMUNICATIONS DEVICES IN EXISTING CEILINGS TO REMAIN OR OUT OF SCOPE CEILING AREAS TO BE COORDINATED ON SITE. REFER TO ENGINEERING DRAWINGS FOR QUANTITIES AND APPROXIMATE LOCATIONS. SET OFF LINE FOR LOW END OF CURVED CEILING. 5 NEW MECHANICAL LOUVER SYSTEM. EXISTING LOUVER TO REMAIN. EXISTING SOFFIT. FORMED METAL POCKET. CEILING ACCESS PANEL. REFER TO QUADRANT RCP FOR EXACT LOCATIONS. SUSPENDED FIXTURE TRACK. REFER TO A5.5501 FOR DETAILS. SELF-SUPPORTED CEILING. NO LIGHTING ABOVE OR BELOW CEILING. CEILING HEIGHTS BASED ON CENTRAL CORRIDOR HEIGHT. CENTRAL CORRIDOR CEILING HEIGHT. V.I.F CEILING HEIGHT TO MATCH EXISTING CONDITION. V.I.F CEILING HEIGHT TO MATCH CONTIGOUS CONDITIONS AT THE SAME CORRIDOR. MAINTAIN CONTINUITY OF FINISHES ONCE THE TEMPORARY SMOKE CURTAIN IS REMOVED. BEAM INSULATION COVER. REFER TO 5/A5.5114 & 9/A5.5114. 4 SLAB EDGE REFERENCE LINE. 5 ENCLOSE EXPOSED BRACING. CHECK ADA MIN HEAD CLEARANCE. SUSPENDED ART INSTALLATION TO BE REINSTALLED. SUSPENSION SYSTEM TO BE DESIGNED BY A STRUCTURAL ENGINEER AND INSTALLATION COORDINATED WITH CEILING SYSTEM. ARTWORK INSTALLATION REQUIREMENTS TO BE COORDINATED AND APPROVED BY DEN AND THE ARTIST.

SHEET KEYNOTES RCP 24 25

26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43

EXISTING SLOPED EXTERIOR CEILING. OUT OF SCOPE. APPROXIMATE EXTENT OF EXISTING ACT CEILING GRID AND TILES, INCLUDING CEILING-MOUNTED SERVICES/DEVICES, TO BE REMOVED, STORED, AND REINSTATED FOLLOWING CONSTRUCTION OF NEW HORIZONTAL SHAFT SHOWN DASHED ABOVE CEILING. EXISTING GYPSUM BORDER TO BE REINSTATED OR MADE GOOD TO MATCH EXISTING. SECURITY GRILLE CONTINUOUS LINEAR SLOT MADE FROM ACTIVE AND INACTIVE SECTIONS TO MATCH LENGTH INDICATED IN ARCHITECTURAL CEILING. MAINTAIN EXISTING HVAC AND LIGHTING SYSTEMS. EXISTING LIGHT COVE TO REMAIN. REFER TO 17/A5.5306. PARTIALLY ACOUSTICALLY INSULATED CEILING ACCORDING TO ADJACENT ROOM CONDITION. REFER TO A5.5701 ACT CEILINGS IN AGTS ARRIVAL PLATFORM TO MATCH EXISTING HEIGHT AT ELEVATOR LOBBIES. HEIGHT TO BE FIELD VERIFIED. ALIGN TO MATCH EXISTING CONDITION. EXISTING CEILING TO REMAIN EXISTING ESCALATOR TO REMAIN SUSPENDED SIGNAGE. REFER TO WAYFINDING DRAWINGS. ALIGNMENT LINE FOR FIRE PROTECTION AND SPEAKERS CENTRED ON PANEL WIDTH. WALL-MOUNTED SIGNAGE. REFER TO WAYFINDING DRAWINGS. TECHNICAL PANEL. LENGTH CUT TO SUIT. REINSTATE EXISTING WALL FACE ABOVE AND TIE IN TO NEW GYPSUM SOFFIT BORDER. SLAT EDGE PROFILE TO FOLLOW CURVE SIMILAR TO DETAIL 4/A5.3311 EXISTING LIGHTING AND DIFFUSERS TO BE RE-HOUSED IN NEW CEILING. REFER TO ENGINEERING DRAWINGS FOR OTHER NEW DEVICES. LAYOUT TO BE COORDINATED ON SITE. EXISTING EXIT STAIR TO BE REINSTATED. COMPLETE SCOPE TO BE VERIFIED AND COORDINATED ON SITE. EXISTING PROJECTOR TO BE RELOCATED

4

LVA LVA LVA STN STN STN STN STN STN STN STN STN STN STN STN STN STN STN

DATE CKD

IFC PHASE 1 PHASE 1 REV. 1 B-05-0003 B-05-0006 B-05-0006 PRC1 B-05-0007 B-05-0008 RFI 2509 RFI 2441 RFI 2673 RFI 2689 RFI 2772 RFI 2952 RFI 2998 RFI 3015 RFI 2946 RFI 2276 RFI 2998R1

SCALE:

3

1 ACT-1 ACOUSTIC CEILING TILE 4'X4' TEGULAR ACT-2 ACOUSTIC CEILING TILE 2'X4' TEGULAR

ALUM. METAL LINEAR PANELS

SMOKE SENSOR

DOWNLIGHT FIXTURE 5

OTS -

S

0 1 2 3 A 4 5

N16

A

S

ACM-8 8' - 7"

TML_05_11E_093

A

LINEAR RECESSED LIGHTING FIXTURE 4" WIDE MAX. LINEAR RECESSED EMERGENCY LIGHTING FIXTURE

ISSUE RECORD NO. BY PURPOSE

ENTRANCE TML_05_11E_186

S

EXISTING RESTROOM TO REMAIN. CLEAN, REPAIR AND REFRESH MATERIALS TO MAKE READY FOR PUBLIC USE.

GYP-1 8' - 6"

S

GYP-1 8' - 6"

37

CEILING FIXTURE LEGEND

OPP

1

__________________

RFI 2946

RFI 2689

PRC 1

8400 Peña Blvd., Denver CO 80249

4

RFI 2509

5

PLUMBING CHASE

E-GYP 8' - 0"

5

S

N17

S

TML_05_11W_080

5

A

A

E-ACT 9' - 0"

GYP-1 9' - 5"

23

35

S

GYP-1 9' - 8"

MS37

GYP-1 9' - 0" GYP-1 10' - 0"

GYP-1 8' - 0"

1

__________________

(E) MECH. SHAFT

S

OTS -

35 3 __________________ SIM A5.1821 OPP AIRSIDE CIRCULATION

CONVEYOR SYSTEM

TML_05_11E_044

GYP-1 11' - 6"

(E)TE-06N S

(E)TE-06S

S SHELL SPACE TML_05_11E_174

11

ACT-1 12' - 6"

S

E-GYP 8' - 0"

S RFI 2689

S

LANDSIDE CIRCULATION

TML_05_11E_096

42

A 7

1

A5.5301 6

41

S S

OTS -

S

S

__________________

2

GYP-1 8' - 0"

TML_05_11E_009

TML_05_11E_060

35

35

RFI 2509

2

GYP-1 9' - 0" S

S

A

S 7

S

WOMEN'S RESTROOM

Z1 11' - 6"

AIRSIDE CIRCULATION

WP

N18

E-ACT 9' - 0"

WHITE BOX TML_05_11E_010

GYP-1 8' - 0"

(E) STAIR 19 ST19

ACL 14' - 0"

41

WHITE BOX

GYP-1 9' - 0"

GYP-1 10' - 0"

EQ

2'-0"

A5.1764

2

GYP-1 9' - 0"

OTS -

__________________

S

24'-2"

STORAGE

A

A

GYP-1 9' - 0"

41

GYP-1 9' - 0"

S

1 / A5.1563 1 / A5.1564

S

WHITE BOX TML_05_11E_007 GYP-1 8' - 8"

5

__________________

1 / A5.1561

S

S

RFI 2998R1 RFI 2998

RFI 2689

TML_05_11E_110

S

TML_05_11E_040

FAMILY RESTROOM

SC-3

__________________

GENERAL NOTES: 1. REFER TO MECH., FIRE PROTECTION, PLUMBING, IT, ELECTRICAL AND TELECOM DRAWINGS FOR TYPES OF ASSOCIATED APPURTENANCES. 2. FOR CEILING TRIMS, TRANSITIONS AND EDGES, RE:A5.5301-A5.5314 CEILING DETAILS. 3. ALL RESTROOMS SHALL HAVE WATER RESISTANT CEILING FINISHES. 4. GRAY SHADED AREAS ARE OUT OF SCOPE. GRAY SHADED ELEMENTS ARE EXISTING. BLACK CROSSHATCH INDICATES OUT OF PHASE. 5. ALL "ACL" TYPE CURVED CEILINGS TO BE PROVIDED WITH FACTORY MITER CUTS AND FACTORY ASSEMBLED CURVED CARRIERS TO MATCH EXACT DIMENSIONS AND ANGLES SHOWN ON DRAWINGS. RE: A5.3207, A5.5303, A5.5304, AND A5.3311 - A5.3314 FOR DETAILS. 6. "ACL" TYPE CEILING LAYOUT WILL HAVE STAGGERED JOINTS WITH AT LEAST THREE STANDARD PANEL LENGTHS. 7. ALL CEILING TILES AND METAL PLANKS SHALL BE ACCESSIBLE IN ORDER TO PROVIDE ACCESS TO SYSTEMS OVER THE CEILING. 8. UNLESS OTHERWISE NOTED, ALL END DEVICES MUST BE CENTERED TO CEILING SPACE AND TO CLOSEST CEILING TILE, PANEL OR GYPSUM SOFFIT. 9. CEILING SUSP. SYSTEM TO BE DESIGNED BY CONTRACTOR’S ENGINEER WHO IS REGISTERED OR LICENSED TO PRACTICE WITHIN THE JURISDICTION OF THE PROJECT. DUCTWORK SUSP. SYSTEM SHALL NOT BE USED TO HANG CEILING BELOW UNLESS COORDINATED WITH DUCTWORK INSTALLER. 10. AT LEVEL 4 RCP, V.I.F AND COORDINATE EXISTING MECHANICAL, FIRE PROTECTION, IT, ELECTRICAL, TELECOM DEVICES AND ACCESS PANELS. MEP COORDINATION AT THIS LEVEL NOT INCLUDED IN PRESENT PERMIT PACKAGE U.N.O IN DRAWINGS. 11. REFER TO SHEETS A5.3312 & A5.3313 FOR SLAB EDGE BULKHEAD TYPES. 12. ALL CEILING HEIGHTS REFER TO FINISHED FLOOR ELEVATION. 5 13. CONTROL JOINTS AT CONTINUOUS GYP CEILINGS TO BE PLACED MAX 30' O.C. ALIGN WITH STRUCTURAL GRID AND WALL CONTROL JOINTS. RE: A5.5301. 14. "CL" SYMBOL REFERS TO CENTER OF ROOM OR CENTER BETWEEN COLUMNS U.N.O 15. ALL CEILING ELEMENTS WITHIN ACT CEILINGS TO BE CENTERED IN FULL TILE U.N.O

4

RCP - 11B - LEVEL 5 SCALE: 1/8" = 1'-0"

As indicated

DATE:

03/04/2021

DRAWN BY:

Stantec

CHECKED BY:

RNN Architects

DESIGN CONTRACT NO. VOLUME NAME: N

08/15/18 JC 10/19/18 JC 06/03/19 JC 06/01/20 RNN 07/06/20 RNN 07/20/20 RNN 08/19/20 RNN 09/03/20 09/23/20 10/16/20 10/30/20 11/25/20 01/19/21 02/02/21 02/11/21 2/18/21 02/25/21 RNN 03/04/21

201839412

ARCHITECTURAL

SHEET TITLE

RCP - LEVEL 5 PLAN 11B 11B

SHEET NO.

0 2 4

8

16

A5.1562 BIM FILE NO.

(585)-905-5651| bminster333@gmail.com

01.\


Turn static files into dynamic content formats.

Create a flipbook
WorkSamples_Blake_Minster by Blake Minster - Issuu