Contents Introduction Reference Glossary Important Information for Employers Entry Requirements
Assessment Options NQual Approach Approved Centre Approach
2 2 4 5 5 5 6
Assessment Design
7
Mandatory Component
7 7
Project
Additional Component Professional Discussion
9 9
Assessment Materials
10
Apprentice Assessment Timelines
11
Assessment Assessor Requirements
12 12 12
Assessor Requirements IQA Requirements
Component Mapping Table
13
Grading Descriptors
17 17 19
Mandatory Component: Project Additional Component: Professional Discussion
Grading and Standard Setting
21
Gateway to Completion
21
Behaviours
22
Certification
22
NQual Details
22
1 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
Introduction This Apprenticeship Specification provides the requirements, advice, and guidance for the assessment of the NQual Level 4 Apprenticeship Assessment for Associate Project Manager (ST0310). It outlines the assessment components, timelines, and expectations for apprentices, employers, and training providers, and is structured to cover all relevant aspects of the assessment process. The information in this Specification is based on the Skills England Apprenticeship Assessment Plan for the Associate Project Manager Level 4 (ST0310) Apprenticeship. For reference, you can access the official document: Associate Project Manager L4 Assessment Plan | Skills England. Associate Project Managers contribute to the successful delivery of a project, ensuring its scope and benefits are achieved as planned, by identifying, resourcing, scheduling and monitoring project activities. They work within the limits set by a Project Manager, applying governance, risk, quality and stakeholder management principles across the project lifecycle. The apprenticeship typically takes 18 months.
Reference Glossary Below is a reference glossary of the new Skills England terminology, with a brief explanation of what each term means. You might want to refer to this table when using this document. New Term / Process
Apprenticeship Specification
What it Replaces
New Concept
What it Means NQual designs Apprenticeship Specifications to support employers, apprentices and training providers in their delivery of Apprenticeship Standards. This document also outlines the assessment requirements in full. Both terms refer to the organisation that delivers the on-programme training for an apprentice.
Training Provider / Approved Centre
New Concept
Approved Centre refers to those who have undergone additional quality and compliance checks with NQual and are approved to undertake assessments on NQual’s behalf, as per the CASS strategy. Training Provider refers to those who have not undergone additional quality and compliance checks with NQual and are not approved to undertake assessments on NQual’s behalf.
Gateway to Completion
Gateway
Final checkpoint before an apprenticeship certificate can be requested. Confirms the apprentice has met all completion requirements (English & maths and employer-verified behaviours).
2 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
NQual Assessment of Behaviours
Employers confirm the apprentice has sufficiently demonstrated the behaviours in the occupational standard. NQual no longer assesses behaviours. NQual requires behaviours to be confirmed as achieved prior to finalising ‘Gateway to Completion’.
Apprenticeship Assessment Plan (AAP)
End-Point Assessment Plan
The document sets out how a specific apprenticeship is assessed: assessment outcomes, assessment requirements/Component, and performance descriptors. NQual is required to use the Apprenticeship Assessment Plan (AAP) to design its Apprenticeship Specification.
Assessment Organisation (AO)
End-Point Assessment Organisation (EPAO)
The organisation responsible for designing, quality assuring and (where applicable) delivering the apprenticeship assessment. NQual is the Assessment Organisation.
New Concept
Broad statements that group knowledge and skills to describe how an apprentice demonstrates occupational competence. Each knowledge/skill statement maps to an outcome; all outcomes must be fully assessed in every version.
New Concept
Describe the level of performance needed for a pass or distinction. They bridge assessment outcomes and NQual’s grading approach and support comparability; apprentices are not marked directly against them. Performance Descriptors are set by Skills England and prescribed for each level.
New Concept
The subset of content in an AAP (shown in bold) that must be assessed in every version of the assessment. Other statements must still be assessed but can be covered over time.
New Concept
A structured approach allowing NQual to assess across the full range of nonmandatory content over time, rather than every statement in every assessment version.
Centre Handbook
A document specifically for Approved Centres undertaking apprenticeship assessment on behalf of NQual, outlining key policies and processes to support success.
New Concept
Featured in the AAP. The single assessment method that must appear in every version of an assessment. NQual may add optional Components from the set list in the AAP.
Employer Verification of Behaviours
Assessment Outcomes
Performance Descriptors
Mandatory Knowledge and Skills Statements
Sampling
Centre Handbook
Mandatory Assessment Method
3 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
Mandatory Qualification (MQ)
Mandated Qualification
An additional qualification required for completion (for legal, professional-body or sector requirements). This standard has no mandatory qualification.
Pass / Distinction
Pass / Merit / Distinction
The standard grades under reform. Merit has been removed to improve consistency and fairness across apprenticeships. Resit = resitting without further training
Resits and Retakes
Same Concept
Retake = further training, then reassessment. Apprentices can choose to resit/retake to achieve a higher grade.
IfATE / Institute for Apprenticeships and Technical Education
Skills England
The body now responsible for occupational standards and apprenticeship assessment plans, working with DfE, Ofqual and OfS.
Important Information for Employers The Associate Project Manager apprenticeship assessment has been updated as part of national assessment reform led by Skills England. These changes are designed to reduce duplication and ensure assessments reflect occupational competence.
Key changes include: •
Assessment timing can be flexible and based on apprentice readiness, and the ‘Gateway Period’ has been replaced by the ‘Gateway to Completion’ process. Apprentices can now complete some or all of their assessments on programme; at least one assessment should be towards the end of the programme.
•
Employers are responsible for verifying that apprentices have sufficiently demonstrated the behaviours set out in the occupational standard before ‘Gateway to Completion’.
•
Assessment Organisations (AO) and Training Providers (TP) are no longer required to assess behaviours themselves. This ensures behavioural judgements are made by those with direct workplace insight and supports a more streamlined and appropriate assessment approach.
Gateway to Completion will take place once the apprentice has: •
Passed both assessment components.
•
Had completion of the behaviours verified by the employer.
•
Achieved any maths and English qualifications required in line with the apprenticeship funding rules and employer requirements.
4 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
Entry Requirements •
Minimum age: 16 years old.
•
Apprentices must be employed in a relevant associate project management role for the duration of the programme, with sufficient opportunity to develop and evidence the knowledge and skills set out in the standard.
•
Employers and training providers may set additional entry requirements appropriate to the role. English and maths must be completed in line with the apprenticeship funding rules.
Assessment Options NQual offers two options for Apprenticeship Assessment: •
The NQual Approach.
•
The Approved Centre Approach.
The NQual Approach If providers choose this option, NQual will complete all assessment components.
Registration Apprentices must be registered on ACE360 at least 90 days before their first assessment. Assessments can take place on the programme in any order. Training Providers are required to complete the NQual Booking Form, confirming that the apprentice, provider and employer agree that the apprentice is ready to complete the assessments. Booking forms must be submitted via ACE360 at least 2 weeks prior to the requested assessment date for all components. Where booking forms are not completed within the timelines, preferred dates might not be accommodated.
Results Results will be sent to the apprentice and the training provider and uploaded onto ACE360 within 10 working days after the completion of each component. Following completion of all assessment components, centres must submit Gateway to Completion evidence in line with the requirements set out in the Gateway to Completion section of this document. NQual will confirm completion within 48 working hours of all evidence being uploaded.
Resits and Retakes For standards comprising multiple assessment components, apprentices will only be required to resit or retake the component(s) in which they have been unsuccessful. Apprentices may also choose to resit an assessment component with the aim of improving their grade; however, an increased grade cannot be guaranteed.
5 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
There is no formal cap on the number of resits and retakes, and the grade achievable is not restricted through reassessment attempts. However, it is strongly recommended that the apprentice is adequately prepared prior to reassessment to minimise repeated attempts. NQual’s approach to resits and retakes will not limit an apprentice’s ability to achieve a distinction grade or place a cap on the grade an apprentice can achieve. All resits and retakes must be completed within 12 months of the initial fail notification. Each resit or retake is subject to employer agreement and confirmation of apprentice readiness prior to booking.
The Approved Centre Approach If providers choose this option, the additional component of the assessment can be undertaken by the approved centre. These components are carried out in line with NQual’s CASS strategy and are subject to ongoing External Quality Assurance (EQA). The mandatory Project continues to be delivered by NQual. Centres wanting to use this approach must undergo NQual’s Centre Approval process prior to registering and undertaking any form of assessment of any apprentices. If you would like to become an NQual Approved Centre, please contact admin@nqual.co.uk for our NQual Centre Approval Process Guide. Centres must declare conflicts of interest in advance, and apprentice tutors/assessors must not undertake formal assessments. When choosing this approach, all assessors and internal quality assurers (IQA) details must be recorded by NQual and are subject to EQA review to ensure competence. Please see ‘Assessment Assessor and IQA Requirements’ in this document. Assessors conducting apprenticeship assessments on behalf of NQual are subject to initial standardisation and the completion of an ‘Assessor Declaration’.
Registration Apprentices must be registered on ACE360 at the start of the programme, within 60 days of the start date, and will be subject to ongoing EQA activity. For the additional component delivered by the Centre, NQual must be notified of the assessment date and time at least 2 weeks in advance, by completing the NQual Booking Form, which must be uploaded to ACE360. When the apprentice is ready to be assessed by NQual for the Project, the Centre must complete the NQual Booking Form, confirming that the apprentice, employer and Centre agree that the apprentice is assessment ready. NQual will then schedule and assess the Project in accordance with the selected delivery method.
Results All results remain subject to confirmation through NQual’s External Quality Assurance process. For the NQual-assessed component, results will be sent to the apprentice and the training provider and uploaded onto ACE360 within 10 working days after completion. Results from the additional component, completed by the centre, will be subject to additional external quality assurance, and results will be confirmed within 10 working days. Following completion of all assessment components, centres must submit Gateway to Completion evidence in line with the requirements set out in the Gateway to Completion section of this document. NQual will confirm completion within 48 working hours of all evidence being uploaded.
6 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
Resits and Retakes NQual must be informed of booked resits and retakes via the NQual Booking Form, uploaded to ACE360. For standards comprising multiple assessment components, apprentices will only be required to resit or retake the component(s) in which they have been unsuccessful. Apprentices may also choose to resit an assessment component with the aim of improving their grade; however, an increased grade cannot be guaranteed. There is no formal cap on the number of resits and retakes, and the grade achievable is not restricted through reassessment attempts. However, it is strongly recommended that the apprentice is adequately prepared prior to reassessment to minimise repeated attempts. NQual’s approach to resits and retakes will not limit an apprentice’s ability to achieve a distinction grade or place a cap on the grade an apprentice can achieve. All resits and retakes must be completed within 12 months of the initial fail notification. Each resit or retake is subject to employer agreement and confirmation of apprentice readiness prior to booking.
Assessment Design The Level 4 Apprenticeship for Associate Project Manager requires the completion of two assessment components. This standard comprises one mandatory component and one additional component. The mandatory component for this apprenticeship standard is a Project. For this standard, it has been outlined that the mandatory component must be completed by NQual. The apprentice must additionally complete a Professional Discussion to complete their apprenticeship.
Mandatory Component Project The Project requires the apprentice to plan, monitor and report on an element of a live project within their workplace, contributing to its scope, planning, control and successful delivery. The Project can be assessed via either a presentation or a written submission. At the point of booking the apprentice will be given a project brief showing the mandatory grading descriptors for the project, along with additional sampled criteria to be included. The apprentice can choose to deliver their project as either a Presentation with Q&A or a Written Project Report. The apprentice can only choose one delivery method for their project.
Delivered as a Presentation with Q&A If the apprentice decides to deliver their project as a Presentation, they should review this section.
7 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
The Presentation requires the apprentice to present the approach, analysis, findings and recommendations from a real workplace project, using appropriate visual support. The Project component should take place after month 6. The Presentation is delivered live and remotely to a qualified Independent Assessor from NQual and is followed by a question-and-answer session. The apprentice must complete assessments independently; any referenced material must be cited appropriately, and outputs must not include plagiarism nor the unauthorised use of Artificial Intelligence. Please refer to NQual’s Malpractice and Maladministration Policy regarding the use of AI and plagiarism. The apprentice will complete the assessment in a controlled environment, ensuring they are alone in the room and free from any external influence, in accordance with the required assessment conditions. The assessment decision will be issued within 10 working days of the assessment date.
Timings The total time for the Presentation with Q&A is 40 minutes (+/- 10%), typically the Presentation will last 20 minutes (+/10%), followed by a question-and-answer session.
Delivered as a Written Project Report If the apprentice decides to deliver their project as a Written Project Report, they should review this section. The written submission must not exceed 4000 words. Any appendices can be submitted but will not be counted towards the word count. The written project submission should be submitted towards the end of the programme, typically after month 6. The apprentice will be responsible for demonstrating how they support the project management plan, contribute to scheduling, budgeting, risk, quality and stakeholder activity, and apply governance, procurement and continuous improvement principles within the limits of their role. Example Projects include, but are not limited to; •
Contributing to the development, maintenance or assurance of an integrated project management plan.
•
Preparing and monitoring a project schedule, including critical path analysis and resource allocation.
•
Monitoring and reporting on project budget forecast, spend and variance.
•
Identifying and managing project risks, issues and changes to support predictable delivery.
•
Supporting ethical and sustainable procurement or resource management activity.
•
Applying lessons learned and continuous improvement processes to enhance future project delivery.
The apprentice has a maximum of 16 weeks to complete their project. This includes 12 weeks to complete their project and gather evidence, and a further 4 weeks for the write-up. The suggested structure of the Written Project Report includes: •
Introduction and context: the project, its organisational alignment, and the apprentice's role and limits of responsibility
•
Planning and control: contribution to the project management plan, scope, scheduling, estimating and resourcing
8 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
•
Risk, issue, change and quality: approaches taken to identify, analyse and manage risks, issues, changes and quality requirements
•
Commercial and resource management: contribution to procurement, budget monitoring and resource management
•
Professional practice and improvement: application of legislation, ethics, sustainability and digital tools, and use of lessons learned
•
Reflection: what the apprentice would do differently and what this demonstrates about their professional development
Additional Consideration An Independent Assessor from NQual will conduct and mark this component after submission to NQual via ACE360. Details of all criteria covered in this component can be found in the Mapping Table within this document. The apprentice must complete the written submission independently. Any referenced material must be cited appropriately and must not include plagiarism nor the unauthorised use of Artificial Intelligence. Please refer to NQual’s Malpractice and Maladministration Policy regarding the use of AI and plagiarism.
Additional Component Professional Discussion The Professional Discussion requires the apprentice to demonstrate their understanding of project context, governance, stakeholder engagement, commercial control and regulatory/ethical practice in a structured conversation with an assessor, drawing on real examples from their own role. The Professional Discussion should take place after month 6.
The NQual Approach The Professional Discussion is a structured discussion conducted remotely by a qualified Independent Assessor from NQual. The apprentice will complete the assessment in a controlled environment, ensuring they are alone in the room and free from any external influence, in accordance with the required assessment conditions. Apprentices are permitted to bring the NQual approved ‘Self-Assessment Document’, which they can prepare in advance and bring to their assessment. This document must be submitted in advance to NQual along with the NQual Booking Form. Apprentices may also bring an additional notes page on the template provided by NQual. Details of specific criteria assessed in this component are provided in the Mapping Table within this document.
The Approved Centre Approach The Professional Discussion is a structured discussion conducted by an Independent Assessor from the approved Centre. The Centre can choose to conduct the assessment either face to face or remotely; a video/audio recording must be provided for either option for quality assurance purposes. 9 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
The recording alongside the provided NQual grading document must be uploaded to ACE360 within 10 working days of the completed assessment date. Once uploaded, the assessment decision will be externally quality assured by NQual within a further 10 working days. The apprentice must complete the assessment in a controlled environment, ensuring they are alone in the room and free from any external influence, in accordance with the required assessment conditions. Apprentices are permitted to bring the NQual approved ‘Self-Assessment Document’, which they can prepare in advance and bring to their assessment. This document must be submitted in advance to NQual along with the NQual Booking Form. Apprentices may also bring an additional notes page on the template provided by NQual. Details of specific criteria assessed in this component are provided in the Mapping Table within this document.
Timings This component must last 45 minutes (+/- 10%), from the point the apprentice is asked their first question.
Assessor Responsibilities Throughout the assessment, apprentices should not receive feedback. Assessors are responsible for ensuring assessment conditions are followed, and for completing and recording in full the Assessor Declaration. All assessments must be video/audio recorded in line with NQual’s Assessment Processes for quality and compliance purposes. If recordings are not received, NQual reserves the right to request a resit.
Assessment Materials The required assessment materials, including assessment documentation and sample question banks, are available to Approved Centres and Training Providers. These materials support Centre preparation and assessor standardisation and should be reviewed before delivery commences. Materials are available via ACE360, with Approved Centre Assessment materials being shared directly with each Centre following standardisation and training. Please note that, to align with sampling requirements, regular review of Approved Centre Assessment materials will be completed by NQual’s Quality Team, which will result in assessment material updates and version changes. These will be communicated in advance, and a clear start date will be indicated on each. When apprentice bookings are confirmed, NQual will provide the relevant assessment materials. Centres must use the correct assessment materials; if outdated materials are used, NQual reserves the right to request a resit of assessments where it deems appropriate.
10 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
Apprentice Assessment Timelines Step
NQual Approach
Sign –Up
Registration
Apprentice signs up with their Training Provider / Centre. Apprentices registered on ACE360 at least 90 days before the first assessment.
Learning
Booking Assessments
Assessments
Results
Approved Centre Approach
Apprentices registered on ACE360 within 60 days of their ‘sign-up’ date. This must be before apprentices complete any assessments.
On-programme learning. Training Providers must complete the NQual Booking Form at least 2 weeks prior to each component: the mandatory Project and the additional Professional Discussion.
Centres must inform NQual using the NQual Booking Form at least 2 weeks before the Professional Discussion and before conducting the optional component (Project).
Assessments are conducted by NQual Independent Assessors.
NQual will mark the Project written submission or the Presentation with Q&A.
NQual will assess the mandatory Project, either as a Written Project Report or as a Presentation with Q&A, depending on the delivery method selected.
Independent Assessors from the Centre will conduct the Additional Component (Professional Discussion).
Results of the component conducted by NQual will be sent out a maximum of 10 working days after each assessment component.
Results of the component conducted by NQual will be sent within 10 working days after completion.
If an apprentice fails an assessment method, they must book a resit or retake using the NQual booking form.
Centres submit their evidence using NQual's required paperwork and recordings within 10 working days of the completed assessment.
Final confirmed results of centreassessed components will be issued by NQual following completion of the EQA process within 10 working days of confirmed uploaded evidence.
The Training Provider / Centre provides evidence of: Gateway to Completion
• • •
Both components achieving Pass or Distinction Maths & English evidence Employer-verified behaviours.
NQual confirms Gateway to Completion. Certification
NQual applies for the apprenticeship certificate
11 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
Assessment Assessor Requirements Assessment Assessor and IQA requirements remain the same regardless of the option chosen.
Assessor Requirements •
Assessors must hold a relevant assessor qualification, such as the Level 3 Certificate in Assessing Vocational Achievement (CAVA). Assessors currently undergoing training must have all assessment decisions confirmed by a suitably qualified assessor.
•
Assessors must also be occupationally competent to assess the standard, typically demonstrated by at least two years of recent experience in project management or a comparable environment, supported by a regularly updated CPD record. This should evidence current, practical experience and knowledge of project management to ensure valid assessment decisions.
•
Assessors must be qualified in the subject at the same level or above the standard they are assessing.
•
Conflict of Interest: Assessors must declare any personal or professional relationship, or any potential benefit from the assessment outcome.
•
Independence: The assessor must be independent from the apprentice to ensure impartiality and integrity in the assessment process.
IQA Requirements •
IQAs must hold a relevant IQA qualification, such as the Level 4 Award in the Internal Quality Assurance of Assessment Processes and Practice. IQAs currently undergoing training must have all assessment decisions confirmed by a suitably qualified IQA.
•
IQAs must also be occupationally competent in the sector area, typically demonstrated by recent and relevant experience, supported by an up-to-date CPD record evidencing current knowledge of industry standards and assessment practices.
•
IQAs must be qualified in the subject at the same level or above the standard they are assessing.
•
Conflict of Interest: IQAs must declare any personal or professional relationship, or any potential benefit from the sampling process, before carrying out quality assurance activities.
•
Independence: The IQA must be independent from the apprentice and assessor, to ensure impartiality and integrity in the quality assurance process.
12 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
Component Mapping Table The table below maps each knowledge (K) and skill (S) statement to the component in which it is assessed. Knowledge and Skills statements marked with an asterisk (*) identify Skills England mandatory criteria and must be assessed in every version of the assessment.
Assessment Outcome
What is Required
Project
Professional Discussion
AO1: Project Context, Governance, and Organisational Alignment Understands how projects operate within organisational, programme, and portfolio environments and applies governance frameworks, roles, and structures to ensure project activity aligns with strategic objectives and delivers intended benefits. K2*
The importance of alignment between the project and organisational objectives.
K4
Techniques used to understand the project context, such as PESTLE (political, economic, social, technological, legal, and environmental), SWOT (strength, weakness, opportunities, threats) or VUCA (velocity, uncertainty, complexity, ambiguity).
K5*
The need and benefit of the project governance structure, requirements, and process and the impact on their role.
K10
Approaches to the maintenance of a business case and the management of the benefits which will be achieved upon the successful delivery of the project.
K26*
Principles for evaluating project success, including how lessons learned are captured and can impact future project delivery.
S9*
Review and provide feedback on a project business case to ensure the project remains valid.
K1*
The differences between projects and business as usual.
K3*
The interdependencies between project, programme, and portfolio management.
K6
The differences and comparative benefits between functional, matrix and project structures.
K7*
Different roles and responsibilities within a project environment.
K8*
The differences and comparative benefits between linear, iterative and hybrid life cycle approaches.
K9*
Importance, content, and purpose of a business case.
13 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
S20
Provide underpinning data to support the written submission through the governance process.
AO2: Stakeholder Engagement and Collaborative Working Identifies, engages, and communicates with stakeholders and project teams, adapting communication approaches, supporting the project vision, and managing collaboration, negotiation, and conflict within agreed limits of responsibility.
K14
Communication techniques and approaches to interact with stakeholders to meet their requirements.
S3
Influence and negotiate with others to create a positive outcome for the project.
S6
Communicate and support the project vision, to ensure buy in to the project objectives.
S7
Collate and analyse information and provide input to support negotiations relating to project objectives.
S18*
Work with stakeholders to deliver the project.
K13*
The identification, analysis, and management of stakeholders.
K16
Techniques for managing conflict and negotiation.
K17*
Techniques for working collaboratively within a team and with stakeholders.
K31
Presentation tools and techniques.
S2*
Manage and engage with stakeholders.
S4
Resolve conflict as and when required with stakeholders within limits of responsibility.
S5
Adapt communications to different stakeholders.
AO3: Project Scope, Planning, Scheduling, and Control Contributes to the development, maintenance, and assurance of integrated project management plans, using estimating, scheduling, budgeting, and performance monitoring techniques to support effective control of time, cost, scope, and resources. K11*
The purpose, format, and significance of the project management plan.
K12*
Methods used to define, record, integrate, deliver, and manage scope.
14 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
K18
How and when to apply different estimating methods.
K21*
Project scheduling and maintenance, including critical path analysis.
S1*
Use project monitoring and reporting techniques to track, interpret and report on performance.
S11*
Evaluate an integrated project management plan to provide recommendations on areas for improvement.
S12*
Prepare, monitor, and schedule activities that contribute to the delivery of the overall project schedule and objectives.
S25
Use configuration management and change control to schedule and maintain projects.
K20
The principles of earned value management (EVM) and the interpretation of EVM information.
S22
Ensure that integrated schedules support critical path analysis, interface management, resource forecasting and risk management.
AO4: Risk, Issue, Change, and Quality Management Applies structured approaches to identifying, analysing, and managing risks, issues, changes, and quality requirements, using appropriate controls, data, and assurance activities to support predictable project delivery. K19
K19: Configuration management and change control.
S10*
S10*: Apply change control processes to support the management of project scope.
S14*
S14*: Identify and monitor project risks and issues; and plan and implement responses to them.
S24
S24: Use data to inform decisions on actions to take to mitigate risks on project.
K23*
K23*: Principles of project risk and issue management.
K25*
K25* The role and purpose of quality requirements, planning and control in a project environment.
S13*
S13*: Evaluate and make recommendations on the risk management plan to threats to delivery and recommend solutions.
S15*
S15*: Deliver a Quality Management Plan which contributes to quality control processes.
15 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
AO5: Commercial Awareness, Resource, and Financial Management Supports ethical and sustainable procurement, resource management, and financial control activities throughout the project lifecycle, working within approved budgets and contributing data and analysis to inform commercial and governance decisions. K24
Procurement strategies and processes that are both ethical and sustainable.
S8*
Monitor and analyse project budgets.
S17
Support the preparation or maintenance of a resource management plan for project activities.
S21
Work within the approved project budget.
S26*
Manages resources through the project lifecycle.
K22
Allocation and management of resources throughout the project life cycle.
AO6: Professional Practice, Compliance, Sustainability, and Continuous Improvement Applies legislation, regulation, ethical and inclusive practices, sustainability principles, digital tools, and information management to their project role, using lessons learned and continual improvement processes to enhance future project delivery.
K28
The impact of project objectives and how to respond to challenges around sustainability and the UK Government's policy to achieve net carbon zero.
K29*
Principles of conducting project management activities which are ethical and inclusive.
K30
Technology and software used in the performance of project management activities.
S16*
Use an organisation's continual improvement process including lessons learned to improve performance.
S19
Use digital tools and software to meet project objectives for example research, collaboration, presentations, and resolution of problems.
K15
The use of information management.
K27*
Relevant regulations and legislation such as data protection, and how they impact on their role.
S23*
Apply relevant legislation, regulations, codes of practice, and ethical guidance where appropriate to their work.
16 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
Grading Descriptors Each assessment outcome is graded against the Pass and Distinction descriptors below, expressed across the six Skills England performance categories (applied knowledge, applied skills, regulatory and procedural awareness, communication and collaboration, information use and decision making, and responsibility and autonomy) at a level appropriate to Level 4. In the tables below Knowledge and Skills marked with an asterisk (*) identify mandatory criteria as per the assessment plan plus any additional criteria deemed mandatory by NQual to meet the Assessment Outcome.
Mandatory Component: Project (Presentation with Q&A/Written Project Report) Assessment Outcomes AO1: Project Context, Governance and Organisational Alignment
Pass Descriptors Applies knowledge of how the project aligns with organisational objectives, of the project governance structure and its impact on their role, and of how project success and lessons learned are evaluated, using suitable techniques to understand the project context. (K2*, K5*, K26*) Reviews the project business case and provides feedback, using relevant information to judge whether the project remains valid, including how the expected benefits will be realised. (S9*)
AO2: Stakeholder Engagement and Collaborative Working
Works with stakeholders to deliver the project, communicating clearly and supporting shared objectives within the limits of the role, and using suitable communication and negotiation approaches to secure buy-in. (S18*)
Distinction Descriptors Applies this knowledge with confidence and precision, producing high-quality work that strengthens how the project's alignment, governance and lessons learned inform delivery. (K2*, K5*, K26*) Evaluates business case information from a range of sources, giving well-justified feedback that shows strong awareness of the wider implications for the project. (S9*)
Works with stakeholders with confidence and insight, tailoring the approach to different stakeholders needs to improve collaboration and support delivery in more complex situations. (S18*)
17 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
AO3: Project Scope, Planning, Scheduling and Control
Applies knowledge of the purpose and format of the project management plan and of the methods used to define, record and manage scope, to support effective control of scope. (K11*, K12*) Uses scheduling (including critical path analysis), monitoring and reporting techniques to prepare and schedule activities, track and report performance, and evaluate the project management plan to recommend improvements, choosing appropriate estimating methods and applying change control as needed. (K21*, S1*, S11*, S12*)
Applies plan and scope knowledge with precision, producing high-quality work that improves how scope is controlled. (K11*, K12*) Applies scheduling, monitoring and evaluation skills with flexibility and fluency, producing well-evidenced recommendations that improve control of time, cost, scope and resources. (K21*, S1*, S11*, S12*)
AO4: Risk, Issue, Change and Quality Management
Applies change control processes and identifies, monitors and responds to project risks and issues, using data to inform decisions that support predictable delivery. (S10*, S14 *)
Applies change control and risk management with flexibility and fluency, producing well-evidenced, datainformed responses that keep delivery on track in more complex situations. (S10*, S14*)
AO5: Commercial Awareness, Resource and Financial Management
Manages resources across the project lifecycle, using relevant project information to allocate, monitor and adjust resources to support project objectives, demonstrating awareness of the occupational context and the wider associate project management role. (S26*)
Analyses and interprets relevant project information to make well-informed decisions when managing resources throughout the project lifecycle, demonstrating proactive awareness of the occupational context and the wider associate project management role. (S26*)
AO6: Professional Practice, Compliance, Sustainability and Continuous Improvement
Applies knowledge of ethical and inclusive project management, and of sustainability challenges including net carbon zero, to their project role. (K29*)
Applies ethical, inclusive and sustainability knowledge with confidence, producing work that strengthens responsible delivery. (K29*)
Uses the organisation's continual improvement process, including lessons learned, and appropriate digital tools and software, to improve project delivery. (S16* )
Uses continual improvement and digital tools with fluency, producing well-evidenced improvements to future delivery. (S16*)
18 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
Additional Component: Professional Discussion Assessment Outcomes
Pass Descriptors
Distinction Descriptors
AO1: Project Context, Governance and Organisational Alignment
Explains the differences between projects and business as usual, the interdependencies between project, programme and portfolio management, the roles and responsibilities in a project environment, the differences and benefits of linear, iterative and hybrid life cycles, and the importance, content and purpose of a business case. (K1*,K3*, K7*, K8*, K9* )
Explains and connects this knowledge with confidence and precision, showing how the choice of structure, life cycle and governance affects delivery in their project context. (K1*,K3*, K7*, K8*, K9* )
AO2: Stakeholder Engagement and Collaborative Working
Explains how they work collaboratively within a team and with stakeholders, and how they manage and engage stakeholders, using suitable techniques for conflict management, negotiation and adapting communication. (K17*, S2* )
Explains these approaches with insight, showing how they tailor collaboration and communication to different stakeholders to improve outcomes. (K17*, S2*)
Demonstrates application of project management knowledge to identify, analyse and manage stakeholders, applying suitable methods to support stakeholder engagement. Communicates clearly and collaborates with stakeholders to support effective project delivery within agreed responsibilities. (K13*) AO4: Risk, Issue, Change and Quality Management
Applies stakeholder management knowledge with confidence and precision to identify, analyse and manage project stakeholders. Adapts and applies stakeholder engagement methods with a high degree of flexibility and operational fluency, communicating and collaborating effectively and adapting approaches to stakeholder needs to enhance project delivery outcomes. (K13*)
Explains the principles of project risk and issue management, and the role and purpose of quality requirements, planning and control. (K23*, K25* )
Explains risk and quality principles with confidence, showing how they support predictable delivery. (K23*, K25*)
Explains how they evaluate and make recommendations on the risk management plan, and how they deliver a Quality Management Plan that contributes to quality control. (S13*, S15* )
Explains their risk and quality recommendations with insight and fluency, showing how they improve control in more complex situations. (S13*, S15*)
19 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
AO5: Commercial Awareness, Resource and Financial Management
Explains how they monitor and analyse project budgets to inform commercial and governance decisions. (S8*)
Evaluates budget and commercial information from a range of sources, giving well-justified decisions that show awareness of wider commercial implications. (S8*)
AO6: Professional Practice, Compliance, Sustainability and Continuous Improvement
Explains the relevant regulations and legislation, such as data protection, and how they impact the role, and how they apply legislation, regulations, codes of practice and ethical guidance in their work. (K27*, S23* )
Interprets and applies regulatory and ethical requirements with insight, identifying implications and making informed decisions in more complex situations. (K27*, S23*)
20 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
Grading and Standard Setting The available grades for this standard are Fail, Pass and Distinction. All assessment outcomes must be demonstrated to the level described in the grade descriptors in both assessment components to achieve an overall Pass grade. To be considered for an overall Distinction, the apprentice must first meet all assessment outcomes at the pass standard in both assessment components. A Distinction will then be awarded where the apprentice achieves a minimum of 50% of the available distinction criteria in each assessment component. The final grade will be decided on the following combinations: Mandatory Component:
Additional Component:
Project
Professional Discussion
Any grade
Fail
Fail
Fail
Any grade
Fail
Pass
Pass
Pass
Pass
Distinction
Pass
Distinction
Pass
Pass
Distinction
Distinction
Distinction
Overall Grading
Gateway to Completion Gateway to Completion is the last part of the apprentice’s journey and requires the training provider/centre to upload evidence that the apprentice is ready to complete their apprenticeship. The Gateway to Completion form must be completed and submitted to NQual, along with the required evidence, via ACE360. Requirements for Gateway to Completion: •
Both components have achieved a minimum of a pass grade.
•
Evidence of achieving relevant maths and English qualifications or exemptions where required, in line with the apprenticeship funding rules.
•
Confirmation that the employer deems the apprentice competent against the required behaviours.
21 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02
Associate Project Manager Level 4
Behaviours As part of this apprenticeship standard, it is the responsibility of the employer to review behaviours throughout the apprentice’s programme and confirm sufficient demonstration of these behaviours before a certificate can be requested. Below is a list of behaviours the employer is required to confirm for this standard. Behaviours B1
Works flexibly and adapts to circumstances.
B2
Works collaboratively and builds strong relationships with others across the organisation and external stakeholders.
B3
Has accountability and ownership of their tasks and workload.
B4
Operates professionally with integrity and confidentiality.
B5
Seeks learning opportunities and continuous professional development.
Certification For this apprenticeship standard, NQual is responsible for requesting the apprentice's certificate once Gateway to Completion has been confirmed.
NQual Details To find out further information or discuss anything within this Apprenticeship Specification, please reach out to a member of the team: admin@nqual.co.uk.
22 Apprenticeship Specification: Associate Project Manager Level 4 (V2.0) Property of NQual Ltd | Document Version: APM4-SPE-02