DURATION 10 Months 5 BUILDINGS
With VIVO Defence we successfully completed fire safety works at the Dorset & Wiltshire Fire and Rescue training facility in West Moors.
We worked across five buildings, (four unoccupied, one partially occupied).
To minimise disruption to the building users, we strategically phased the work, carefully managing all activities in the occupied building.
In addition to replacing the fire door sets and installing penetrations seals and emergency lighting, our Refurbishment and M&E works updated the facility’s appearance and increased/ enhanced its safety, energy efficiency, comfort and compliance. CONTRACT VALUE £1.8M
Replacement of fire door sets
Penetration seal
Emergency lighting
Redecoration
Removal and replacement of heating pipes
Removal and replacement of carpets
During the project, changes to the original scope of work required additional after the initial ones had been placed. Working closely with the client, we adapted our approach to accommodate efficiently, ensuring seamless progress and the successful completion of the fire door installations.
Our flexible and proactive approach helped maintain project momentum while meeting the client’s requirements.
The MOD properties have improved passive fire safety
Heating and pipework replacements ensure future safety
Carpet replacements and redecoration modernise the properties
VIVO Defence Services oversee facilities management and service family accommodation for the MOD (Ministry of Defence).
We have an established relationship with VIVO Defence Services, having successfully completed similar works for them at Marchwood Military Port near Southampton between 2022 and 2023.
We also partnered with the client on EWI (external wall insulation) works to 62 MOD properties at Southwick, Portsmouth.