Skip to main content

CLC Case Study - North Cheshire and Mersey NHS Foundation Trust - NHS Halton General Hospital

Page 1


View the Case Study & Video

North Cheshire and Mersey NHS Foundation Trust

PHARMACY ASEPTIC SUITE TRANSFORMATION

Project Details

In just 16 weeks, CLC successfully delivered a highly specialised pharmaceutical cleanroom fit-out at Halton Hospital, transforming a former pharmacy storage and delivery area into a fully operational aseptic compounding suite.

Working closely with the Trust’s Estates and Pharmacy teams as part of a wider NHS capital projects programme, the project enables the hospital to prepare aseptic injectable medicines, including chemotherapy and intravenous nutrition, directly on site.

“

Axis CLC are working closely with the Trust Estates and Pharmacy teams on delivering this project as part of the Trust’s capital programme. This facility is vital in allowing us to manufacture aseptic drugs on site, improving efficiency, reducing costs, and enhancing patient care through faster, tailored treatments.

Head of Capital Projects

“

Highlights

The programme began with a full strip-out, followed by first fix mechanical and electrical installations, installation of specialist hygienic wall systems, and completed with second fix M&E and commissioning. The result is a fully compliant, GMP-aligned cleanroom environment. GMP (Good Manufacturing Practice) refers to a system of regulations that ensures medicines are consistently produced and controlled to the highest quality and safety standards, minimising risks such as contamination, errors, and inconsistencies in pharmaceutical manufacturing.

This cleanroom construction project required the integration of advanced HVAC systems, delivering tightly controlled air quality, filtration, and pressurisation. The facility includes multiple interlocked rooms with varying classifications, from unclassified corridors through to Grade D and Grade C cleanrooms, with Grade C providing the highest level of sterility within the suite. A key feature of the project is the installation of fully sealed, pressure-controlled environments, ensuring contamination control and regulatory compliance for sterile pharmaceutical production. Staff must pass through a series of airlock and

gowning rooms, maintaining strict cleanliness protocols before entering critical areas. With approximately 30 professionals involved across client and contractor teams, the project demonstrates CLC’s specialist healthcare construction expertise, particularly in aseptic facility design and build, controlled environments, and turnkey cleanroom solutions.

Communication & Care

As a live hospital environment, maintaining operational continuity was critical. We worked collaboratively with hospital stakeholders to minimise disruption to clinical services and patient care. Close coordination with Estates and Pharmacy teams ensured clear communication throughout all phases of the programme, including scheduling of high-impact works, access planning, and adherence to strict healthcare compliance and infection control protocols. Our team operated within a vacant pharmacy storage and deliveries area, applying best practices in site safety, infection prevention, and stakeholder engagement, ensuring seamless integration of construction activities within the hospital setting.

NORTH CHESHIRE AND MERSEY NHS FOUNDATION TRUST

Specifications

Full strip-out of former pharmacy intake and storage area

Design and construction of aseptic cleanroom facility

Installation of floor-to-ceiling welded hygienic wall systems (Gemclad)

Specialist mechanical and electrical (M&E) installations

Air handling systems with controlled pressure regimes

Cleanroom validation (Grade C and Grade D environments)

Airlock and gowning room construction

First and second fix M&E works

Specialist flooring and sterile finishes

Commissioning of aseptic suite for oncology drug preparation

Client Benefits

On-Site Aseptic Manufacturing

Enables the preparation of oncology treatments directly within the hospital.

Reduced Supply Chain Dependency

Minimises reliance on external pharmaceutical providers for critical medications.

Cost Efficiency

Delivers significant long-term savings through inhouse drug production.

Faster Treatment Turnaround

Supports rapid preparation of patient-specific medications when needed.

Client Relationship

CLC was appointed via a framework mini-competition tender process, demonstrating its capability in delivering specialist healthcare construction and refurbishment projects.

This project highlights our expertise in pharmaceutical environments, NHS infrastructure, and complex M&E installations, as well as its ability to collaborate effectively with multidisciplinary teams.

By working in partnership with the Trust’s Estates and Pharmacy departments, CLC ensured the successful delivery of a technically complex facility that will provide long-term value to both the hospital and its patients.

Improved Patient Care

Facilitates just-in-time delivery of treatments, enhancing patient experience and outcomes.

Operational Efficiency

Streamlines pharmacy processes and improves overall Trust performance.

Regulatory Compliance

Meets stringent cleanroom standards, GMP requirements, and healthcare regulations.

Future-Ready Facility

Provides a scalable solution to support increasing clinical demand and service expansion.

Turn static files into dynamic content formats.

Create a flipbook
CLC Case Study - North Cheshire and Mersey NHS Foundation Trust - NHS Halton General Hospital by Axis CLC - Issuu