Construction Update - March 2021

Page 1

ALAMO HEIGHTS ISD B O N D U P DAT E

MARCH 2021


Alamo Heights Natatorium Swimmers are swimming! Divers are diving! Solar panels are reinstalled along north fence line.


High School | Athletics Complex Press Box construction continues Grandstands are up and reserved seating is installed Brick work continues Gymnasium Ceiling Deck and Structure are painted Hard ceilings are being installed in showers and restrooms Weight Room ceilings are being installed


Coaches Offices are framed, sheetrock is installed and glazing is installed Sky Gym work continues Dance Gym ceiling is being installed Running track ceiling installation is about to commence