Client Website Handover & Launch-Day Runbook for Web Agencies

Page 1

P R E - L AU N C H Q A F O R W E B A G E N C I E S · 2 0 2 6 E D I T I O N

Client Website Handover & LaunchDay Runbook Who does what, in what order, from five days before go-live to thirty days after. It covers the go/no-go call, the cutover, the rollback plan and the handover pack your client keeps. For web agencies of roughly 3–20 people shipping client sites on WordPress, Webflow, Shopify, Squarespace, Wix or a custom stack.

Péter Kiss · Launch Ready · November 2026 · Free to share and adapt (CC BY 4.0) · uselaunchready.com


WHY A RUNBOOK

A checklist tells you what to check. A runbook tells you who does it, and when. Most launch-day problems don't come from a check nobody knew about. They come from a check that everyone assumed somebody else did: the form recipient that stayed on the developer's inbox, the DNS login nobody could find, the client who announced the launch before the redirects were on. This runbook puts a name and a time next to each step. Copy it into your project template and adjust it to your own stack.

How to use it

Pick the launch date and the launch owner first. Everything else hangs off those two. Work backwards from T-0. T-5 means five working days before go-live. Keep an evidence log. One line per step: who, when, result, link or screenshot. Hand the log over. It becomes the "what we checked" part of the handover pack. For the item-by-item QA checks themselves, use your own launch checklist (or the free "Website Launch QA Checklist for Web Agencies").

Client Website Handover & Launch-Day Runbook

uselaunchready.com · 2 / 10


ROLES

Five roles, one name each. One person can hold two, never all five. Role

Owns

On launch day

Launch owner

The runbook, the evidence log, the go/no-go call and the rollback call.

Runs the cutover clock. Doesn't do the fixes, so they can keep the overview.

Developer

Production configuration, DNS and hosting changes, redirects, fixes.

Does the cutover steps and reports each one back to the launch owner.

Second checker

An independent smoke test on the live domain.

Someone who didn't build the site. Fresh eyes find the "Hello world!" post.

Account / project manager

Client communication, sign-off, the handover pack.

Sends the "we're starting" and "it's live" messages. Nobody else talks to the client.

Client contact

Content approval, registrar/DNS access, receiving test form submissions.

Reachable during the launch window, and confirms the test enquiries arrived.

Write the five names at the top of the evidence log, with a phone number for each. Launch day is when you need them and it's too late to look them up.

Client Website Handover & Launch-Day Runbook

uselaunchready.com · 3 / 10


T- 5 T O T- 1

The five days before go-live T-5 · Access and inputs

Test every login you'll need on the day: registrar, DNS, hosting, CMS, analytics, tag manager, form/email service. Test them now, not at 09:00 on launch day. Agree the content freeze date with the client. Build the redirect map: old site's top URLs → new URLs. List every form and the inbox it must deliver to on production. T-4 · DNS preparation

Export or screenshot the current DNS zone. This is your rollback. Lower the TTL on the records you'll change, early enough that the old TTL has run out by launch.

Client Website Handover & Launch-Day Runbook

T-3 · Full staging QA pass

Run your full launch checklist (or a scan) on staging and sort the findings into the three severities on the next page. Open the client review window: they comment in your feedback tool, not by email. T-2 · Close the fix list

Fix every "Block launch" item. Re-check the ones you fixed. Take a full backup of the old live site (files and database) and of staging. T-1 · Go/no-go call (15 minutes)

Launch owner, developer, account manager. Fill in the decision record. Send the client the launch-window message (template on page 9).

uselaunchready.com · 4 / 10


T- 1 · G O / N O - G O

Three severities, one rule: any open blocker means "not yet" Block launch

Fix before handoff

Can wait

The client or their customers would be hurt on day one: site set to noindex, a form posting to staging, checkout or the main enquiry form not working, the wrong host serving the site, analytics missing on a campaign launch.

Visible, but not harmful on day one: missing meta descriptions, a missing share image, duplicate H1s, a placeholder in a footer link.

Improvements: image weight, alt text on decorative images, copy tweaks the client wants "after launch".

Rule: owner and date in the known-issues list, and fixed before you send the handover pack.

Rule: logged and agreed with the client, usually under the care plan.

Rule: fixed and re-checked before go-live.

Decision record (one per launch) Site · Date · Build/version · Attendees · Open "Block launch" items (must be 0) · Accepted known issues (owner + date each) · Rollback trigger agreed · Decision: GO / NOT YET · Signed: launch owner

Client Website Handover & Launch-Day Runbook

uselaunchready.com · 5 / 10


T- 0 · C U T OV E R

Launch-day sequence (example times, morning start) Time

Step

Who

09:00

Final backups. Post "starting" in the project channel. Account manager tells the client.

Dev · AM

09:10

Switch production settings: form recipients, SMTP, analytics and tag IDs, environment variables, staging password off, indexing on.

Dev

09:25

DNS change or domain connect. Wait for the certificate on both www and non-www.

Dev

Keep the old site running, untouched, for at least a week after launch.

09:45

Redirects on: one canonical host, http → https, old-URL map.

Dev

Who decides: the launch owner. The client is told, not asked, mid-incident.

10:00

Smoke test on the live domain (next page), by the developer and the second checker separately.

Dev · 2nd

10:30

Keep-live or roll-back decision, recorded in the log.

Launch owner

11:00

"It's live" message to the client.

AM

Client Website Handover & Launch-Day Runbook

Rollback plan (write it before T-0)

Trigger: agreed in advance, e.g. "homepage, checkout or main form not working, and no fix within 30 minutes". How: restore the DNS records you exported at T4, or re-point the domain to the old host.

Avoid starting after lunch on a Friday. You want the whole team around for the first few hours.

uselaunchready.com · 6 / 10


T- 0 · F I R S T H O U R

The 15-minute smoke test, split so two people don't check the same thing Developer

Second checker (on a phone)

1. Homepage has no noindex (meta tag and X-Robots-Tag header).

7. Submit every form once. The client contact confirms each one arrived.

2. robots.txt doesn't block the site; the sitemap loads and lists real pages only.

8. Tap the phone number, the email link and the map link.

3. www, non-www, http and https all end on the same page in one hop. 4. A made-up URL returns a real 404. 5. View source: search for the staging hostname. Expect zero hits. 6. Analytics real-time report shows your visit.

9. Click every header and footer link, including the legal pages. 10. Open three old-site URLs from the redirect map. 11. Paste the homepage into a social post composer (don't publish) and check the preview. 12. Read the homepage title and description as Google would show them.

Log each line with the result and a URL or screenshot. If any item 1–7 fails, it's a "Block launch" finding and the rollback clock starts.

Client Website Handover & Launch-Day Runbook

uselaunchready.com · 7 / 10


H A N D OV E R

The handover pack: what the client keeps 1 · Access and ownership

3 · What was checked

The client owns their accounts: registrar, DNS, hosting, CMS admin, analytics, Search Console, tag manager. You're added as a user.

The launch QA report: what was checked, when, by whom, and the result.

Access is shared through invites or the client's password manager, not in an email thread.

The redirect map.

Paid themes, plugins and services listed with renewal dates, and who pays for each. 2 · How the site works

A short "how to edit" guide or screen recordings for the tasks the client will actually do. The list of forms and where each one delivers, plus the integrations list.

Client Website Handover & Launch-Day Runbook

The known-issues list, with owner and date for each item.

4 · What happens next

Backup schedule and where backups are kept. Update and care-plan scope, and what's outside it. Support contact and the response times in your contract. 5 · Sign-off

A short acceptance note the client replies "approved" to. It closes the project.

uselaunchready.com · 8 / 10


C L I E N T M E SS A G E S

Two messages to copy into your templates T-1 · Launch window Hi [Name], Your new site goes live tomorrow between 09:00 and 11:00. During that window the site may briefly show the old version, or a security warning for a few minutes while the certificate is issued. That's normal. Please keep your phone nearby: we'll send two test enquiries through the contact form at about 10:00 and ask you to confirm they arrived. Please hold any announcement until we confirm it's live. [Account manager]

Client Website Handover & Launch-Day Runbook

T-0 · It's live, and what we checked Hi [Name], [site.com] is live. Before we called it done, we checked indexing, redirects from your old pages, every form, analytics, and how the site looks when it's shared on social media. Two small items are still open: [item, date] and [item, date]. We'll confirm when they're fixed. Your handover pack (logins, how-to guide, the launch report) follows by [date]. [Account manager]

uselaunchready.com · 9 / 10


A F T E R L AU N C H

T+1, T+7, T+30 T+1

T+7

T+30

Sitemap submitted in the client's Search Console (and Bing Webmaster Tools).

Search Console indexing report: unexpected "noindex" or "soft 404" pages?

Re-run the launch checks: content edits since launch bring old mistakes back.

Real visitors and conversions showing in analytics.

Redirects added for any real URLs in the 404 log.

Remove temporary access nobody needs any more.

404 and 500 errors in the server or uptime log.

First scheduled backup has run.

Short review call, and agree the care plan.

Staging password-protected or noindexed.

Known issues closed and the handover pack sent.

About this runbook Written by Péter Kiss, who builds Launch Ready, pre-launch QA for web agencies. Launch Ready runs deterministic, rule-based checks on a client's staging or live site and returns a Launch Readiness score, a prioritized list of blockers and a client-ready report. It runs in the browser, from CI, or from AI coding agents over MCP on every plan. People still make the launch decision. Free to share and adapt under CC BY 4.0. A practical aid, not a legal, accessibility or security audit.

Catch launch mistakes before your clients do.

Check a client site: uselaunchready.com Don't launch broken.

Client Website Handover & Launch-Day Runbook

uselaunchready.com · 10 / 10