Measure T 2022 Biennial Report

Page 1

Measure T 2022 Report.indd 1 5/25/2023 3:45:17 PM
Measure T 2022 Report.indd 2 5/25/2023 3:45:17 PM

ITOC MEMBERS

Municipal Audit, Finance and/or Budgeting

Pamela Kindig, Chair

Members At-Large

Chuck McMinn, Vice Chair

Richard Tippett

Licensed Civil Engineer

Robert Peterson

Certified Public Accountant

Kevin Alfaro

Chamber of Commerce

Valerie Zizack-Morais

Taxpayer Association

Jill Barwick

EX-OFFICIO MEMBERS

NVTA-TA Chair

Liz Alessio

NVTA-TA Executive Director

Kate Miller

Napa County AuditorController

Tracy Schulze

TAC Chair

Rosalba Ramirez

Letter from the Chair of the Independent Taxpayer Oversight Committee

Dear Napa Taxpayers and Fellow Community Members:

It has been a pleasure to serve as the chair of the Independent Taxpayer Citizens Oversight Committee since its inception in 2018. I have enjoyed my life as a public servant, including my years as Napa County’s AuditorController. My career has been governed by transparency and financial accountability, and keeping the transparency and accountability going is my role as ITOC chair.

Measure T is a half-cent sales tax that improves local streets, roads, sidewalks, ADA ramps, curbs, and gutters. It is expected to generate about $500 million over 25 years. Napa County, the Town of Yountville, and the Cities of Napa, American Canyon, St. Helena, and Calistoga first received Measure T revenue in January 2019. Measure T was passed by voters in Napa County in 2012; the ballot measure also created an Independent Taxpayer Oversight Committee (ITOC), which is the citizen oversight committee that helps ensure transparency of this local sales tax revenue.

Citizen oversight committees provide the opportunity for citizens to take an active part in their government and its direction. The ITOC is made up of people who want to make sure that the Napa Valley Transportation Authority is on the right course and spending its tax revenue to reflect what was voted on by the taxpayers. We are often looking for more citizens to get involved. Please go to https://nvta.ca.gov/programs/itoc/ to learn about ITOC member opportunities.

As we continue to recover economically from the pandemic, I’d like to remind my fellow Napans when you shop in Napa Valley, Napa Valley benefits. Every time we spend money in Napa County, the tax revenue goes right back to our community. It goes to improving roads and reducing wear on vehicles; to bike lanes so that people can more safely enjoy alternative transportation or outdoor recreation; and to better sidewalks so kids and families can safely walk to school.

Sincerely,

1
Measure T 2022 Report.indd 1 5/25/2023 3:45:17 PM

NVTA BOARD MEMBERS

City of American Canyon

Mayor Leon Garcia

Mark Joseph, Vice Chair

City of Calistoga

Mayor Donald Williams

Kevin Eisenberg

City of Napa

Mayor Scott Sedgley

Liz Alessio, Chair

County of Napa

Alfredo Pedroza

Ryan Gregory

City of St Helena

Mayor Paul Dohring

Anna Chouteau

Town of Yountville

Mayor Marjorie A. Mohler

Eric E. Knight

Paratransit Coordinating Council

Tom Collette

NVTA

Kate Miller Executive Director

Letter from the NVTA Board of Directors Chair

Dear Napa County Residents:

As a Napa native, I grew up with the small-town charm of a quiet but bustling hub for world-class agriculture, great schools, and unmatched outdoor activities. So much of Napa’s small-town vibes are in the seemingly small things like walking or biking to work, kids being able to safely get to school, or exploring the Valley’s hidden (and not-so-hidden) treasures through a safe network of streets and roads. These seemingly small things are anything but small.

In Napa County, Measure T allows us as taxpayers to reinvest in ourselves. Every time we buy groceries, dine out, or shop locally, we are sending tax revenue right back into our community. Every penny generated goes to those seemingly small projects like better roads and safer bike and pedestrian infrastructure.

Measure T projects can cost anywhere from the tens of thousands to millions of dollars. Of course, these projects don’t magically appear overnight, either. Measure T generates jobs within our community. The workers who work on these transportation projects are local. From people to projects, there is no corner of Napa Valley that Measure T doesn’t touch.

Over the past two years since the last Measure T Report, we have repaired over 10 miles of road and over 7,000 feet of sidewalks, and installed or replaced over 28 ADA curb ramps, throughout the County.

I am especially grateful to the Independent Tax Oversight Committee members who provide their expertise in accounting and finance, so that NVTA can remain transparent and on track to deliver these important transportation projects to make life in Napa Valley even better.

Sincerely,

2
Measure T 2022 Report.indd 2 5/25/2023 3:45:17 PM
3 Measure T 2022 Report.indd 3 5/25/2023 3:45:18 PM

MEASURE T FUNDS PROJECT STATUS

4
Jurisdiction Project Name Project City of American Canyon James Rd: Crawford Way to Donaldson Way W $537,330 City of American Canyon James Rd: W American Canyon Rd to Crawford Way 605,924 City of American Canyon Folland Dr: Elliott Dr to Danrose Dr 201,894 City of American Canyon Blanco St: Marla Dr to Capra Dr 176,331 City of American Canyon Corsicana Dr 88,165 City of American Canyon Brophy St 176,331 City of American Canyon Eucalyptus Sidewalk Gap Closure 175,000 City of American Canyon Kemp Ln 41,411 City of American Canyon Kemp Way 41,411 City of American Canyon Sheffield Way 82,822 City of American Canyon Folland Dr: Danrose Dr to Corbin Dr 105,695 City of Calistoga Harley St: Fair Way to Grant St N/A City of Calistoga FY 21/22 Design: Cedar St, Berry St, and Washington St Pavement Projects N/A City of Napa Westwood Neighborhood Rehabilitation Phase 2a: Bremen Ct and Bancroft Ct $305,173 City of Napa Trancas St Rehabilitation $3,672,206 City of Napa Trower Ave Rehabilitation Phase 2 $582,391 City of Napa Lincoln Ave and Main St: Traffic Signal Project $845,169 City of Napa Soscol Ave Rehabilitation: Central Ave to La Homa Dr $1,594,000 City of Napa Paving Program. Courts: Stiles, Calvary, Clement, Jacqueline, Gordon, Kingford, Caber, Exeter. Streets: Clifford, St. Francis Cir., Grandview, Hilton, Stallings, Summerfield, Manchester, Hyde Park, Darling $1,485,818 City of Napa ATMS: Jefferson St Corridor: Clairemont Way to Third St $835,000 City of Napa West Lincoln Ave: Lone Oak Ave to Solano Ave/Highway 29 $150,000 City of Napa Coombs St and South Coombs: 5th St to West Imola Ave $150,000 City of Napa Laurel Street Phase 1: First St to Griggs Ln $3,150,000 City of Napa Jefferson St: Trower Ave to Sierra Ave $2,500,000 City of Napa Coombsville Rd: 3rd St/Silverado Trail to Pascale Pl $150,000 City of Napa Coombsville Rd: Pascale Pl to East End $150,000 City of Napa Browns Valley Rd: Westview Dr to Highway 29/Freeway Dr $1,150,000 City of Napa Westwood Neighborhood Streetlights: Phase 3 Interior Streets $1,500,000 City of Napa Westwood Neighborhood Streetlights: Laurel St to Freeway Dr $100,000 City of St. Helena R19-79 Pavement Restoration: Kearney St from Pine St to Adams St $89,847 City of St. Helena R19-05 Rehabilitation: Grayson Ave and South Crane Ave $132,570 City of St. Helena R19-05 Grayson and South Crane Rehabilitation: South Crane Ave from Sulphur Springs Ave to Grayson Ave $132,570 County of Napa Berryessa/Knoxville Rd: MPM 20.5-22 Storm Damage Repair, Northeast Napa County $930,638 County of Napa Dry Creek Rd MPM 7.75: Storm Damage Repair, Southwest Napa County $525,729 County of Napa Dry Creek Rd MPM 10.5: Storm Damage Repair, Southwest Napa County $697,929 County of Napa Dry Creek Rd MPM 10.75: Storm Damage Repair, Southwest Napa County $591,383 County of Napa Mt Veeder Rd MPM 4.75: Storm Damage Repair, Southwest Napa County $1,544,884 County of Napa Dry Creek Rd MPM 7.51: Storm Damage Repair, Southwest Napa County $740,263 County of Napa Mt Veeder Rd MPM: 4.0 Storm Damage Repair, Southwest Napa County $856,882 County of Napa Mt Veeder Rd MPM 5.1 $1,624,646 County of Napa Airport Blvd: Hwy 29 to Airport Rd $4,775,524 Measure T 2022 Report.indd 4 5/25/2023 3:45:18 PM
5 Project Cost Measure T Funds Other Funds Start Date End Date Project Status $537,330 $537,330 September 2020 December 2020 Completed 605,924 605,924 September 2020 December 2020 Completed 201,894 201,894 Summer 2022 March 2023 In Progress 176,331 176,331 Summer 2022 March 2023 In Progress 88,165 88,165 Summer 2022 March 2023 In Progress 176,331 176,331 Summer 2022 March 2023 In Progress 175,000 175,000 Summer 2022 March 2023 In Progress 41,411 41,411 Summer 2022 March 2023 In Progress 41,411 41,411 Summer 2022 March 2023 In Progress 82,822 82,822 Summer 2022 March 2023 In Progress 105,695 105,695 Summer 2022 March 2023 In Progress N/A 12,444 August 2020 September 2020 Completed N/A 8,450 July 2021 TBD In Progress $305,173 $305,173 December 2020 July 2021 Completed $3,672,206 $3,672,206 August 2019 December 2021 Completed $582,391 $582,391 July 2018 October 2021 Completed $845,169 $845,169 Fall 2020 November 2021 Completed $1,594,000 1,594,000 Winter/Spring 2020 January 2022 Completed Exeter. Hyde $1,485,818 $1,485,818 July 2021 Winter 2021 Completed $835,000 $835,000 Fall 2019 Summer 2022 In Progress $150,000 $150,000 TBD TBD In Progress $150,000 $150,000 Summer 2021 Summer 2024 In Progress $3,150,000 $3,150,000 Summer 2021 Summer 2023 In Progress $2,500,000 $2,500,000 Fall 2021 Spring 2023 In Progress $150,000 $150,000 Fall 2021 TBD In Progress $150,000 $150,000 Fall 2021 TBD In Progress $1,150,000 $1,150,000 Fall 2021 Summer 2023 In Progress $1,500,000 $1,500,000 December 2020 TBD In Progress $100,000 $100,000 July 2021 TBD In Progress $89,847 $32,035 $57,812 March 2019 Fall 2020 In Progress $132,570 $132,570 June 2020 June 2024 In Progress Ave to $132,570 $132,570 June 2020 June 2023 In Progress $930,638 $860,024 $10,273 May 2020 July 2020 Completed $525,729 $484,614 $8,356 February 2019 August 2020 Completed $697,929 $656,227 $6,426 February 2019 August 2020 Completed $591,383 $540,039 $51,344 February 2019 September 2020 Completed $1,544,884 $1,491,667 $6,122 February 2019 August 2020 Completed $740,263 $697,332 $4,558 February 2019 August 2020 Completed $856,882 $835,669 $13,399 February 2019 September 2020 Completed $1,624,646 $1,606,646 $18,000 May 2021 October 2021 Completed $4,775,524 $4,775,524 December 2019 April 2022 Completed Measure T 2022 Report.indd 5 5/25/2023 3:45:18 PM

Town of Yountville Washington Park Paving Project: Foxglove, Lande to Forrester

Town of Yountville Washington Park Paving Project: Jasmine, Lande to Forrester

Town of Yountville Washington Park Paving Project: Lande Way, 29 Lande to Stags View

Town of Yountville Washington Park Paving Project: Mount Ave, Yount St to Jasmine

Town of Yountville Washington Park Paving Project: Redwood Dr, Lande to Forrester

Town of Yountville Washington St South Rehabilitation: Yount St to Oak Cir $607,607

Town of Yountville Washington St South Rehabilitation: Oak Cir to California Dr

Town of Yountville Washington St South Rehabilitation: California Dr to Champagne

Town of Yountville Washington St South Rehabilitation Champagne to Town Limits

6 Jurisdiction Project Name Project County of Napa Silverado L- Silverado Trail: Oak Knoll Ave to Hardman Ave $1,981,079 County of Napa Silverado M- Silverado Trail: Hardman Ave to Trancas Ave $1,887,128 County of Napa Buhman Bridge: Buhman Ave at Congress Valley Rd Intersection $1,634,633 County of Napa Salvador Ave: Big Ranch Rd to City Limits $50,000 County of Napa El Centro Ave: Big Ranch Rd to City Limits $50,000 County of Napa Dry Creek Rd: MPM 9.75 Storm Damage Repair $1,139,673 County of Napa Dry Creek Bridge: MPM 10 and 0.8 miles west of Mt Veeder Rd $2,282,111 County of Napa Dry Creek Rd: MPM 6.2 $1,384,295 County of Napa Dry Creek Rd: MPM 6.2 $924,830 County of Napa American Canyon Rd Paving: Flosden Rd to County Line $708,638 County of Napa Deer Park Seal: Hwy 29 to Silverado Trail $19,500 County of Napa Oak Knoll Seal: Hwy 29 to Silverado Trail $19,000 County of Napa Buhman Seal $20,000 County of Napa Old Sonoma Rd Seal: Hwy 121 to City Limits $17,000 County of Napa Big Ranch Seal: City Limits to Oak Knoll $13,500 County of Napa Congress Valley Seal: Old Sonoma to Buhman $5,000 County of Napa Old Sonoma Hwy Seal: Hwy 121 to Old Sonoma Rd $5,000 County of Napa Redwood Rd: MPM 5.76 $555,746 County of Napa Angwin Area Paving: Deer Park Rd (between Silverado Trail and Mund Rd) and Howell Mountain Rd (between White Cottage Rd and College Ave) $150,000 Town of Yountville Washington Park Paving Project: Forrester, Mount to End $389,574
Measure T 2022 Report.indd 6 5/25/2023 3:45:18 PM
7 Project Cost Measure T Funds Other Funds Start Date End Date Project Status $1,981,079 $1,292,079 $689,000 May 2020 February 2022 Completed $1,887,128 $1,887,128 May 2020 May 2022 Completed $1,634,633 $1,299,666 $334,967 August 2021 May 2022 Completed $50,000 $50,000 January 2020 October 2023 In Progress $50,000 $50,000 January 2020 October 2023 In Progress $1,139,673 $1,139,673 March 2021 October 2023 In Progress $2,282,111 $454,204 $1,827,907 July 2021 November 2024 In Progress $1,384,295 $1,384,295 December 2021 October 2022 In Progress $924,830 $924,830 August 2021 June 2023 In Progress $708,638 $698,581 $10,057 July 2022 August 2023 In Progress $19,500 $19,500 February 2022 Fall 2022 In Progress $19,000 $19,000 February 2022 Fall 2022 In Progress $20,000 $20,000 February 2022 Fall 2022 In Progress $17,000 $17,000 February 2022 Fall 2022 In Progress $13,500 $13,500 February 2022 Fall 2022 In Progress $5,000 $5,000 February 2022 Fall 2022 In Progress $5,000 $5,000 February 2022 Fall 2022 In Progress $555,746 $555,746 January 2022 October 2023 In Progress Mountain $150,000 $150,000 April 2022 August 2023 In Progress $389,574 $389,574 March 2021 July 2021 Completed $607,607 $525,000 $113,000 October 2021 March 2022 In Progress Measure T 2022 Report.indd 7 5/25/2023 3:45:18 PM
8 TRANSPORTATION Measure T 2022 Report.indd 8 5/25/2023 3:45:19 PM

MEASURE T FUNDING FLOW CHART

The funding flow chart illustrates how funds flow back to the sources for approved projects.

STATE OF CALIFORNIA

NAPA VALLEY TRANSPORTATION AUTHORITY

9
Measure T 2022 Report.indd 9 5/25/2023 3:45:20 PM

AMERICAN CANYON

JAMES ROAD CRAWFORD TO DONALDSON

JAMES ROAD RECONSTRUCTION

STATUS: COMPLETE

LOCATION: JAMES RD FROM CRAWFORD TO DONALDSON

ROAD SECTION LENGTH: 894 FEET

SIDEWALK LENGTH: 894 FEET

CURB RAMPS INSTALLED/REPLACED: 1

TOTAL PROJECT COST: $537,330

MEASURE T FUNDS: $537,330

PROJECT DESCRIPTION

Road reconstruction including pedestian and bicycle improvements.

10
Measure T 2022 Report.indd 10 5/25/2023 3:45:20 PM

AMERICAN CANYON

JAMES ROAD

CRAWFORD TO AMCAN RD W.

JAMES ROAD RECONSTRUCTION

STATUS: COMPLETE

LOCATION: JAMES RD FROM AMERICAN CANYON ROAD W TO CRAWFORD WAY

ROAD SECTION LENGTH: 903 FEET

SIDEWALK LENGTH: 903 FEET

CURB RAMPS INSTALLED/REPLACED: 7

TOTAL PROJECT COST: $605,924

MEASURE T FUNDS: $605,924

PROJECT DESCRIPTION

Road reconstruction including pedestian and bicycle improvements.

11
Measure T 2022 Report.indd 11 5/25/2023 3:45:20 PM

CALISTOGA

BERRY STREET

BERRY STREET IMPROVEMENTS

STATUS: COMPLETE

ROAD SECTION LENGTH: 1,030 FEET

SIDEWALK LENGTH: 100 FEET

CURB RAMPS INSTALLED/REPLACED: 7

TOTAL PROJECT COST: $566,410

MEASURE T FUNDS: $538,089

PROJECT DESCRIPTION

Berry Street improvements including overlay and pedestrian improvements.

12
Measure T 2022 Report.indd 12 5/25/2023 3:45:21 PM

HARLEY STREET OVERLAY

STATUS: COMPLETE

LOCATION: HARLEY STREET

ROAD SECTION LENGTH: 880 FEET

SIDEWALK LENGTH: 30 FEET

CURB RAMPS INSTALLED/REPLACED: 3

TOTAL PROJECT COST: $274,648

MEASURE T FUNDS: $248,878

CALISTOGA

HARLEY STREET

PROJECT DESCRIPTION

Overlay including pedestrian facility improvements.

Measure T 2022 Report.indd 13 5/25/2023 3:45:21 PM

CITY OF NAPA

TRAFFIC MANAGEMENT

JEFFERSON STREET TRAFFIC MANAGEMENT

STATUS: IN PROGRESS

LOCATION: CLAREMONT WAY TO THIRD STREET

ROAD SECTION LENGTH: N/A

TOTAL PROJECT COST: $835,000

MEASURE T FUNDS: $835,000

PROJECT DESCRIPTION

Advanced Traffic Management System (ATMS) on Jefferson Street in the City of Napa. ATMS is designed to provide control, monitoring, and traveler information in an effort to reduce traffic congestion, travel time, and accidents.

14
Measure T 2022 Report.indd 14 5/25/2023 3:45:21 PM

CITY OF NAPA

JEFFERSON STREET RESTORATION

STATUS: IN PROGRESS

BEGINNING LOCATION: TROWER AVENUE

END LOCATION: SIERRA AVENUE

ROAD SECTION LENGTH: 1,800 FEET

SIDEWALK LENGTH: 102 FEET

CURB RAMPS INSTALLED/REPLACED: 2

TOTAL PROJECT COST: TBD

MEASURE T FUNDS: $2,500,000

JEFFERSON STREET

PROJECT DESCRIPTION

Design work for improvements along Jefferson Street completed in 2022 with construction to begin in Summer 2023.

15
Measure T 2022 Report.indd 15 5/25/2023 3:45:21 PM

COUNTY OF NAPA

DEER PARK RD

OAK KNOLL ROAD

OLD SONOMA HWY

PAVING AND SEALING

STATUS: COMPLETE

LOCATIONS: VARIOUS ROADS IN

UNINCORPORATED NAPA COUNTY

ROAD SECTION LENGTH: 60,614 FEET

TOTAL PROJECT COST: $4,500,000

MEASURE T COST: $2,570,000

PROJECT DESCRIPTION

Pavement patching, crack seal, and cape seal along various unincorporated areas of Napa County, including Deer Park Road, Oak Knoll Road, and Old Sonoma Highway.

16
Measure T 2022 Report.indd 16 5/25/2023 3:45:22 PM

COUNTY OF NAPA SILVERADO TRAIL

HARDMAN AVE TO OAK KNOLL

SILVERADO TRAIL OVERLAY

STATUS: COMPLETE

LOCATION: SILVERADO TRAIL FROM HARDMAN AVE TO OAK KNOLL

ROAD SECTION LENGTH: 10,924 FEET

TOTAL PROJECT COST: $1,981,079

MEASURE T COST: $591,818

PROJECT DESCRIPTION

Overlay on Silverado Trail from Hardman Ave (just north of Trancas Ave) to Oak Knoll in the unincorporated area of Napa County.

17
Measure T 2022 Report.indd 17 5/25/2023 3:45:22 PM

CITY OF ST. HELENA*

*previously reported

VARIOUS STREETS

PAVEMENT RESTORATION AND ADA IMPROVEMENTS

STATUS: COMPLETE

LOCATION: VARIOUS STREETS IN ST. HELENA

ROAD SECTION LENGTH: 5,100 FEET

CURB RAMPS INSTALLED/REPLACED: 19

TOTAL PROJECT COST: $1,100,000

MEASURE T FUNDS: $1,100,000

PROJECT DESCRIPTION

Pavement restoration and ADA improvements on various streets in St. Helena.

18
Measure T 2022 Report.indd 18 5/25/2023 3:45:24 PM

CITY OF ST. HELENA*

*previously reported

CRINELLA NEIGHBORHOOD

PAVEMENT OVERLAY AND ADA IMPROVEMENTS

STATUS: COMPLETE

LOCATION: CRINELLA NEIGHBORHOOD

ROAD SECTION LENGTH: 4,752 FEET

SIDEWALK LENGTH: 45 FEET

CURB RAMPS INSTALLED/REPLACED: 17

TOTAL PROJECT COST: $940,000

MEASURE T COSTS: $940,000

PROJECT DESCRIPTION

Pavement overlay and ADA improvements in St. Helena’s Crinella subdivision.

19
Measure T 2022 Report.indd 19 5/25/2023 3:45:24 PM

TOWN OF YOUNTVILLE

WASHINGTON PARK

WASHINGTON PARK REHABILITATION

STATUS: COMPLETE

LOCATION: WASHINGTON PARK AREA ON MOUNT

AVE, FORRESTER LN, JASMINE ST, LANDE WAY, FOXGLOVE LN, AND REDWOOD DR.

ROAD SECTION LENGTH: 4,118 FEET

TOTAL PROJECT COST: $389,574

MEASURE T FUNDS: $389,574

PROJECT DESCRIPTION

Paving rehabilitation including asphalt repairs, including cold planing existing asphalt; hot mix asphalt paving, traffic striping, and lowering and adjusting utilities.

20
Measure T 2022 Report.indd 20 5/25/2023 3:45:25 PM

TOWN OF YOUNTVILLE

WASHINGTON STREET S.

WASHINGTON STREET SOUTH REHABILITATION

STATUS: COMPLETE

LOCATION: WASHINGTON STREET FROM YOUNT

STREET TO THE SOUTH TOWN LIMITS

ROAD SECTION LENGTH: 2,932

TOTAL PROJECT COST: $607,607

MEASURE T FUNDS: $525,000

PROJECT DESCRIPTION

Paving rehabilitation including asphalt repairs, including: cold planing existing asphalt; hot mix asphalt paving, traffic striping, lowering and adjusting utilities.

21
Measure T 2022 Report.indd 21 5/25/2023 3:45:25 PM
Published May 2023 Learn more at nvta.ca.gov/measure-t Measure T 2022 Report.indd 22 5/25/2023 3:45:26 PM