HENRY COUNTY SPLOST IV PROJECT STATUS UPDATE Ron Burckhalter, SPLOST Capital Projects Director and Roque Romero, SPLOST Director of Transportation BOARD OF COMMISSIONERS MEETING November 1, 2016


SPLOST IV – COUNTY WIDE PROJECT UPDATE


SPLOST IV – COUNTY WIDE 911 RADIO REPLACEMENT

Budget: $6,560,000.00 Status: In Progress Contract awarded to Harris Corporation 3/15/2016 Project 20% Complete Projected Completion January 2018


SPLOST IV – COUNTY WIDE

AMBULANCES (1-Remount/1-New) Budget: $326,529.00 Status: COMPLETE (1) Ambulance Remount Cost $100,214.00 Located at F.S. #13 (1) New Ambulance Cost $226,315.00 Located at F.S. #12

Ambulance Remount


SPLOST IV – COUNTY WIDE

ANIMAL CONTROL RENOVATION Budget: $100,000.00 Status: COMPLETE Cost: $98,167.00 Renovation items included: New digital security camera system. Epoxy wall coating in kennels, puppy room, and quarantine area. Additional fencing and new automatic gate. New interior doors.


SPLOST IV – COUNTY WIDE

FIRE STATIONS CAPITAL EQUIPMENT Budget: $2,153,471.00 Status: In Progress New Equipment for (3) New Fire Stations: Fire Station #14 (Luella) Fire Station #15 (N. Mt. Carmel) Fire Station #16 (Kelleytown) (3) New Fire Trucks – Ordered; Delivery Expected December 2016 (3) New Ambulances – (1) Received; (2) In Progress


SPLOST IV – COUNTY WIDE

FIRE STATION #14 (Luella Area) Budget: $2,235,000.00 Status: In Progress Location: 1875 Hampton Locust Grove Road, Locust Grove, GA Architect: The Howell Group of Marietta, GA Contractor: Tommy Gibson Builders of Warner Robbins, GA Construction 50% Complete. Estimated Completion January 2017.


Fire Station #14


SPLOST IV – COUNTY WIDE

FIRE STATION #15 (N. Mt. Carmel Area) Budget: $2,440,000.00 Status: In Progress Location: 325 N. Mt. Carmel Road, Hampton, GA Architect: The Howell Group Contractor: Headley Construction Construction 60% Complete. Estimated Completion April 2017.


Fire Station #15


SPLOST IV – COUNTY WIDE

FIRE STATION #16 (Kelleytown Area) Budget: $2,600,000.00 Status: In Progress Location: 1575 Kelleytown Road, McDonough, GA Architect: The Howell Group Contractor: Tommy Gibson Builders Construction Notice to Proceed issued. Estimated Completion September 2017.


SPLOST IV – COUNTY WIDE

HCDOT CONSTRUCTION EQUIPMENT Budget: $450,000.00 Status: COMPLETE Purchase of 2015 ROADTEC FB-100 Heavy Duty Front Mount Broom  Cost: $67,757.00 Purchase of (2) New 2017 International 7500 Dump Trucks Cost: $228,636.00 Purchase of (3) New 2016 Ford F250 Pick-Up Trucks Cost: $115,853.00


SPLOST IV – COUNTY WIDE JAIL RENOVATIONS

Budget: $1,500,000.00 Status: In Progress Pod B Renovation - COMPLETE Pod A Renovation – In Progress Renovation Items Include: New Surveillance Cameras. New Access Control System. Plumbing Renovation. Plumbing Fixture Upgrade. Epoxy Wall Coating in Shower/Toilet Area.


SPLOST IV – COUNTY WIDE NEW INTERCHANGE ON I-75

Budget: $5,500,000.00 Status: In Progress Engineers: Pond & Company Interchange Justification Report – In Progress Feasibility Study - COMPLETE


SPLOST IV – COUNTY WIDE

(30) POLICE PATROL VEHICLES Budget: $1,406,806.00 Status: COMPLETE Purchase of (30) Police Patrol Vehicles and Related Equipment Cost: $1,383,187.00


SPLOST IV – COUNTY WIDE SEWER TO AIRPORT

Budget: $2,000,000.00 Status: In Progress Design By: Henry County Water Authority HCWA Design In Progress.


SPLOST IV – COUNTY WIDE SEWER TO FAIRVIEW

Budget: 2,000,000.00 Status: In Progress Design By: Henry County Water Authority HCWA Design In Progress.


SPLOST IV – COUNTY WIDE PROJECT STATUS SUMMARY

13 of 17 County Wide Projects In Progress or COMPLETE – 76%


SPLOST IV - DISTRICT 1 PROJECT UPDATE Commissioner Bo Moss


SPLOST IV – DISTRICT 1

FIRE STATION #2 (Replacement) Budget: $2,360,000.00 Status: In Progress Location: 35 Frances Ward Drive, Locust Grove, GA Architect: The Howell Group Contractor: J.R. Bowman Construction Construction 75% Complete. Estimated Completion December 2016.


Fire Station #2


SPLOST IV – DISTRICT 1 TANGER BALL FIELDS

Budget: $550,000.00 Status: In Progress Location: 2951 Tanger Blvd., Locust Grove, GA Joint project with the City of Locust Grove Concession Bldg., Sports Lighting, Storage/Meeting Bldg., and Fencing COMPLETE. Parking Lot Design COMPLETE.


SPLOST IV - DISTRICT 1

MAJOR TRANSPORTATION (2 of 3 In Progress) McDonough Parkway (Henry Connector) Budget: $5,000,000.00 Status: Right of Way Acquisition In Progress Engineer: Heath & Lineback Engineers

SR81 Widening (Lemon to Bethany) D1 Budget: $750,000.00 (50/50 Shared Cost w/District 3)  ARC Design Contribution up to $1.2M Status: Design In Progress Engineer: Moffatt & Nichol


McDonough Parkway (Henry Connector)


SPLOST IV - DISTRICT 1

INTERSECTION IMPROVEMENTS (3 of 3 In Progress or COMPLETE)

Locust Road/Jackson Street @ SR42 Status: COMPLETED by GDOT

South Bethany @ Old Jackson Budget: 1,000,000.00 Status: Final Plans In Progress Engineer: AECOM

SR81 @ Mt. Bethel/Wynn (50/50 Shared Cost w/District 3) District 1 Cost: $505,804.00 Status: COMPLETE


SPLOST IV - DISTRICT 1

DIRT ROADS (5 of 5 In Progress or COMPLETE) Harris Drive (Leguin Mill Road to South Bethany Road) Cost: $1,849,700.00 Status: COMPLETE

Lester Mill Road (Hampton L.G. to Indian Creek) Budget: $2,843,250.00 Status: Construction Bid Opened 10/18/2016 Contractor: TBD


Harris Drive


SPLOST IV - DISTRICT 1

DIRT ROADS (Continued) Peeksville Road (New Hope to Bridge) Budget: $1,200,000.00 Status: Design In Progress Engineer: Heath & Lineback

Peeksville Road (Bridge to Old Jackson) Design Only Budget: $300,000.00 Status: Design In Progress Engineer: Heath & Lineback

Weems Road (Hampton LG to End) Surface Treatment Cost: $78,243.00 Status: COMPLETE


SPLOST IV – DISTRICT 1

BRIDGE IMPROVEMENTS (5 of 5 In Progress) King Mill over Tussahaw Creek (Culvert Repair) Budget: $150,000.00 Status: Construction In Progress Contractor: Baldwin Paving

Locust Grove over Indian Creek (Bridge Repair) Budget: $75,000.00 Status: Construction In Progress Contractor: Baldwin Paving

Jackson Lake over Mackey Creek (Bridge Replacement) District 1 Budget: $456,750.00 (1/3 Cost – District 1)(2/3 Cost – District 3) Status: Construction In Progress Contractor: Georgia Bridge & Concrete


SPLOST IV – DISTRICT 1

BRIDGE IMPROVEMENTS (Continued) Old Jackson over Tussahaw Creek (Bridge Repair) Budget: $25,000.00 Status: Construction In Progress Contractor: Baldwin Paving

South Ola over Tussahaw Creek (Bridge Repair) Budget: $150,000.00 Status: Construction In Progress Contractor: Baldwin Paving


SPLOST IV – DISTRICT 1

RESURFACING, WIDENING OR SURFACE TREATMENT 13 COMPLETE Amber Court Davis Lake Road Ellistown Road Ingram’s Lane Leguin Lane Luella Road (East of SR155) Luella Road (West of SR155)

Makayla Drive McCart Road Peeksville Road Sandy Ridge Road Trestle Road Weems Road


Davis Lake Road - Surface Treatment


SPLOST IV – DISTRICT 1

PROJECT STATUS SUMMARY 2 of 3 Capital Projects In Progress – 67% 15 of 16 Transportation Projects In Progress or COMPLETE – 94% NOTE: Excludes (13) Resurfacing/Surface Treatment projects that are COMPLETE.


SPLOST IV - DISTRICT 2 PROJECT UPDATE


SPLOST IV – DISTRICT 2

SENIOR/RECREATION CENTER Budget: $4,000,000.00 Status: In Progress Location: 56 McDonough Street, Hampton, GA Architect: Flynn, Finderup Architects Contractor: Meja Construction Construction 75% Complete. Estimated Completion January 2017.


Hampton Senior Center & Recreation Center


SPLOST IV – DISTRICT 2

INTERSECTION IMPROVEMENTS (5 of 6 In Progress) Industrial Parkway @ SR20 Budget: $500,000.00 (Joint Project with GDOT) Status: Right of Way Acquisition In Progress

Jodeco Road @ Blackhall Road Budget: $739,924.00 (Joint Project with GDOT) Status: Right of Way Acquisition In Progress

Mill @ SR81 Budget: $1,250,000.00 Status: Right of Way Acquisition In Progress Engineer: AECOM


SPLOST IV – DISTRICT 2

INTERSECTION IMPROVEMENTS (Continued) Mt. Carmel @ Chambers Budget: $1,000,000.00 Status: Construction Bid Opened 10/18/2016 Contractor: TBD

Simpson Mill @ Hampton-L.G. Budget: $620,000.00 Status: Preliminary Design In Progress Engineer: AECOM


Mt. Carmel @ Chambers


SPLOST IV – DISTRICT 2

DIRT ROADS (10 of 10 In Progress or COMPLETE) Amah Lee (Old SR3 to End of Pavement) Budget: $390,000.00 Status: Final Design In Progress Engineer: Wolverton & Associates

Farmer Drive (Surface Treatment) Cost: $24,988.00 Status: COMPLETE

Fields Drive (Surface Treatment) Cost: $20,686.00 Status: COMPLETE


SPLOST IV – DISTRICT 2

DIRT ROADS (Continued) Floyd Road (Surface Treatment) Cost: $9,085.00 Status: COMPLETE

Jones Road (Surface Treatment) Cost: $44,776.00 Status: COMPLETE

Mt. Olive Road (Jonesboro to End of Pavement) Cost: $55,472.00 Status: COMPLETE


SPLOST IV – DISTRICT 2

DIRT ROADS (Continued) Selfridge Road (Speedway Blvd. to Airport Entrance) Budget: $850,000.00 Status: Preliminary Design In Progress Engineer: Wolverton & Associates

South Cleveland Church (New Morn to Stone Road) Budget: $862,000.00 Status: Preliminary Design In Progress Engineer: Wolverton & Associates

South Mt. Carmel (Surface Treatment) Cost: $17,529.00 Status: COMPLETE


SPLOST IV – DISTRICT 2

DIRT ROADS (Continued) Thoroughbred Drive (Greenwood Road to End of Pavement) Budget: $507,000.00 Status: Final Design In Progress Engineer: Wolverton & Associates


SPLOST IV – DISTRICT 2

BRIDGE IMPROVEMENTS (5 of 5 In Progress) Blackhall over Rum Creek (Bridge Replacement) Budget: $300,000.00 (Joint Project with GDOT) Status: Design In Progress - GDOT

Hampton over Indian Creek (Culvert Repair) Budget: $198,281.00 Status: Construction In Progress Contractor: Baldwin Paving

Hampton over Towaliga River (Bridge Repair) Budget: $168,000.00 Status: Construction In Progress Contractor: Baldwin Paving


SPLOST IV – DISTRICT 2

BRIDGE IMPROVEMENTS (Continued) Jonesboro over Walnut Creek (Bridge Repair) Budget: $58,719.00 Status: Construction In Progress Contractor: Baldwin Paving

Old SR3 over Norfolk Southern RR (Bridge Repair) Budget: $80,000.00 Status: Construction In Progress Contractor: Baldwin Paving


SPLOST IV – DISTRICT 2

RESURFACING, WIDENING OR SURFACE TREATMENT 24 COMPLETE Arnold Road Chambers Road

Lake Talmadge Dam Lower Woolsey Road

David Road Dillion Drive Gold Leaf Drive

Manley Drive Meadow Trail Norfolk Drive

Falls Court

North Drive


SPLOST IV – DISTRICT 2

(Continued)

RESURFACING, WIDENING OR SURFACE TREATMENT Oakridge Court Oak Trail Pates Lake Court Pates Lake Cove Pates Lake Drive Pates Lake Way

Portsmouth Avenue Shoreline Way Simpson Mill Road South Drive Tidewater Avenue Water Oaks Court


Simpson Mill Resurfacing


SPLOST IV – DISTRICT 2

PROJECT STATUS SUMMARY 1 of 2 Capital Projects In Progress – 50% 20 of 23 Transportation Projects In Progress or COMPLETE – 87% NOTE: Excludes (24) Resurfacing/Surface Treatment projects that are COMPLETE.


SPLOST IV - DISTRICT 3 PROJECT UPDATE Commissioner Gary Barham


SPLOST IV – DISTRICT 3

HERITAGE PARK IMPROVEMENTS Budget: $25,000.00 Status: COMPLETE Cost: $21,437.00 Improvements Included: Steps with handrails from upper parking lot to Military Museum and crosswalk. Sidewalk with handrails to Veteran’s Wall of Honor.


SPLOST IV – DISTRICT 3

JASON T. HARPER ARENA IMPROVEMENTS Budget: $1,500,000.00 Status: In Progress Architect: Southern A&E Design to Enclose the Arena - COMPLETE Permitting In Progress. Cost Estimate In Progress.


SPLOST IV – DISTRICT 3 NORTH OLA PARK

Budget: $1,500,000.00 Status: In Progress New 3-4 Year Old T-Ball Field COMPLETE Purchased BOE property behind Ola Elementary, south of the park, for park expansion Concept Design for (4) additional ball fields COMPLETE. New Parking Lot Addition In Progress Design COMPLETE. Construction In Progress.  115 Additional Spaces


SPLOST IV – DISTRICT 3

MAJOR TRANSPORTATION (2 of 2 In Progress) McDonough Parkway (SR42 to SR155)

Budget: $2,827,000.00 Status: Final Design In Progress Engineer: Kimley-Horn SR81 Widening (Lemon to Bethany) D3 Budget: $750,000.00 (50/50 Shared Cost w/District 1)  ARC Design Contribution up to $1.2M Status: Concept Design In Progress Engineer: Moffatt & Nichol


McDonough Parkway (SR42 to SR155)


SPLOST IV – DISTRICT 3

INTERSECTION IMPROVEMENTS (7 of 9 In Progress OR COMPLETE)

Bethany Road @ SR81 Status: Completed by GDOT

Campground Road @ SR155 Budget: $600,000.00 Status: Right of Way Acquisition In Progress Engineer: AECOM

Dailey Mill @ Jodeco Road Budget: $250,000.00 Status: Construction In Progress Contractor: CMES


SPLOST IV – DISTRICT 3

INTERSECTION IMPROVEMENTS (Continued) East Lake @ SR20 District 3 Budget: $1,121,966.00 (50%/50% Shared Cost w/District 4) Status: Construction In Progress Contractor: Baldwin Paving

Jodeco Road @ Oak Grove Road Budget: $303,000.00 Status: Construction In Progress Contractor: CMES


East Lake @ SR20


SPLOST IV – DISTRICT 3

INTERSECTION IMPROVEMENTS (Continued) Lake Dow/Rodgers @ Rosser Budget: $1,500,000.00 Status: Construction In Progress Contractor: Southeastern Site Development

SR81 @ Mt. Bethyl/Wynn (50/50 Shared Cost w/District 1) District 3 Cost: $506,431.00 Status: COMPLETE


SR81 @ Mt. Bethel/Wynn (D1/D3)


SPLOST IV – DISTRICT 3

DIRT ROADS (6 of 7 In Progress or COMPLETE) Butler’s Bridge Drive (Surface Treatment) Cost: $52,904.00 Status: COMPLETE

Candler Road (Surface Treatment) Cost: $31,176.00 Status: COMPLETE

East Knight Road (Surface Treatment) Cost: $30,348.00 Status: COMPLETE


SPLOST IV – DISTRICT 3

DIRT ROADS (Continued) Eskew Road (Surface Treatment) Cost: $37,419.00 Status: COMPLETE

Turner Church Road (East of Bridge to SR20) Budget: $1,802,000.00 Status: Right of Way Acquisition In Progress Engineer: Pond & Co.

Turner Circle (Surface Treatment) Cost: $26,832.00 Status: COMPLETE


SPLOST IV – DISTRICT 3

BRIDGE IMPROVEMENTS (4 of 4 In Progress) Dailey Mill over Walnut Creek (Bridge Repair) Budget: $235,103.00 Status: Construction In Progress Contractor: Baldwin Paving

Elliott over Walnut Creek Tributary (Bridge Repair) Budget: $300,000.00 (Joint Project with GDOT) Status: Design In Progress - GDOT


SPLOST IV – DISTRICT 3 BRIDGE IMPROVEMENTS (Continued) Jackson Lake over Mackey Creek (Bridge Replacement) District 3 Budget: $1,370,250.00 (2/3 Cost District 3)(1/3 Cost District 1) Status: Construction In Progress Contractor: Georgia Bridge & Concrete

Oak Grove over Walnut Creek (Bridge Repair) Budget: $403,331.00 Status: Construction In Progress Contractor: Baldwin Paving


SPLOST IV – DISTRICT 3

RESURFACING, WIDENING OR SURFACE TREATMENT 29 COMPLETE Airline Road Brookdale Court Chardonnay Oaks Drive Charming Court Clearview Circle Compton Court Country Meadows

East Lake Road (50/50 Shared w/D4) Fir Drive Foster Drive Jodeco Road (50/50 Shared w/D4) Juniper Drive Lakehaven Parkway Millbrook Way Millstone Court


East Lake Resurfacing


SPLOST IV – DISTRICT 3 (Continued) RESURFACING, WIDENING OR SURFACE TREATMENT Overlook Drive Pinecone Court Post Oak Ridge Rosser Road Rowan Drive Saxony Court Sherwood Court

Sherwood Loop Silver Tip Court Spruce Drive Whispering Pines Lane Wood Valley Drive Wynnfield Blvd. Wynnfield Way


SPLOST IV – DISTRICT 3

PROJECT STATUS SUMMARY 3 of 3 Capital Projects In Progress – 100% 19 of 22 Transportation Projects In Progress or COMPLETE – 86% NOTE: Excludes (29) Resurfacing/Surface Treatment projects that are COMPLETE.


SPLOST IV - DISTRICT 4 PROJECT UPDATE Commissioner Blake Prince


SPLOST IV – DISTRICT 4 BUD KELLEY PARK

Budget: $2,750,000.00 Status: COMPLETE Location: 1605 Kelleytown Road, McDonough, GA Design/Build Firm: Sports Turf 124 Acre Passive Park 2+ Miles of Walking Trails (1) 30’x60’ Pavilion with Serving Window & Tables (2) 20’x40’ Pavilions with Picnic Tables Large Playground with Rubber Surface at ADA Areas 20’x40’ Shade Structure with (6) Fitness Elements


Bud Kelley Park


SPLOST IV – DISTRICT 4

MAJOR TRANSPORTATION (1 of 2 In Progress) Rock Quarry Road Widening Budget: $300,000.00  ARC Design Contribution up to $1.2M Status: Concept Design In Progress Engineer: Croy Engineering


SPLOST IV – DISTRICT 4

INTERSECTION IMPROVEMENTS (4 of 4 In Progress or COMPLETE)

Banks Road @ Rock Quarry Road Cost: $559,401.00 Status: COMPLETE

East Lake Road @ SR20 Budget: $1,121,566.00 (50%/50% Shared Cost w/District 3) Status: Construction In Progress Contractor: Baldwin Paving


SPLOST IV – DISTRICT 4

INTERSECTION IMPROVEMENTS (Continued) Hemphill Road @ SR138 Budget: $2,342,000.00 Status: Construction Out for Bid in November

Moseley Road @ SR138 Status: COMPLETED by GDOT


SR138 @ Hemphill Road


SPLOST IV – DISTRICT 4

DIRT ROADS (1 OF 2 IN PROGRESS) Elliott Road (East Lake Drive to Crumbley Drive) Budget: $2,272,000.00 Status: Final Design In Progress Engineer: Wolverton & Associates


SPLOST IV – DISTRICT 4 BRIDGE IMPROVEMENTS (3 of 3 In Progress) Hemphill over James Creek (Bridge Repair) Budget: $100,000.00 Status: Construction In Progress Contractor: Baldwin Paving

Old Conyers over Big Cotton Indian Creek (Bridge Repair) Budget: $50,000.00 (50/50 Shared Cost w/District 5) Status: Construction In Progress Contractor: Baldwin Paving


SPLOST IV – DISTRICT 4 BRIDGE IMPROVEMENTS (Continued) Selfridge over Little Cotton Indian Creek (Bridge Replacement) Budget: $2,912,000.00 Status: Preliminary Design In Progress Engineer: AECOM


SPLOST IV – DISTRICT 4 RESURFACING, WIDENING OR SURFACE TREATMENT 5 IN PROGRESS Banks Road Crumbley Road Flat Rock Road Old Conyers Road Tie Street


SPLOST IV – DISTRICT 4 RESURFACING, WIDENING OR SURFACE TREATMENT 15 COMPLETE Earlygold Street East Lake Road (50/50 Shared w/D3) Elberta Street Holloway Road Jodeco Road (50/50 Shared w/D3) Kelleytown Woods Drive Kelleytown Woods Parkway Kelley Way

Maygold Street North Grove Court Pleasant Grove Circle Roseberry Road Sunhigh Street Woods Court Woods Lane


SPLOST IV – DISTRICT 4

PROJECT STATUS SUMMARY 1 of 2 Capital Projects COMPLETE – 50% 9 of 11 Transportation Projects In Progress or COMPLETE – 82% NOTE: Excludes (20) Resurfacing/Surface Treatment projects that are In Progress or COMPLETE.


SPLOST IV - DISTRICT 5 PROJECT UPDATE Commissioner Bruce Holmes


SPLOST IV – DISTRICT 5 NEW DISTRICT 5 PARK Budget: $6,850,000.00 Status: In Progress Location: 750 Fairview Road Ellenwood, GA Contractor: Sunbelt Builders Construction 90% Complete Estimated Completion November 2016 34+ Acre Community Park Event Lawn Interactive Fountain

Community Building (2) Multi-Use Sport Fields Concession/Meeting/Restroom/ Scoring Tower Building (1) 40’x60’ Pavilion w/Serving Window and Tables (2) 20’x40’ Pavilions w/Tables Walking Trails Fitness Circuit Playground


New District 5 Park


SPLOST IV – DISTRICT 5 COCHRAN PARK IMPROVEMENTS Budget: $600,000.00 Status: In Progress Location: 305 East Atlanta Road, Stockbridge, GA Improvements Include: New Sports Field Lighting. New Field Netting. New Scoreboards – COMPLETE.


SPLOST IV – DISTRICT 5

MAJOR TRANSPORTATION (2 of 3 In Progress) Anvil Block Road Widening Budget: $5,500,000.00 Status: Right of Way Acquisition In Progress Engineer: AECOM

West Village Parkway (Previously Known as West Panola) Budget: $4,238,639.00 Status: Final Design In Progress Engineer: McGee Partners


Anvil Block Road Widening


West Village Parkway (Previously West Panola)


SPLOST IV – DISTRICT 5

INTERSECTION IMPROVEMENTS (1 of 3 In Progress) East Atlanta @ Thurman & Flatrock Budget: $2,002,000.00 Status: Preliminary Design In Progress Engineer: Wolverton & Associates


SPLOST IV – DISTRICT 5 BRIDGE IMPROVEMENTS (2 of 2 In Progress) Old Conyers over Big Cotton Indian Creek (Bridge Repair) Budget: $50,000.00 (50/50 Shared Cost w/District 4) Status: Construction In Progress Contractor: Baldwin Paving

Stagecoach over Big Cotton Indian Creek (Bridge Repair) Budget: $25,000.00 Status: Construction In Progress Contractor: Baldwin Paving


SPLOST IV – DISTRICT 5

RESURFACING, WIDENING OR SURFACE TREATMENT 6 IN PROGRESS OR COMPLETE Awendaw Circle - COMPLETE Fairview Road – In Progress Orchard Road – In Progress Panola Road – In Progress Rex Road – In Progress Waverly Blvd. - COMPLETE


SPLOST IV – DISTRICT 5

PROJECT STATUS SUMMARY 2 of 2 Capital Projects In Progress – 100% 5 of 9 Transportation Projects In Progress – 56% NOTE: Excludes (6) Resurfacing/Surface Treatment projects that are In Progress or COMPLETE.


SPLOST IV PROJECT STATUS SUMMARY CAPITAL PROJECTS Total Projects: Projects COMPLETE: Projects In Progress:

TRANSPORTATION PROJECTS 28 6 15

75% of Capital Projects are COMPLETE or In Progress.

Total Projects: Projects COMPLETE: Projects In Progress:

82 17 53

85% of Transportation Projects are COMPLETE or In Progress. • NOTE: These numbers do not include any Resurfacing/Surface Treatment/Widening projects.