Skip to main content

CESA Aon Awards publication 2021

Page 14

Projects with a value between R50 million and R250 milion

Design and Construction of the Emoyeni Reservoir by Knight Piésold for eThekwini Municipality

COMMENDATION

T

he design and construction

movement joints in the structure. As this

of the Emoyeni Reservoir

was a very large concrete structure

was unique in that several

(100 m x 35 m x 8 m), the removal of

aspects in both areas

movement joints required careful modelling.

deviated from previous designs and

Furthermore, the previously utilised tapered

construction techniques.

wall width was changed to uniform walls.

Traditional structures incorporate several

The modelling of the structure showed

PROJECT TEAM Client: eThekwini Municipality Consulting Engineer: Knight Piésold Consulting Contractor: Afrostructures Occupational Health & Safety: Engelbrecht and Associates

movement joints to allow for movement

that the uniform walls performed better

and shrinkage of the concrete while still

as a propped cantilever with smaller crack

maintaining water-tightness. The client

width, and made the reinforcing designs at

This large structure was constructed in the

(eThekwini Municipality) had used this

the corners simpler and easier to construct.

heart of a high-income residential suburb

concept design for most of the existing

Construction joints were still required;

with very little working space and with

reservoirs in and around the Durban area.

however, the specification on these was

cognisance of issues such as noise

The problem with these designs is that they

given careful consideration and was closely

pollution, dust pollution and traffic

relied on the construction of the joints and

monitored during construction. Although

congestion. Furthermore, the existing

specifically the water bars to be undertaken

the steel quantity increased in order to

water storage system that was on-site

correctly. Any errors or movement of the

mitigate cracking, this cost was offset

needed to be operational throughout the

water bars during the concrete pours result

against the savings in water bars, as well

contract duration.

in the water-tightness being compromised.

as the decrease in construction duration

This has resulted in many of the existing

and the lower risk of leakage. These design

utilised on the walls was to pour the 8 m

reservoir developing leaks.

changes resulted in a structure that was

high walls in a single lift. This was done to

commissioned with zero leaks and a high

reduce the number of construction joints, as

quality of concrete.

well as the construction duration.

For this design, Knight Piésold decided on a different approach, doing away with the

12 C E S A A o n E n g i n e e r i n g E x c e l l e n c e Aw a r d s 2 0 2 1

One of the unique construction techniques


Turn static files into dynamic content formats.

Create a flipbook
CESA Aon Awards publication 2021 by 3S Media - Issuu