Exhibit 18: Alliance contributions to catalytic change, systems change and impact through India's PM-KUSUM scheme Contributing alliance partners Government of India, Rajasthan Energy Department, DISCOMs, private DRE developers, engineering, procurement and construction contractors, local landowners and farmers, agricultural cooperatives

Catalytic change Enhanced capacity and policy: Launch of land registration portal removed land aggregation bottlenecks

Enabling

Pipeline developed: 900 feeder-level solar plants (~5–6GW) in active pipeline with March 2026 deadline

Finance unlocked: Land portal unlocked ~3.5GW of prospective capacity, reflecting accelerated and expanded capital deployment

Pivotal

Systems change Enabling

Increased access: Feeder-level solarization users received ~5 extra hours/day of reliable power, enabling irrigation and enterprise in daylight

Enabling

Higher utilization: Users reported lower costs (64% decrease) and more time for other activities

Impact Improved livelihoods: Improved power access enabled income gains and better time use, particularly for women. Around half (51%) of farmers reported higher yields.

Reduced emissions: Acceleration in solar capacity (+0.36MW/day) and pump installations (+28.6/day) sped up carbon impacts; Rajasthan added roughly 183MW more installed capacity and 12,700 more solarized pumps than projected without Global Energy Alliance involvement.