FEDERALLY-FUNDED PROJECTS I-70 Corridor Improvements Phase 2: Woodlawn Ave. to Hwy. K Construction was substantially complete and open to traffic in June 2023. This project is a continuation of previous phases to improve the traffic flow through the Interstate 70 and Highway K/M interchange. The City obtained a total of $4,944,000 in outside funding to support this project from County & State funding sources.

Dardenne Greenway Connector Project This project will include the installation of a new Trailhead area and parking lot for bike and pedestrian users located along Dardenne Creek adjacent to Interstate 64/40. Path connectivity to existing path systems will be included along with a 12’ shared use path on the new bridge structure traversing Dardenne Creek. The City obtained a total of $3,664,500 in outside funding to support this project from State, Federal and Great Rivers Greenway funding sources.

25


Turn static files into dynamic content formats.

Create a flipbook
Engineering Department 2023 Annual Report by City of O'Fallon - Issuu