MetroBus construction report for October South of Patchway Brook
The new northbound bus lane was fully opened during the second week of October, following the completion of the final piece of work to install a pollution control chamber in the verge, close to Primrose Bridge. Traffic cones remain along the boundary of the on-road cycle lane on the southbound side, for the safety of workers who have been rectifying minor defects in the kerbing.
Great Stoke Roundabout
Carriageway works associated with the construction of the new southbound bus lane on Bradley Stoke Way were completed during the first week of October. Work on the footways in this area was completed in mid-October and was followed soon after by
the installation of street lighting columns in the verges. The final anti-skid road surfacing in this area remains to be completed (a 28-day settling period must be observed following the main surfacing) and this was due to be carried out as we went to press (week commencing 30th October). All work by Alun Griffiths on Bradley Stoke Way is due to be completed by mid-November. This will be followed by a 12-month defect-fixing period during which any issues will be dealt with as they arise.
MetroBus shelters
There is one remaining MetroBus shelter to be installed, on the northbound side of Bradley Stoke Way, just prior to Great Meadow Roundabout. This is scheduled
Your trusted electrical contractor serving Bristol & the surrounding area.
CALL TODAY
For Your FREE estimate Providing a comprehensive range of Domestic & Commercial Electrical services. Don’t be shocked when we turn up on time!
Domestic
Commercial
EV Charging
www.bradleystokeelectrical.co.uk T 0117 332 7200 E info@bradleystokeelectrical.co.uk Units 3-4 The Laurels, Cribbs Causeway, Bristol, BS10 7TT
The final push? Cones out again on Bradley Stoke Way, where it joins Great Stoke Roundabout – to facilitate the application of anti-skid surfacing
for installation during the final week of November. Work to “seal” the new MetroBus shelters, making them fully waterproof, has recently been started by Clearchannel, the firm responsible for installing the shelters.
Stoke Gifford By-Pass
Whilst the new road may appear more or less completed when viewed from either end (Parkway North Roundabout and the A4174 Ring Road), a MetroBus spokesperson has told the Journal that a number of significant tasks remain to be completed before the it can be opened. The bridge over Ham Brook was completed during the third week in October and Alun Griffiths has started to lay the road surface over the bridge and tie it in with the rest of the road that they have built. Once this has been completed, final landscaping will take place. In the coming weeks, Western Power Distribution will undertake work to provide metered power supplies to work the traffic signals at the Hambrook Lane and A4174 junctions, South Gloucestershire Council’s signals team will then install the signals along with the induction loops in the road that alert the signals to oncoming traffic. In the vicinity of the new bridge over the main railway line, near Kings Drive, Bristol
Water need to install two lengths of pipework through ducts in the bridge platform and connect these into the existing main on Curtis Lane. Once all the above tasks are completed, the road will undergo a safety audit. Subject to passing the audit, the road will be then be opened to general traffic. This is now likely to be in “late December or early January”.
New road sign at the southern end of Bradley Stoke Way, with destinations that will be reached via the new bypass temporarily painted over
Start of MetroBus services Asked by the Journal when MetroBus services are likely to start running through Bradley Stoke and along the new Stoke Gifford By-Pass, a MetroBus spokesperson said: “There is still no news to report regarding the operator of the Cribbs Causeway to Hengrove route or when services are likely to start.”