Short-Term Action Plan for GoG to Manage FCs from PPPs
Table A.2 Proposed PPP Projects for Stocktaking FC Project
Sector
Status of project (to be confirmed by GoG)
Meridian Port Services- MPS Tema Terminal Concession Tema Osonor Power Plant Cen Power (signed ECG) Asogle Power Plant (signed VRA) Teshie-Nungua desalination project. Asutsuare Treatment Plant Accra-Kumasi Dualization Accra-Tema Dualization Expatriate Identity Card PPP Project
Port
Signed in 2002/03
Power Power Power Water Water Roads Roads Other
Signed/Almost Signed Signed/Almost Signed Signed/Almost Signed Signed 2012 Negotiations in progress Negotiations in progress Negotiations in progress In progress
Source: World Bank data. Note: GoG = Government of Ghana; ECG = Electricity Company of Ghana; PPP = public-private partnership; VRA = Volta River Author
51