ACO Technologies - ACO Qmax Sitework & Instalation

Page 1

Uniclass L7315 + L2123

EPIC J3413

CI/SfB (52.5)

The most advanced drainage system of its kind ACO Qmax 速 Sitework and Installation

In6


ACO Qmax速 System

SITEWORK & INSTALLATION Contents

Sitework - general

3

Recommended installation

4

Offloading/handling/storing

7

ACO Qmax速 System

2


ACO Qmax® System

SITEWORK & INSTALLATION 2.0 Sitework – General 2.1 Installation Groups: ACO Qmax® is designed for use within all Installation Groups defined in BS EN 1433:2002. By varying the structure surround detail around the channel and in line with engineering guidelines, installation groups from pedestrian, through car parks, to airfields may be accommodated [from 3.5 tonne to 30 tonne wheel loads].

2.3 Reinforcement: Reinforcement of the concrete surround may be required for the higher load classes. Typically, any reinforcement in a concrete pavement would be continued through the concrete arches of the unique ACO Qmax® intake slot design. The reinforcement included in the ACO load test samples is detailed on Page 7, but the customer may choose to omit or increase reinforcement subject to the loading and ground conditions anticipated. Engineering advice may be necessary.

Group 1 (min. class A 15) Areas which can be used only by pedestrian and pedal cyclists Group 2 (min. class B 125) Footways, pedestrian areas and comparable areas, private car parks or car parking decks Group 3 (min. class C 250) Kerb sides and non-trafficked area of hard shoulders and similar; kerb units are always Group 3 Group 4 (min. class D 400) Carriageways of roads (including pedestrian streets), hard shoulders and parking areas for all types of road vehicles Group 5 (min. class E 600) Areas subjected to high wheel loads, e.g. ports and dock areas Group 6 (min. class F 600) Areas subjected to especially high wheel loads, e.g. aircraft pavements 2.2 Ground Conditions: The customer should ensure that the minimum dimensions of the concreted section are suitable for the existing ground conditions with respect to ground bearing and consolidation. Ground conditions will also determine whether side shuttering or temporary strutting of an excavation is required. Engineering advice may be necessary.

2.4 Test Load Certificates: ACO Qmax® 600 and ACO Qmax® 900 are both certified to Load Class D400, BS EN 1433: 2002. ACO Qmax® 900 has been independently load tested to Load Class F900 of BS EN 1433:2002. The in-situ load test was terminated without failure at a load of 92 tonnes with a recorded central deflection of the cover slab of 1.4mm. 2.5 Pavement Finishes: ACO Qmax® may be installed in concrete [car park, distribution centre, aircraft pavements]; asphalt [car park, highways] and block pavement [car park] finishes. A galvanised steel angle is supplied for Installation Groups 5 and 6 and for concrete pavements of Installation Groups 2, 3 and 4. For car parks a heel safe waterway inlet is provided pre-assembled to the channel sections.

Note: Due consideration, in the selection of Groups 1 to 3, must be given to the possibility of the channel being trafficked by construction vehicles and which therefore may require specifying to a higher Group.

3


ACO Qmax® System

SITEWORK & INSTALLATION Recommended installation of ACO Qmax® 600 and ACO Qmax® 900 Note: These general advice notes outline the principle of installing ACO Qmax®. They do not purport to represent every activity or sequence. These notes must be read with the Sitework and Installation notes.

Stage B: Support/Align DYWIDAG or similar. See Note B 4.0 Cross trench temporary Packing to maintain line support. See Note B 4.0 and level (thickness determined by falls to slot)

Engineering advice may be necessary concerning ground conditions; temporary support; concrete specification; reinforcement etc.

1. Top hung method: Concrete pavement

See Note B 1.0

Stage A: Excavation

Box-out in pavement

Pavement construction varies

See Note B 6.0

See Note A 1.0

y

Minimum 225mm See Note A 2.0 (z)

Trench depth See NOTE A1.0

x

See Note A 1.0

A 1.0 Excavate to the minimum dimensions: ACO Qmax 600 ACO Qmax® 900 ®

Width 0.8m 1.0m

Depth (to top of slot) 1.1m 1.4m

Allow extra excavation for working rooms; concrete blinding; trench support etc. where necessary. A 2.0 In accordance with BS EN 1433, the installation is as a drainage channel type M, with the following minimum dimensions:

B 2.0 Approximately 10mm of deviation [at the end of a 2m unit] from both the vertical and horizontal will still maintain a watertight joint. B 3.0 Where steel angles are fitted to the channel [Installation Groups 4, 5 or 6] the fishplate connection, at both ends, will also help to maintain level and lateral alignment of the channel. The fishplates are locked in position using the NYLOC M10 nuts provided. B 4.0 Offer temporary support beams across the excavation at centres to suit kentledge. Hang channels, through their arches under the inlet slot, from the cross beams. DO NOT HANG CHANNELS FROM THE STEEL ANGLES.

X Minimum 200mm

B 5.0 Pack and batten as required to maintain line and level.

Y (to minimum concrete height above invert) Qmax 900 Y = 1040mm; Qmax 600 Y = 740mm

B 6.0 Strut off channel collars (not from channel body) before first concrete pour.

Z Minimum 225mm A 3.0 Remove from the formation all loose material and make good any soft spots with an appropriate concrete mix.

4

B 1.0 Assemble channels in trench and connect spigot/socket with the 2 bolts supplied. Where required, ensure EPDM seal is fully located within the socket and tighten bolts until contact of moulded stops (on male collar). DO NOT OVERTIGHTEN.


ACO Qmax速 System

SITEWORK & INSTALLATION Stage C: Concrete Kentlege

D 3.0 Prior to final stage concreting ensure that the protective tape, supplied with the steel angles, is not damaged. Stage E: Final Pour

Max. 300 Min. 200

See notes E1.0 & E2.0

Joints, see note E3.0

Fabric reinforcement. See Note C 3.0 Construction Joint

See Note C 2.0

C 1.0 Provide kentledge appropriate to depth of concrete (minimum Strength Class C32/40). See note C 2.0

C 2.0 On the 2m unit only, a longitudinal line 200mm above the ACO Qmax速 600 channel invert and 300mm above the ACO Qmax速 900 channel invert, is moulded externally on both sides of the channel. DO NOT pour over this line but ensure the level of the pour is near this line in order to anchor the channel for subsequent pours. C 3.0 Steel fabric reinforcement [A393] may be required in top face of base for Installation Group 6 only [Airfields]. Engineering advice may be necessary.

E 1.0 Place concrete (minimum Strength Class C32/40 air entrained) to final level. Note that the concrete finish, and extent of trowelled falls to the inlet slot, are to specification by others. E 2.0 Ensure that concrete is placed and well compacted below the flats of the steel angles. E 3.0 Provide transverse saw cuts at approximate collar positions, at 4.0m centres, to a maximum depth of 100mm, (or install proprietary plastic joint former). Provide longitudinal expansion joints against adjacent slabs to specification of others.

Stage D: Reinforcement See Note D 3.0

Reinforcement varies. See Note D 2.0

D 1.0 Dismantle kentledge. D 2.0 Fix reinforcement. Note that reinforcement varies with installation Group as appropriate and should be designed by the customer taking note of the loadings and ground conditions anticipated. Engineering advice may be required. For reference, the reinforcement used in ACO Qmax速 load test samples is shown on page 7. (The samples were tested as blocks, with no ground support to their sides).

5


ACO Qmax速 System

SITEWORK & INSTALLATION Stage B: Install/Align

2. Concrete bedding method: Concrete pavement Note: Where this method is used, it is vital to ensure that the channels cannot float during any stage of the concrete pours.

Stage A: Excavation and bedding Minimum width See note A1.0

x

y

Steel fabric reinforcement See note A.1.0 See note A.5.0

Minimum 225mm See Note A 2.0 (z)

Concrete around feet only. See note B.4.0

Minimum 1.4m See note A.1.0

A 1.0 Excavate to the minimum dimensions: ACO Qmax速 600 ACO Qmax速 900

Width 0.8m 1.0m

Depth (to top of slot) 1.1m 1.4m

Allow extra excavation for working rooms; concrete blinding; trench support etc. where necessary. A.2.0 In accordance with BS EN 1433, the installation is as a drainage channel type M, with the following minimum dimensions: X Minimum 200mm Y (to minimum concrete height above invert) Qmax 900 Y = 1040mm; Qmax 600 Y = 740mm Z Minimum 225mm A.3.0 Remove from the formation all loose material and make good any soft spots with an appropriate concrete mix. A.4.0 Lay concrete base (minimum Strength Class C32/40). A.5.0 Steel fabric reinforcement [A393] may be required in top face of base for Installation Group 6 only (airfields).

6

B.1.0 Assemble channels in the trench and connect spigot/socket with the 2 bolts supplied. Where required, ensure EPDM seal is fully located within the socket and tighten bolts until contact of moulded stops (on male collar). DO NOT OVERTIGHTEN. B.2.0 Align the channel using a pipe laser or by other means. B.3.0 Where steel angles are fitted to the channel [Installation Group 4, 5 or 6] the fishplate connection, at both ends, will also help to maintain the level and lateral alignment of the channel. The fishplates are locked in position using the NYLOC M10 nuts provided. B.4.0 Pack the feet with some C32/40 concrete to establish correct line and level. Place a quantity of fresh concrete around the feet to hold the units in place. Ensure sufficient concrete to hold the units in place for the Stage C concrete pour, but do not put in excess concrete that might float the channels.


ACO Qmax® System

SITEWORK & INSTALLATION Offloading/handling/storing:

Stage C: Concrete 2nd pour C.1.0 On the 2m unit only, a longitudinal line 200mm above the ACO Qmax® 600 channel invert and 300mm above the ACO Qmax® 900 channel invert, is moulded externally on both sides of the channel. DO NOT pour over this line but ensure the level of the pour is near this line in order to anchor the channel for subsequent pours. Stage D: Reinforcement Concrete, see note E.1.0

Tape, see note D.2.0

Note - in all operations DO NOT STACK ON SPIGOT END

Offload channel units from delivery vehicle using long forks or slings as appropriate. DO NOT THROW channels off the vehicle. If craned DO NOT SUPPORT FROM STEEL ANGLES. Use the arches under the inlet slot. ACO Qmax® may be stored vertically [single stacked on socket end for the 2 metre channel] or horizontally. If stored externally for greater than 6 weeks protect from direct sunlight.

Joints, see note E.3.0

Reinforcement varies

Similarly protect from prolonged sub zero temperatures [-10°C]. Do not allow heavy material to be stacked on or against channels.

Reinforcement of ACO Load Test Samples D.1.0 Fix reinforcement. Note that reinforcement varies with Installation Group as appropriate. D.2.0 Prior to final stage concreting, ensure that the protective tape, supplied with the steel angles, is not damaged. Stage E: Concrete, final pour E.1.0 Place concrete (minimum Strength Class C32/40 air entrained) to final level. Note that the concrete finish and extent of trowelled falls to the inlet slot, are to specification by others. E.2.0 Ensure that concrete is placed and well compacted below the flats of the steel angles. E.3.0 Provide transverse saw cuts at approximate collar positions, at 4.0m centres, to a maximum depth of 100mm, (or install proprietary plastic joint formers). Provide longitudinal expansion joints against adjacent slabs, to specification by others.

The customer should determine the reinforcement required, if any, in the concrete surround. Engineering advice may be required. For reference, the following reinforcement was used by ACO in the test blocks for the load testing of the products to BS EN 1433. Load Class A15, B125 and C250. No reinforcement required. (It might nevertheless be sensible to continue any reinforcement in a concrete pavement over the channel and through the arches.) Load Class D400. T12 straight bars at 200mm centres across the channel (one through each arch) and T12 straight bars along the channel (one each side of the inlet arch and stopped at each channel joint). Load Class F900. A393 mesh in the concrete base under the channel. T16 U-Bar at 200mm centres over the top of the channel (one through each arch). T12 L-bars at 200mm centres down each side of the channel, from the top to a point below the widest part of the channel. T12 longitudinal bars to tie the other bars together. Further details of the reinforcement used by ACO in their test blocks can be provided.

7


ACO Qmax® System

LITERATURE FOR ACO QMAX®

ACO QMAX® SYSTEM

TECHNICAL DATA

HYDRAULICS & LEGISLATION

Call for literature or more information: 01462 816666

ACO Technologies plc

International Enquiries

ACO Business Park, Hitchin Road, Shefford, Bedfordshire SG17 5TE

Tel: +44 (0)1462 816666 Fax: +44 (0)1462 850957 e-mail: international@aco.co.uk website: www.aco.co.uk

Tel: 01462 816666 Fax: 01462 815895 e-mail Sales: customersupport@aco.co.uk e-mail Technical: draintechnical@aco.co.uk website: www.aco.co.uk

ACO Qmax® is a registered trademark of ACO Technologies plc. The Qmax® channel system is protected by patent and registered design rights. All intellectual rights are the property of ACO Technologies plc. Any infringement of these property rights will result in the appropriate legal action being taken. © August 2005 ACO Technologies plc. All reasonable care has been taken in compiling the information in this document. All recommendations and suggestions on the use of ACO products are made without guarantee since the conditions of use are beyond the control of the Company. It is the customer's responsibility to ensure that each product is fit for its intended purpose, and that the actual conditions of use are suitable. This brochure and any advice is provided by ACO Technologies plc (the Company) free of charge and accordingly on terms that no liability including liability for negligence will attach to the Company or its servants or agents arising out of or in connection with or in relation to this brochure or any such advice. Any goods supplied by the Company will be supplied solely upon its standard conditions of sale, copies of which are available on request. The Company's policy of continuous product development and improvement renders specifications liable to modification. Information provided in this brochure is therefore subject to change without prior notification.